This document outlines requirements for an air quality monitoring support contract. The contractor will perform monthly air quality sampling at a testing station in partnership with UC Davis and the Mark Twain National Forest. Key responsibilities include conducting samples every Tuesday for 12 months according to a provided calendar, mailing used filters every three weeks, securing facilities, and addressing any equipment issues by working with UC Davis to install replacement parts or repair items. The contract is set aside for small businesses and will be conducted according to FAR Parts 12, 13, and 19.

View the file

Other files

File Type Posted
7. Experience Questionnaire.docx DOCX document
Appendix C Example Guide - Inspection List.docx DOCX document
Appendix D Daily Diary.pdf PDF
3. Maps.pdf PDF
4. 2024 Calendar.pdf PDF
Appendix B Example Discrepancy Report.docx DOCX document
6. Sampler Maintenance by Site Operators.pdf PDF
5. Taney County SCA WD 2015-5103.txt TXT text file
OM-RFQ 12444524Q0015.pdf PDF
Appendix A Example Performance Requirement Summaries.docx DOCX document
1. Performance Work Statement (PWS).docx DOCX document
Show all 11

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

US Department of Agriculture (USDA)

Quality Assurance Surveillance Plan

Contents

Project Name3
Section 1: Introduction3
1.1Purpose3
1.2QASP Relation to the Contract3
1.2.1QASP Revisions3
1.2.2Surveillance of Performance Progression3
1.3QASP Relation to the Quality Control Plan (QCP)3
Section 2: Performance Description3
2.1Performance Standards and Acceptable Quality Levels (AQLs)3
2.1.1Allowable Deviation4
2.1.2Substantially Complete4
2.2Non-Performance4
2.2.1Documentation4
2.2.2Remedial Actions4
Section 3: Contractor and Government Responsibilities4
3.1Contractor Responsibility4
3.2Government Responsibility5
3.2.1Contracting Officer (CO)5
3.2.2Contracting Officer Representative (COR)5
3.2.3Customers5
Section 4: Surveillance Methods to Perform Quality Assurance5
4.1Surveillance Methods5
4.1.1 100 Percent Inspection5
4.1.1.1 Performance Standards and AQLs5
4.1.1.2 Evaluation Procedures6
4.2Analysis and Results6
4.2.1 Outstanding Performance6

Project Name Air Quality monitoring

Section 1: Introduction This Quality Assurance Surveillance Plan (QASP) is pursuant to the requirements listed in the performance work statement (PWS) entitled Air Quality monitoring. This plan sets forth the procedures and guidelines that the USDA, USFS will use in ensuring the required performance standards or services levels are achieved by the contractor.

1.1 Purpose

The purpose of the QASP is to describe the systematic methods used to measure performance and to identify the reports required and the resources to be employed. The QASP provides a means for evaluating whether the contractor is meeting the performance standards identified in the PWS. This QASP is designed to define roles and responsibilities, identify the performance objectives, define the methodologies used to monitor and evaluate the contractor’s performance, describe quality assurance reporting, and describe the analysis of quality assurance monitoring results.

1.2 QASP Relation to the Contract

1.2.1 QASP Revisions

The Contracting Officer Representative (COR) may make revisions or changes to the QASP procedures and surveillance methods or increase or decrease the degree of surveillance methods at any time during the contract performance period. Changes to the Metric must be incorporated into the PWS, Performance Requirement Summary (PRS) and QASP by a bilateral modification to contract that is issued by the Contracting Officer (CO). A copy of the QASP is provided to the contractor to enable the contractor to enhance its Quality Control (QC) program to perform in accordance with its Quality Control Plan (QCP).

1.2.2 Surveillance of Performance Progression

As the performance period progresses, the levels of surveillance may be altered for service areas where performance is either consistently excellent or unsatisfactory. If consistently good performance, then the amount of surveillance may be reduced. If observations reveal consistent deficiencies, increased surveillance may be implemented.

1.3 QASP Relation to the Quality Control Plan (QCP)

The QCP is a required element of contract, and the Contractor shall adhere to its established quality control processes and procedures in managing and performing work as described in the contract. While the QCP represents the way in which the Contractor will ensure its quality and timeliness of services, as defined in the PWS, the QASP represents the way in which the Government personnel specified in Section 3: Contractor and Government Responsibilities, Paragraph 3.2, Government Responsibilities will evaluate the contractor’s performance. The contractor’s QC program and the residual organization’s QASP should be complementary programs that ensure successful contractor performance.

Section 2: Performance Description Performance of the contractor will be monitored through the surveillance methods described in Section 4: Surveillance Methods to Perform Quality Assurance to assess the Contractor’s performance against PWS requirements.

