2-00-43-00.pdf

PDF 223 KB Posted

Attached to
FCE130309 4610 Wasatch Hollow Outfall Redesign - CONST
Solicitation number
FCE130309 4610 Wasatch Hollow Outfall Redesign - CONST
Issued by
Salt Lake County, Salt Lake City, Utah

About this file

This Bid Schedule 00 43 00 document is a pricing and payment structure instrument for the Wasatch Hollow Outfall Redesign project (Project No. EFCFP240001) in Salt Lake City, Utah. The project involves general contracting services at 1499 S 1700 E to modify the existing outlet and overflow structure at the Wood Hollow detention pond, install a new overflow and outlet storm drain pipe routing through the park to connect with the existing system at 1700 S, and make improvements to components inside the outlet structure including new gates and linkage. The base bid schedule contains 38 line items covering mobilization, traffic control, construction survey, stormwater pollution prevention planning, dewatering, clearing and grubbing, removal and replacement of pavement, sidewalks, structures, and landscape features, furnishing and installation of reinforced concrete pipe, inlet structures, storm drain manholes, slide gates, sensors, and protective housing. An additive bid schedule includes two items for electrical components and gate actuators. Quantities range from single lump sum items to measurable units such as 456 linear feet of 30-inch reinforced concrete pipe, 43 cubic yards of emergency spillway basin material, and 81 linear feet of fence and gate removal and reinstallation.

Payment terms are structured by individual bid items with measurement units specified as lump sum, each, linear foot, square yard, square foot, cubic yard, or acre. Mobilization costs are capped at a maximum of 10 percent of the total bid schedule, with mobilization payment released in phases based on percentages of original contract amount earned. First mobilization payment is contingent upon receipt and acceptance of a pre-construction video recording. Individual pay items provide detailed descriptions of work scope, included materials, labor, and equipment. Measurement and payment are specified for each item and include associated costs such as labor, materials, equipment, permits, coordination, testing, compaction, restoration, and incidentals necessary to complete the work as shown on plans and per specifications. References are made to APWA standards and Salt Lake City specifications for guidance on material quality and installation procedures.

View the file

Other files

File Type Posted
4-ProjectManual.pdf PDF
5-Drawings.pdf PDF
3-00-43-13.pdf PDF
1-00-41-00.pdf PDF
7-FCE130309 Bid Tabulation.xls XLS spreadsheet
6-Addendum 1.docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

BID SCHEDULE

00 43 00 - 1

DOCUMENT 00 43 00

PART 1 GENERAL

1.01 BIDDER

A. Company Name ______________________

1.02 CONSTRUCTION CONTRACT

A. Name of Project: Wasatch Hollow Outfall Redesign Project No. EFCFP240001 Contract No. XXX-XXX-XXXXX

1.03 RELATED REQUIREMENTS

A. APWA 01 29 00: Payment Procedure.

1.04 SCHEDULES TO BE ADDED TO THE AGREEMENT

A. This Bid Schedule contains the schedules of prices which will be incorporated into the Agreement (Document 00 52 00) by reference.

1.05 SCHEDULES OF PRICES

Base Bid Schedule (Structure and Spillway):

Item No.

Specification Reference Number Classification of Unit Price

Work

Quantity Unit

Unit Price Amount

1 Mobilization 1 Lump Sum

2 Traffic Control 1 Lump Sum

3 Construction Survey 1 Lump Sum

4 Prepare and Implement SWPPP

Lump Sum

5 Prepare and Implement Dewatering Plan

Lump Sum

6 Clearing and Grubbing 0.1 Acre

7 Remove and Replace Topsoil and Sod

2,848 Square Foot

Bid Schedule 00 43 00 -2

Item No.

