This document is Addendum No. 3 for the Phase 2 Cell 7 Construction project at the Chaffee County Landfill in Salida, Colorado, issued by Sanborn, Head & Associates, Inc. on April 7, 2025. The addendum addresses a correction in the Schedule of Values (Bid Form) previously provided in Addendum No. 2, specifically noting that the subtotal equation did not initially include mobilization/demobilization costs. The addendum requires bidders to acknowledge receipt of this update in their proposal and includes a corrected Excel file with the revised schedule.

The addendum does not provide additional pricing details or funding information beyond the procedural correction to the bid form. The document is addressed to bidders and copies are distributed to Chaffee County representatives Don Reimer, Beth Helmke, and Shannon Wilcox, as well as Sanborn Head internal contacts Timothy Reed and Marcel Kozlowski. The file is associated with the larger Landfill Disposal Cell Construction project, which involves constructing a 6.6-acre disposal cell with specific geosynthetic liner system requirements, including a geosynthetic clay liner and high-density polyethylene geomembrane.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

1667 Cole Blvd., Bldg. 19, Suite 260

Lakewood, Colorado 80401

Re: Addendum No. 3 Phase 2 Cell 7 Construction Chaffee County Landfill Salida, Colorado

This Addendum shall be part of the Contract Documents for the Phase 2 Cell 7 Construction Projects at Chaffee County Landfill in Salida, Colorado. Please acknowledge receipt of this Addendum in your proposal.

Revised Schedule of Values (Bid Form) It was brought to our attention that the subtotal equation (Cell H19) in the Schedule of Values (Bid Form) provided as a part of Addendum No. 2 did not include mobilization/demobilization.

This addendum includes the corrected excel file that includes mobilization/demobilization.

We look forward to receiving your bids.

Very truly yours, SANBORN, HEAD & ASSOCIATES, INC.

Vittoria E. Zucchelli, E.I.T.

Project Manager

VEZ/MBK: vez cc: Don Reimer (Chaffee County) Beth Helmke (Chaffee County) Shannon Wilcox (Chaffee County) Timothy Reed (Sanborn Head) Marcel Kozlowski (Sanborn Head)

P:\6100s\6164.00\Source Files\Cell 7 Construction\Bid Package\Addenda\Addendum #3 - Revised Schedule of Values\20250407 CCLF Ph2 C7 Addendum No. 3.docx

To: BIDDERS April 7, 2025 File No. 6164.00