2_Subconsultant-Subcontractor_Utilization_Worksheet_(1).xlsx
XLSX spreadsheet 32 KB Posted
- Solicitation number
- REQ- 24 - 224
- Issued by
- Pinellas County, Florida
About this file
The document is a Subconsultant/Subcontractor Utilization Worksheet issued by the City of St. Petersburg for the I-375 Surface Parking Lot Project (Project Number 20077-112). The worksheet provides detailed instructions for prime contractors regarding subcontractor participation, with up to 50% of the contract allowed to be subcontracted. The form requires comprehensive information about potential subconsultants, including their legal name, business address, contact information, trade classifications, and contract amounts.
The worksheet includes specific provisions for changing subconsultants, with seven defined scenarios permitting substitution, such as subcontractor failure to execute contracts, licensing issues, bankruptcy, or performance problems. The city has a particular focus on Small Business Enterprise (SBE) participation, requiring that any SBE subconsultants replaced must be substituted with another SBE subcontractor unless the prime contractor can demonstrate alternative SBE requirement fulfillment. The form is designed to ensure transparency, accountability, and compliance in subcontractor selection and utilization for municipal projects.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Cosme_WTP_Lime_Softening_Byproduct_(Lime_Sludge)_Excavating_and_Removal_(Addendum_#4_Revision).pdf | ||
| NRO_Permit_HC-NRO-24-0000014.pdf | ||
| Pond_Drawings_.pdf | ||
| 00768827_Agreement_Sludge.docx | DOCX document | |
| B-03._Public_Construction_Bond-Construction_(00525880).docx | DOCX document | |
| B-01._Bid_Bond_(00525848).docx | DOCX document | |
| Site_Drawing.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Instructions
| City of St. Petersburg |
| Subconsultant/Subcontractor Utilization Worksheet Instructions |
WORKSHEET MUST BE COMPLETED AND SUBMITTED WITH YOUR BID
1. The Subconsultant/Subcontractor Utilization Worksheet reflects the percentage of work which may be subcontracted for this project. Refer to Contract Standards, Instructions to Bidders, Article I-13, Subcontractors for applicable rules, or the governing Contract Documents.
2. Enter the name of your company in the Prime Consultant/Contractor field.
3. Enter the name and date of Prime Consultant/Contractor employee completing this form.
4. Provide all information requested on each intended Subconsultant/Subcontractor. If Subconsultants/Subcontractors will NOT be used for this project, provide a written statement on the Subconsultant/Subcontractor List indicating the same.
5. Subconsultants/Subcontractors may not be changed or substituted once a Prime Contractor is awarded the project (and the pre-construction meeting held), except for the following reasons:
A. Subconsultant/Subcontractor fails or refuses to execute a written contract for the scope of work as specified at the price specified;
B. Subconsultant/Subcontractor is not appropriately licensed to perform the scope of work;
C. Subconsultant/Subcontractor becomes bankrupt or insolvent;
D. Subconsultant/Subcontractor is ineligible to perform the work on the project;
E. Subconsultant/Subcontractor fails or refuses to perform its subcontract;
F. Engineer determines the work performed by the Subconsultant/Subcontractor is substantially unsatisfactory and not in substantial accordance with the plans and specifications;
G. Subconsultant/Subcontractor is substantially delaying or disrupting the progress of the work.
Requests for changes to the Subconsultant/Subcontractor List shall be made in writing to the Procurement & Supply Management, Attention: Contracts Compliance Manager at compliance@stpete.org.
6. SBE Subconsultants/Subcontractors used to meet the SBE percentage requirement, if replaced, shall be replaced with a SBE Subconsultant/subcontractor, unless the Prime Contractor demonstrates that SBE requirements are being met in another way.
7. Restrictions on subconsulting/subcontracting percentage and use of multiple-tier Subconsultants/Subcontractors do not apply to FDOT LAP or federally funded projects.
Worksheet
| City of St. Petersburg |
| Subconsultant/Subcontractor Utilization Worksheet |
| Project Name: | I-375 Surface Parking Lot |
| Project Number: | 20077-112 |
| Percentage of Contract Which May be Subconsulted/Subcontracted: Up to 50% |
| Name of Prime Consultant/Contractor: | Cells below will be "hidden" on the worksheet since they are only for Procurement's use. |
| Name/Date of Individual Completing this Form: |
| City of St. Petersburg SBE Contractor Yes or No | Subconsultant/ | ||||||||||
| Subcontractor's Name (Provide complete Legal Name) | Subconsultant/ | ||||||||||
| Subcontractor's Primary Business Address | Name/Phone Number and Email Address of Subconsultant/ Subcontractor's Employee Responsible for Project Supervision | State Tiered Level of Subconsultant/ | |||||||||
| Subcontractor | Trade Classification(s) Being Sunconsultant/ | ||||||||||
| Subcontracted (List One Trade per Line) | Subconsultant/ | ||||||||||
| Subcontractor Amount ($) | Added (A) Deleted (D) | Reason Code | City Approver/Date | Add (A) and Delete (D) Legend | |||||||
| Example: Yes | XYZ Contractors, Inc. | 123 N. Burlington Ave., St. Petersburg, FL 33701 | Joe Jones - 727-555-555 Email - XYXCon@yahoo.com | First | Electrical | 13,234.00 | D | B | Employee XYZ/03-01-19 | A. Subcontractor fails or refuses to execute a written contract for the scope of work as specified at the price specified; | |
| B. Subcontractor is not appropriately licensed to perform the scope of work; | |||||||||||
| C. Subcontractor becomes bankrupt or insolvent; | |||||||||||
| D. Subcontractor is ineligible to perform the work on the project; | |||||||||||
| E. Subcontractor fails or refuses to perform its subcontract; | |||||||||||
| F. Engineer determines the work performed by the Subcontractor is substantially unsatisfactory and not in substantial accordance with the Plans and Specifications; |
G. Subcontractor is substantially delaying or disrupting the progress of the work.
Total: 0.00
| Contract Amount | |
| 0.00 | Amount Allowed to be Subcontracted |
&8Rev. 8/3/2022 &10Page 1 of &P