2.1 Performance Standards and Acceptable Quality Levels (AQLs) For selected activities in the PWS, the PRS provides a performance standard and an AQL. A performance standard is the expected level of contractor performance. An AQL defines the level of performance that is satisfactory. Depending on the service evaluated and the evaluation method selected, performance standards and AQLs may be stated as a number of occurrences or as a percentage. Performance standards and AQLs for random sampling and 100 percent inspection are generally stated as percentages. For periodic inspections, performance standards may be stated as either percentages or as absolute numbers.

The contract requires the Contractor to perform all work as specified. Any inaccuracies or omissions in services or products are referred to as “defects” on the part of the Contractor. The Contractor shall be responsible for all identified defects and may be required to perform the work at no cost to the government. The AQLs take into account that in some instances an allowable level of deficiencies (deviations) is possible while overall performance continues to meet the government’s desired level of service.

2.1.1 Allowable Deviation

The AQLs define the level or number of performance deficiencies the Contractor is permitted to reach under this contract. AQLs take into account the difference between an occasional defect and a gross number of defects. AQLs can be expressed as a percentage of or as an absolute number (e.g., three per month). There may be instances where 100 percent compliance is required, and no deviation is acceptable (e.g., where safety is involved).

2.1.2 Substantially Complete

In some cases, service outputs are evaluated using subjective values (e.g., excellent, satisfactory, unsatisfactory). The criteria for acceptable performance and for defects must be defined for these service outputs. The concept of “substantially complete” should be the basis for inspections based on subjective scales. Work is considered “substantially complete” where there has been no significant departure from the terms of the contract and no omission of essential work. In addition, the Contractor has performed the work required to the best of its ability and the only variance consists of minor omissions or deficiencies.

2.2 Non-Performance

Non-performance occurs when the contractor’s performance does not meet the AQL for a given requirement. Requirements may contain multiple performance elements, and therefore, deficiencies may occur in one or more aspects of performance (e.g., timeliness, accuracy, completeness, etc.) or subject areas of effort.

When surveillance indicates that the contractor's service output is not in compliance with the contract requirements, the Contracting Officer’s Representative (COR) must determine whether the Contractor or the Government caused the deficiency. If the cause of the defect rests with the Government, corrective action must be taken through Government channels. If the cause of the defect is due to action or inaction by the contractor, the contractor is responsible for correction of the problem at no additional expense to the Government.

2.2.1 Documentation

Documentation of work non-performed or unacceptable work is essential for tracking Contractor performance. The COR will document deficient work by compiling facts describing the inspection methods and results and to substantiate nonconformance with the contract. A sample documentation reporting form is provided in Appendix D Daily Log form. The documentation, with any recommendations, will be forwarded to the CO. In the case of the Contractor, the COR will decide whether to elevate the problem to the CO for corrective action.

2.2.2 Remedial Actions

The Federal Acquisition Regulation allows for penalties in the event that the Contractor fails to perform the required services. Penalties are defined as those actions taken under the direction of the CO against the contractor within the general provisions of the contract for nonconformance to the PWS and PRS.

Section 3: Contractor and Government Responsibilities

3.1 Contractor Responsibility

The Contractor is responsible for delivering products or services in accordance with the contract. Implementing its QCP, which describes the Contractor’s methods for ensuring all products and services under the contract meet established performance standards and AQLs. Maintaining, and providing for audit, quality control records and reports and all records associated with the investigation and complaint resolutions. Appointing a single quality control point-of-contact to act as a central recipient of communication from the COR or CO.

3.2 Government Responsibility

3.2.1 Contracting Officer (CO)

The CO is responsible for administering and monitoring contract compliance, contract administration, and cost control and for resolving any differences between the observations documented by COR and the contractor’s performance. The CO may delegate various day-to-day contract administration duties to an Administering ACO (ACO) and/or the COR for performance management and administrative actions such as invoice approval and issuance of Contract Discrepancy Reports may be, and normally are, delegated by the CO to the COR. The CO shall approve any revisions to the QASP processes or standards.

3.2.2 Contracting Officer Representative (COR)

The COR, is designated in writing, by the CO. The COR will ensure that the QA function is properly executed, plays a key role in contract administration, and performs the contract surveillance and monitoring. Some key contract administration duties include, but are not limited to, performs surveillance as required by this QASP; make recommendations to the CO for issuance of Contract Discrepancy Reports or letters of commendation and acceptance or rejection of completed work and for administrative actions based on unsatisfactory or non-performed work, and revisions or changes to the QASP; and assists the CO in identifying necessary contract modifications and preparing reports of Contractor performance and cost.