Specification Reference Number Classification of Unit Price

Work

Quantity Unit

Unit Price Amount

8 Remove and Replace Asphalt Pavement

Square Yard

9 Remove and Replace Sidewalk 96 Square Yard

10 Remove and Replace Driveway Approach

Square Yard

11 Remove and Dispose of Existing Inlet Structure

Lump Sum

12 Remove and Replace Tree 2 Each

13 Remove and Replace Curb and Gutter

Linear Foot

14 Remove and Reinstall Fence and Gate - Primary Intake

Linear Foot

15 Remove Existing Fence - Emergency Spillway

Linear Foot

16 Remove and Replace Stamped Concrete Trail

Square Yard

17 Remove and Replace Control Structure Access Hatch

Lump Sum

18 Connect 30" Pipe to Existing Storm Drain Manhole

Each

19 Furnish and Install 12" Culinary Water Loop with Concrete Casing

Each

20 Furnish and Install 30" Reinforced Concrete Pipe

Linear Foot

21 Furnish and Install Irrigation Repairs

Lump Sum

00 43 00 - 3

Item No.

Specification Reference Number Classification of Unit Price

Work

Quantity Unit

Unit Price Amount

22 Furnish and Install 60" Diameter Storm Drain Manhole

Each

23 Furnish and Install Emergency Spillway Inlet Structure

Lump Sum

24 Furnish and Install Emergency Spillway Basin

Cubic Yard

25 Furnish and Install Primary Inlet Structure

Lump Sum

26 Furnish and Install 6” UTBC - Trail Near Primary Intake

Cubic Yard

27 Furnish and Install Scour Protection Plate

Lump Sum

28 Furnish and Install D-Ring 1 Each

29 Remove and Replace Manhole Step

Each

30 Furnish and Install Level Sensor and Wireless Alarm System

Lump Sum

Furnish and Install 54" Slide Gate, Frame, Submersible Gear Boxes, Link Rods, and Non-Rising Stem

Lump Sum $ $

32 Furnish and Install Stainless Steel Protective Housing

Furnish and Install Link Rods, Stems, and Submersible Gear Boxes.

Lump Sum $ $

34 Furnish and Install Stainless Steel Manual Operating Components

Each

35 Furnish and Install Orifice Closure 1

00 43 00 -4

No.

Specification Reference Number Classification of Unit Price

Work

Quantity Unit

Unit Price Amount

36 Furnish and Install Tamperproof Stainless Steel Enclosure

Each

37 Furnish and Install Post and Split Rail Fence – Emergency Spillway

Linear Foot

38 Furnish and Install Double Swing Gate – Emergency Spillway

Base Bid Total = $_____________

Additive Bid Schedule 1 (Power and Communications for the Gates):

No.

Specification Reference Number Classification of Unit Price Work

Quantity Unit

Unit Price Amount

1.1 Furnish and Install Electrical

Components

Lump Sum

1.2 Furnish and Install Stainless Steel

Slide Gate Actuator

Additive Bid 1 Total = $_____________

1.06 MEASUREMENT AND PAYMENT

Unless indicated otherwise within individual bid item descriptions, measurement and payment for bid items shall include only the WORK, which is associated with the applicable Bid Schedule.

1. Mobilization – Bid Item #1

a. Reference Specification: APWA 01 71 13.

b. Measurement: Lump Sum.

c. Payment Covers: All costs of mobilization and demobilization including, but not limited to: mobilization; demobilization; bonding and insurance costs; video

00 43 00 - 5 recording site conditions prior to construction; progress cleaning, temporary facilities; project signs; any additional permits not obtained by the owner;

Coordination with utilities, public agencies, property owners, schools, emergency services, etc.; Administrative incidentals such as Progress Schedules per APWA 01 32 16, and Submittals per APWA 01 33 00 (See project specification modification). This pay item shall constitute full compensation for all labor, equipment, tools, supplies and materials required to complete this portion of the work for as shown on the plans and as specified herein.

d. The lump sum cost of Mobilization shall not exceed 10% of the total bid schedule. Any bid proposal for mobilization that is greater than 10% of the total bid will be adjusted to the maximum amount of 10% of the total bid. The bid item so adjusted will be the Contractor’s bid for that item, and the contractor’s bid for the project will be recalculated and the revised total used to compare with other bidders to determine the low bid. The OWNER will pay the adjusted lump sum price for “Mobilization”."

e. Payment will be made on a percentage basis as follows:

Percent of Original Contract

Amount Earned (Not Including Materials

Purchased) Percent of Amount Bid for

Mobilization to be Paid 5% 30% 15% 20% 40% 20% 50% 15%

*Original contract amount is defined as the dollar value of all awarded bids at the time notice to proceed is issued.

f. First mobilization payment will not be released until a copy of the pre-construction video recording is received and accepted by the engineer.

