This is a site plan map/technical drawing showing the Crystal Springs Dam at Ash Meadows National Wildlife Refuge. The drawing depicts key infrastructure components including an inflow structure, siphon outlet works, erosion gullies, service spillway, emergency spillway, and the Upper Springs Diversion Ditch. The reservoir is labeled as Crystal Springs Reservoir with thick vegetation noted in approach channels.

The dam specifications listed in the notes indicate a length of 5000 feet, crest width of 22.5' to 25', upstream slope of ~4.0H:1V, and downstream slope of ~2.5H:1V. The drawing shows water flow patterns to the Lower Crystal Marsh and includes station markers along various points of the dam structure. A scale bar indicates measurements up to 1500 feet. The document appears to be Figure 4 from a larger set of technical drawings, dated August 2005, related to restoration work at the refuge.

View the file

Other files for this federal contract opportunity

Other files attached to NV ASH MEADOWS NWR CRY SPRNGS RESTORE, newest first.
File Type Posted
FINAL__UCS__EA__8-15-2013__USFWS-Reviewed_0002.pdf PDF
EA__Guidance__508-Compliant__Jan2025_0002.pdf PDF
FONSI__Template__508-Compliant__Jan2025_0002.pdf PDF
24_-_AMNWR__Attachments_List__Crystal_Springs__01-08-2025_0002.pdf PDF
RFI-Questions_and_Responses__01-08-2025_0002.pdf PDF
Sol_140FGA25R0003_Amd_0002.pdf PDF
EA__Template__508-Compliant__Jan2025_0002.pdf PDF
Sol_140FGA25R0003_Amd_0001.pdf PDF
B08_-_Solicitation_Cover_Form_(140FGA25R0003)_0001.pdf PDF
B08_-_Solicitation_(140FGA25R0003_Sections_B-M)_0001.pdf PDF
23_-_190102__Ash_Meadows_NWR__Inventory_Assessment_Memorandum.pdf PDF
16_-_Map_4__EC_Values_Connectivity.pdf PDF
19_-_Nevada_Dept__of_Wildlife__Letter_of_Support.pdf PDF
2_-_AMNWR__Subcontract_List__Crystal_Springs__06-12-2024.pdf PDF
1_-_AMNWR__Proposal_Schedule__Crystal_Springs__06-12-2024.pdf PDF
4_j__-_Crystal_Springs_Restoration_Plan.pdf PDF
9_-_Pre-Work_Safety_Checklist.pdf PDF
11_-_360_FW1__Summary_of_Construction_Permits.pdf PDF
13_-_Map_1__Location.pdf PDF
21_-_2018__Dam_Safety_Inspection_Letter_for_Crystal_Springs.pdf PDF
Sol_140FGA25R0003.pdf PDF
24_-_AMNWR__Attachments_List__Crystal_Springs.pdf PDF
3_-_AMNWR__Statement_of_Work__Crystal_Springs__06-12-2024.pdf PDF
4_a__-_AMNWR__Project_Nomination__Crystal_Springs_Outflow__Edited.pdf PDF
4_d__-_AMNWR__Horseshoe_Dam_Report.pdf PDF
4_g__-_PFAS_Summary.pdf PDF
12_-_360_FW4__Construction_Management.pdf PDF
22_-_191210__Ash_Meadows__H_H_Report.pdf PDF
14_-_Map_2__Agency_Management_Area.pdf PDF
15_-_Map_3__EC_Values_Sustainability.pdf PDF
18_-_Map_6__General_Overview.pdf PDF
4_f__-_Crystal_Reservoir_Dust_Hazard_Analysis_1.pdf PDF
4_h__-_240322__Death-Valley__Output.pdf PDF
4_i__-_Crystal_Reservoir_Rehabilitation_Plan_and_Construction_Sequence.pdf PDF
4_l__-_Crystal_Springs_Construction_Sequence.pdf PDF
6_-_AMNWR__Technical_Requirements__06-12-2024.pdf PDF
25_-_Davis_Bacon_Wage_Determination.pdf PDF
26_-_Past_Performance_Questionnaire).pdf PDF
4_e__-_AMNWR__Lower_Crystal_Dam_Report.pdf PDF
17_-_Map_5__EC_Values_Community.pdf PDF
4_c__-_AMNWR__Crystal_Springs_Dam_Report.pdf PDF
4_k__-_Crystal_Springs_Re-vegetation_Plan.pdf PDF
10_-_Safety_and_Design_Checklists_v_1_1.pdf PDF
B08_-_Solicitation_(140FGA25R0003).pdf PDF
Show all 44

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Job NumberA ug us t 2

5 Crystal Springs Dam

Figure 41636.02

Ash Meadows NWR

Site Plan Map 0 250 500 1000 1500