The COR may use the form(s) included in the Appendices to perform the inspection or other forms as approved by the CO. The Contractor overall guidance is also provided by FAR clause which will be given by the company, University of California (UC) Davis, on what information needs to be provided and any issues that need to be taken care off.

3.2.3 Customers

Customers or organizations/offices that the Contractor provided support may be requested to assist the COR in conducting QA to provide information relating to the Contractor’s performance through Customer Feedback. Information gained from the Customer Feedback may be used in conjunction with other methods of observation to rate the performance of the Contractor.

Section 4: Surveillance Methods to Perform Quality Assurance

4.1 Surveillance Methods

The surveillance methods used in the QA process are the Government’s tools to monitor the Contractor’s products and services. The best means of determining whether the Contractor has met all contract requirements is to inspect the Contractor’s service products and analyze the results. Further, documented inspection results are an effective tool in contract administration that can confirm the successful achievement of all performance requirements or highlight areas where defects exist, and improvements are necessary.

The method of surveillance will be measured and provided by the company, UC Davis. If any issues arise the contractor will be notified by the company at which time, they will be expected to handle the issues and take care of any problems with the equipment. The USFS will be receiving emails at the time of request of the maintenance/issues that needs to be performed. It will be up to the contractor to address the issues within 7 days.

4.1.1 100 Percent Inspection The 100 percent inspection method requires complete inspection each month and will be used for critical contract requirements.

4.1.1.1 Performance Standards and AQLs

The performance standards and AQLs may be stated as either percentages or absolute numbers.

4.1.1.2 Evaluation Procedures

Observed defects for a service monitored by 100 percent inspection is compared to the performance standard and AQL. UC Davis will contact the contractor to notify them of any issues that need address, and the contractor will have 7 days to handle the issue. If the issues are not handled the USFS will be receiving notifications that the work was not performed, and equipment is not in proper working order.

4.2 Analysis and Results

When the inspections and validations have been completed, the COR will perform an analysis of the Contractor’s performance. The purpose of the analysis is to ensure Government is receiving high-quality products and services from the Contractor. The COR will review the results, rate the Contractor’s compliance with the performance standards and AQLs, and characterize the Contractor’s overall performance. Analysis of all types of contract monitoring will result in one of the following outcomes:

4.2.1 Outstanding Performance

Outstanding performance is the result of the Contractor substantially exceeding the performance standards with significant achievements and no significant deficiencies. The Government may reduce its level of surveillance when the COR determines that the Contractor provides sustained performance that significantly exceeds the requirements with no significant deficiencies.

Air Sample Frequency Air quality sampling must be performed every Tuesday of the month for 12 months of the year. A calendar showing when the operator is able to perform the functions within the sampling days is attached and will be provided by the U.C. Davis at the beginning of every year.

Air Sampling Air quality sampling must be performed every Tuesday of the month for 12 months of the year. On weeks that Tuesday is not feasible, other days maybe be an option depending on what week of the month it is. A calendar of the year is provided to the contractor by UC Davis to highlight what days the sampling can be performed. The contractor shall ensure that the air sampling is done on the appropriate days that are allowed. The USFS will have a backup copy of the calendar if needed.

Mailing of Samples The contractor will be set up as the contact for the delivery of the shipment of the box with the new air quality filters. The contractor will also be responsible for mailing in the used filters every three weeks, which will be shipped in a box that is provided with a prepaid mailing label. This will need to be shipped from a UPS shipping location.

Equipment All equipment that will be needed to perform the air samples will be provided by the Air Quality research business, UC Davis. If a piece of equipment is no longer functional, it is the contractor’s responsibility to report the issue of concern to UC Davis and work with them to correct the problem. If a new piece of equipment is needing to be replaced to support the air quality sampling, it is the contractor’s responsibility to install the piece of equipment while working with UC Davis.

UC Davis will provide all parts, replacement components, and instructions on how to disconnect and reconnect the item(s) of needed replacement. In the event air monitor equipment needs repair, a modification will be executed on that CLIN for the respected period of performance. Since replacement parts will be provided, Contractor should provide their hourly rate.

The contractor should also take note of any damage and/or repairs to the building structure that houses the instruments. If an issue occurs the contractor needs to notify the Contracting Officer's Representative (COR) to resolve the issues as soon as possible.

Securing The Facility The contractor is responsible for securing the facilities when leaving the facilities. The location of the tower is located inside a cattle pasture. Upon completion of the air sampling, the contractor will lock the air quality building with a combination lock that is provided by the US Forest Service. A combination lock is also provided on the gate, that enters the fenced in area below the tower, that will also need secured upon leaving the facilities. The contractor will also be responsible for closing the cattle gate which is located at the road entrance and making sure that the chain and wire are both securely fastened to prevent cattle from entering the roadway.

image1.png