2. Traffic Control – Bid Item #2

a. Reference Specification: APWA 01 55 26.

b. Measurement: Lump Sum.

c. Payment Covers: Costs associated with all labor, materials, equipment, and appurtenances required for traffic control including but not limited to developing a traffic control plan; placing appropriate barriers, signs, and sandbags;

implementing flagging; acquiring permits; coordinating with local and state agencies; and all other incidentals as required to complete the work as shown on the plans and as specified herein.

3. Construction Survey – Bid Item #3

a. Reference Specification: APWA 01 71 23.

b. Measurement: Lump Sum.

00 43 00 - 6

c. Payment Covers: Costs associated with all labor, materials, equipment, and appurtenances required for construction surveying, including but not limited to, setting project control, staking alignment, cleanouts, inlets, pipeline, structures, curbing, waterways, location of all signs to be removed and replaced as required, surveying potholed utilities, final grade checks, permitting and work for replacement of disturbed monuments, and all other incidentals as may be required to complete this item and produce the work shown in the plans and as specified herein.

4. Prepare and Implement SWPPP – Bid Item #4

a. Reference Specification: APWA 01 57 00, 31 25 00.

b. Measurement: Lump Sum.

c. Payment Covers: Costs associated with all labor, materials, equipment, and appurtenances required to prepare and implement a stormwater pollution prevention plan (SWPPP) as required by the Utah Pollutant Discharge Elimination System (UPDES) including but not limited to: developing the SWPPP, submitting the SWPPP to the required agencies for approval, implementing the SWPPP and maintaining SWPPP-related construction features, and regular coordination with agencies to ensure compliance. Construction activities cannot begin and will be stopped without the required stormwater permits and if approved SWPPP is not implemented.

5. Prepare and Implement Dewatering Plan – Bid Item #5

a. Reference Specification: APWA 01 57 00, 31 25 00.

b. Measurement: Lump Sum.

c. Payment Covers: Costs associated with all labor, materials, equipment, and appurtenances required to prepare, maintain, and implement the surface water control and ground dewatering including evacuating running water from the basin; installing temporary diversions, cofferdams, dewatering basins, and pumping equipment; transferring water past construction improvement areas;

implementing erosion control practices to prevent particle remobilization upon re-entry; removing controls when they are no longer needed; and all other incidentals as may be required to complete this item and produce the work shown in the plans and as specified herein.

6. Clearing and Grubbing – Bid Item #6

a. Reference Specification: APWA 31 11 00.

b. Measurement: Acre.

c. Payment Covers: Costs associated with all labor, materials, equipment, and appurtenances required for stripping and disposing of site features, including but not limited to, stumps, roots, shrubs, vegetation, sprinkler systems that are to be abandoned, abandoned utility boxes, utilities that are in the way of construction having a nominal size of less than 4”, cast-in-place landscape curbing, and trees less than 4 inches in diameter (12.5” circumference) within the construction limits. Removing, salvaging, and storing, preparing grade for, and resetting precast landscape curbing or tree rings after grading is complete is included in this

00 43 00 - 7 pay item. Removal of pavement, sidewalks, fencing, structures, etc. will be paid under separate pay items.

7. Remove and Replace Topsoil and Sod – Bid Item #7

a. Reference Specification: APWA 32 91 19, 32 92 00.

b. Measurement: Square Foot.

c. Payment Covers: Costs associated with all labor, materials, equipment, and appurtenances required for removing, stockpiling, and reapplying stockpiled topsoil and sod. Payment also includes removal and disposal of sod that is unsuitable for reapplication as determined by engineer and furnishing and installing new sod, and all other incidentals as may be required to complete this item and produce the work shown in the plans and as specified herein. If weather conditions cause unsuitable installation conditions, payment also includes delaying the installation until a later time with better weather conditions.

