RFI-Questions_and_Responses__01-08-2025_0002.pdf

PDF 545 KB Posted

Attached to
NV ASH MEADOWS NWR CRY SPRNGS RESTORE
Solicitation number
140FGA25R0003
Issued by

About this file

This is a Questions and Responses document dated January 8, 2025, for the Ash Meadows NWR Crystal Springs Restoration project (Solicitation No. 140FGA25R0003) issued by the U.S. Fish and Wildlife Service.

The document addresses six contractor questions submitted between December 18, 2024, and January 7, 2024. Key details revealed include: the project has an estimated magnitude exceeding $10 million; a Pre-Offer site visit will be scheduled during Phase II Solicitation; CPARs may be submitted in lieu of Past Performance Questionnaires; and the government will not provide a Government Estimate. The document also references Environmental Assessment (EA) materials, including an Example EA, EA Guidance, EA Template, and FONSI Template documents that were added through an amendment to the solicitation.

View the file

Other files

File Type Posted
Sol_140FGA25R0003_Amd_0002.pdf PDF
FINAL__UCS__EA__8-15-2013__USFWS-Reviewed_0002.pdf PDF
EA__Template__508-Compliant__Jan2025_0002.pdf PDF
EA__Guidance__508-Compliant__Jan2025_0002.pdf PDF
FONSI__Template__508-Compliant__Jan2025_0002.pdf PDF
24_-_AMNWR__Attachments_List__Crystal_Springs__01-08-2025_0002.pdf PDF
B08_-_Solicitation_(140FGA25R0003_Sections_B-M)_0001.pdf PDF
Sol_140FGA25R0003_Amd_0001.pdf PDF
B08_-_Solicitation_Cover_Form_(140FGA25R0003)_0001.pdf PDF
21_-_2018__Dam_Safety_Inspection_Letter_for_Crystal_Springs.pdf PDF
13_-_Map_1__Location.pdf PDF
4_k__-_Crystal_Springs_Re-vegetation_Plan.pdf PDF
23_-_190102__Ash_Meadows_NWR__Inventory_Assessment_Memorandum.pdf PDF
B08_-_Solicitation_(140FGA25R0003).pdf PDF
3_-_AMNWR__Statement_of_Work__Crystal_Springs__06-12-2024.pdf PDF
4_j__-_Crystal_Springs_Restoration_Plan.pdf PDF
12_-_360_FW4__Construction_Management.pdf PDF
24_-_AMNWR__Attachments_List__Crystal_Springs.pdf PDF
25_-_Davis_Bacon_Wage_Determination.pdf PDF
26_-_Past_Performance_Questionnaire).pdf PDF
4_e__-_AMNWR__Lower_Crystal_Dam_Report.pdf PDF
17_-_Map_5__EC_Values_Community.pdf PDF
16_-_Map_4__EC_Values_Connectivity.pdf PDF
9_-_Pre-Work_Safety_Checklist.pdf PDF
10_-_Safety_and_Design_Checklists_v_1_1.pdf PDF
11_-_360_FW1__Summary_of_Construction_Permits.pdf PDF
19_-_Nevada_Dept__of_Wildlife__Letter_of_Support.pdf PDF
1_-_AMNWR__Proposal_Schedule__Crystal_Springs__06-12-2024.pdf PDF
2_-_AMNWR__Subcontract_List__Crystal_Springs__06-12-2024.pdf PDF
4_a__-_AMNWR__Project_Nomination__Crystal_Springs_Outflow__Edited.pdf PDF
22_-_191210__Ash_Meadows__H_H_Report.pdf PDF
4_c__-_AMNWR__Crystal_Springs_Dam_Report.pdf PDF
4_d__-_AMNWR__Horseshoe_Dam_Report.pdf PDF
4_g__-_PFAS_Summary.pdf PDF
Sol_140FGA25R0003.pdf PDF
4_l__-_Crystal_Springs_Construction_Sequence.pdf PDF
6_-_AMNWR__Technical_Requirements__06-12-2024.pdf PDF
18_-_Map_6__General_Overview.pdf PDF
4_i__-_Crystal_Reservoir_Rehabilitation_Plan_and_Construction_Sequence.pdf PDF
15_-_Map_3__EC_Values_Sustainability.pdf PDF
4_f__-_Crystal_Reservoir_Dust_Hazard_Analysis_1.pdf PDF
20_-_Crystal_Springs_Dam__Figure_4.pdf PDF
14_-_Map_2__Agency_Management_Area.pdf PDF
4_h__-_240322__Death-Valley__Output.pdf PDF
Show all 44

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Ash Meadows NWR - Crystal Springs Restoration. Solicitation No. / Notice ID: 140FGA25R0003 Questions and Responses.

Iteration: January 8, 2025.

RFI No. Question. Response.

Date

Submitted.

Date of

Response.

1 Where is the Gov't. Estimate noted?

The USFWS is not providing a Gov't.

Estimate.

12/18/2024 12/30/2024

Does the USFWS plan to schedule a Pre-Offer site visit?

The Pre-Offer site visit is to be scheduled in the Phase II Solicitation.

12/18/2024 12/30/2024

3 Do we know a budget range (i.e. $1 to 5M or higher)?

The estimated magnitude is >$10 million.

12/18/2024 12/30/2024

Under References, most if not all Federal Agencies will not give a reference. Would USFWS give a reference to a Contractor?

Yes, the USFWS may provide a reference to the Contractor and if the reference is available.

12/18/2024 12/30/2024

5 Can we submit CPARS on our Work instead?

CPARs maybe submitted in lieu of Past Performance Questionnaires.

12/18/2024 12/30/2024

6 What about the 'Example EA' mentioned in the SOW?

Refer to separate attachments under the Amendment to Solicitation, which now includes an Example EA, EA Guidance, EA Template, and FONSI Template documents.

1/7/2024 1/8/2024

File details come from the government source that posted it. Updated .