8. Remove and Replace Asphalt Pavement – Bid Item #8

a. Reference Specification: APWA 02 41 14, 32 12 05, 33 05 25.

b. Measurement: Square Yard.

c. Payment Covers: Costs associated with all labor, materials, equipment, and appurtenances required to sawcut, demolish, remove, and dispose of asphalt pavement, regardless of depth. Payment also includes furnishing and installing a Hot Mix Asphalt patch, including subgrade preparation, prime coat application, asphalt placement and compaction, testing, striping restoration, and all other incidentals as may be required to complete this item and produce the work shown in the plans and as specified herein. If weather conditions cause unsuitable installation conditions, payment also includes delaying the installation until a later time with better weather conditions. Payment also includes the installation of temporary asphalt during construction if needed.

9. Remove and Replace Sidewalk – Bid Item #9

a. Reference Specification: APWA 02 41 14, 03 11 00, 03 30 04 to 03 39 00.

b. Measurement: Square Yard.

c. Payment Covers: Costs associated with all labor, materials, equipment, and appurtenances required to sawcut at an existing joint, demolish, remove, and dispose of existing concrete (including any reinforcing steel present). Payment also includes subbase preparation, formwork, concrete testing, placement of new concrete sidewalk, jointing, finishing, curing, weather protection, removal of formwork, and all other incidentals as may be required to complete this item and produce the work shown in the plans and as specified herein.

10. Remove and Replace Driveway Approach – Bid Item #10

a. Reference Specification: APWA 02 41 14, 03 11 00, 03 30 04 to 03 39 00.

b. Measurement: Square Yard.

appurtenances required to sawcut at an existing joint, demolish, remove, and

00 43 00 - 8 dispose of existing concrete (including any reinforcing steel present). Payment also includes subbase preparation, formwork to match existing connecting grades and curb, concrete testing, placement of new concrete driveway approach to match existing concrete thickness (or a minimum thickness of 6 inches, whichever is greater), jointing, finishing, curing, weather protection, removal of formwork, and all other incidentals as may be required to complete this item and produce the work shown in the plans and as specified herein.

11. Remove and Dispose of Existing Inlet Structure – Bid Item #11

a. Reference Specification: APWA 02 41 13.

b. Measurement: Lump Sum.

c. Payment Covers: Costs associated with all labor, materials, equipment, and appurtenances required for removing and disposing of the existing inlet structure.

This includes excavation, demolition, jackhammering, saw cutting, and removal of existing inlet structure steel and concrete components. It also includes the preservation of the existing connected 48” RCP, and all other incidentals as may be required to complete this item and produce the work shown in the plans and as specified herein.

12. Remove and Replace Tree – Bid Item #12

a. Reference Specification: APWA 31 11 00.

b. Measurement: Each.

c. Payment Covers: Costs associated with all labor, materials, equipment, and appurtenances required to coordinate a landscape replacement plan with a Salt Lake City arborist to determine appropriate tree removal mitigation, excavate around the root ball of a tree, cut the roots where necessary, remove and dispose of the tree, prepare the excavated hole, deliver and plant up to four new trees based on arborist recommendations and according to landscaping replacement plan, backfill with appropriate material, and all other incidentals as may be required to complete this item and produce the work shown in the plans and as specified herein.

13. Remove and Replace Curb and Gutter – Bid Item #13

a. Reference Specification: APWA 02 41 14, 03 30 04 to 03 39 00.

b. Measurement: Linear Foot.

c. Payment Covers: Costs associated with all labor, materials, equipment, and appurtenances required to saw cut, remove, and dispose of the existing curb and gutter at existing joint locations, as shown on the plans. Payment also covers costs for labor, materials, equipment, and appurtenances required for subbase preparation, formwork, concrete testing, reinforcement installation, placement of new concrete curb and gutter, jointing, finishing, curing, weather protection, and removal of formwork, as shown on plans and according to APWA Standard Plan 205 and SLCDPU standards.

14. Remove and Reinstall Fence and Gate – Primary Intake – Bid Item #14

00 43 00 - 9

a. Reference Specification: APWA 32 01 10.

b. Measurement: Linear Foot.

c. Payment Covers: Costs associated with all labor, materials, equipment, and appurtenances required for removing and reinstalling existing fences and gates.

This includes excavation and salvaging of fence posts, chain link fabric, fence railings and hardware. It also includes coordination with the Owner to determine which material could be reinstalled, and which material needs to be replaced.

Salvage / reinstall in-kind where feasible. Replace deficient materials to match existing. Cost for this item also includes replacing deficient material, reinstalling/installing fence posts with concrete bases, fence railings, gate hardware, gates, chain link fabric, and all other incidentals that may be required to complete this item and produce the work shown in the plans and as specified herein.

15. Remove Existing Fence – Emergency Spillway – Bid Item #15

a. Reference Specification: APWA 32 01 10.

b. Measurement: Linear Foot.

c. Payment Covers: Costs associated with all labor, materials, equipment, and appurtenances required for removing and disposing of existing fences, and all other incidentals as may be required to complete this item and produce work shown in the plans and as specified herein.

16. Remove and Replace Stamped Concrete Trail – Bid Item #16

a. Reference Specification: APWA 32 13 13.

b. Measurement: Square Yard.

c. Payment Covers: Costs associated with all labor, materials, equipment, and appurtenances required for demolishing, jackhammering, removing and disposing of existing stamped concrete trails and reinforcing steel as indicated in plans.

Payment also includes excavation, regrading, subgrade preparation (this includes, placement, compaction, and testing of 8” of untreated base course), formwork, reinforcement installation, concrete testing, placement of new concrete trail (6” min thickness), jointing, stamping, curing, weather protection, removal of formwork and all other incidentals as may be required to complete this item and produce the work shown in the plans and as specified herein.

17. Remove and Replace Control Structure Access Hatch – Bid Item #17

a. Reference Specification: APWA 05 12 00.

b. Measurement: Lump Sum.

c. Payment Covers: Costs associated with all labor, materials, equipment, and appurtenances required for removing and replacing the control structure access hatch with a Bilco or EJCO Double Leaf Access Hatch or approved equal, with an appropriately anchored frame, hydraulically assisted hinges, lockable handles, and all other incidentals as may be required to complete this item and produce the work shown in the plans and as specified herein.

00 43 00 - 10

18. Connect 30” Pipe to Existing Storm Drain Manhole – Bid Item #18

a. Reference Specification: APWA 31 23 16, 33 41 00.

b. Measurement: Each.

c. Payment Covers: Costs associated with all labor, materials, equipment, and appurtenances required to align the new pipe with an existing storm drain manhole, saw cut the wall of the manhole structure to fit the new pipe, install the pipe into the existing manhole structure at appropriate elevations with sufficient embedment and support, place grout and mastic around the opening of the manhole structure and all other incidentals as may be required to complete this item and produce the work shown in the plans and as specified herein.

19. Furnish and Install 12” Culinary Water Loop with Concrete Casing – Bid Item #19

a. Reference Specification: APWA 33 11 00.

b. Measurement: Each.

c. Payment Covers: Costs associated with labor, materials, equipment, and appurtenances required for pipe installation work and material shown in APWA Plan No. 543.1, 543.2, and Public Utilities Department Standard Practice No. 1, and incidentals such as excavation, additional saw cut and removal of trench pavement; removing interfering structures and obstructions; groundwater control;

pipe dewatering; identifying alignment and location of nearby sewerline; shoring and bracing; transition couplings; sleeves; factory fabricated integral wyes;

bends; bolts and nuts; gaskets, adapters, miscellaneous fittings; plugs; concrete thrust blocks or restraints; joint restraining devices; mechanical thrust restraints;

welding pipe sections together that fall within 10 feet of the sewer line and encasing these pipe sections with 4” of concrete on all sides (the encased portion of the waterline loop shall not have fittings or joints); greasing and wrapping all exposed fittings, bolts and nuts; pipeline repair if disturbed by construction operations, capping or plugging of existing pipe(s) to be abandoned, abandonment of existing water pipe(s), fittings, and salvaging or abandoning existing valves;

pipe zone, untreated road base, and trench backfill and compaction, compaction testing, temporary roadway or sidewalk surfacing materials, cleaning, disinfection and commissioning. Payment under this bid item will only be made for loops approved in advance and in written form by the Project Engineer. Payment also covers all other incidentals as may be required to complete this item and produce the work shown in the plans and as specified herein.

20. Furnish and Install 30” Reinforced Concrete Pipe – Bid Item #20

a. Reference Specification: APWA 33 41 00.

b. Measurement: Linear Foot.

c. Payment Covers: Costs associated with labor, materials, equipment, and appurtenances required for dewatering, excavation, trench box and/or shoring, imported bedding, bedding materials, pipe foundation materials, RCP alignment and installation, mastic and other adhesive joint materials, pipe supports for utility crossings, fittings, saw cutting and grouting for connections to manholes, 00 43 00 - 11 hardware, disposal of excess materials, any other utility restoration not covered by another pay item, and the restoration of any other existing improvements not heretofore noted that have been adversely impacted, damaged, destroyed, or made inoperable by and incidental to the installation of the RCP that have not been specified in another bid item. Payment also includes the placement and compaction of untreated base course backfill up to subgrade level. Work shall be done in accordance with the project plans and specifications. Payment also covers all other incidentals as may be required to complete this item and produce the work shown in the plans and as specified herein.

21. Furnish and Install Irrigation Repairs – Bid Item #21

a. Reference Specification: APWA 32 84 23.

b. Measurement: Lump Sum.

c. Payment Covers: Costs associated with all labor, materials, equipment, and appurtenances required for installing irrigation repairs; which include identifying line locations during excavation activities, cutting and capping lines in the way of construction, identifying irrigation head locations that need to be removed and salvaged, reconnecting cut and capped lines with appropriate coupling components, and pipe materials, reinstalling or installing new sprinkler heads, testing the functionality of the irrigation system, and all other incidentals as may be required to complete this item and produce the work shown in the plans and as specified herein.

22. Furnish and Install 60” Diameter Storm Drain Manhole – Bid Item #22

a. Reference Specification: APWA 31 23 16, 03 40 00, 33 41 00

b. Measurement: Each.

c. Payment Covers: Costs associated with labor, materials, equipment, and appurtenances required furnish and install a reinforced concrete storm manhole which include excavation bedding materials, mastic application, concrete component placement, cover, frame and ring installation, backfill, compaction, and testing, and all other incidentals as may be required to complete this item and produce the work shown in the plans and as specified herein.

23. Furnish and Install Emergency Spillway Inlet Structure – Bid Item #23

a. Reference Specification: APWA 03 11 00, 03 20 00, 03 30 04 to 03 39 00.

b. Measurement: Lump Sum.

c. Payment Covers: Costs associated with all labor, materials, equipment, and appurtenances required for installing inlet structure including excavation, backfill (material containing rocks greater than 3” in diameter shall not be placed within 1 ft of the structure), compaction, and testing of structural fill and other earthwork materials, subgrade preparation, formwork, epoxy covered reinforcement installation, concrete testing, jointing, finishing, curing, weather protection, water stops, shoring, and bracing. Payment also includes the manufacturing, fabrication, delivery, field welding, and installation of all steel components for the trash rack, 00 43 00 - 12 and all other incidentals as may be required to complete this item and produce the work shown in the plans and as specified herein.

24. Furnish and Install Emergency Spillway Basin – Bid Item #24

a. Reference Specification: APWA 31 37 00.

b. Measurement: Cubic Yard.

c. Payment Covers: Costs associated with all labor, materials, equipment, and appurtenances required for installing the riprap for the emergency spillway which includes excavation and grading, subgrade preparation, granular filter placement and compaction, geotextile installation, riprap placement, and all other incidentals as may be required to complete this item and produce the work shown in the plans and as specified herein. No separate payment will be made for riprap or geotextile in the spillway basin; all such work is included in this item. Costs for Emergency Spillway Concrete Weir and Inlet Structure are considered in separate bid items.

25. Furnish and Install Primary Inlet Structure – Bid Item #25

a. Reference Specification: APWA 03 40 00.

b. Measurement: Lump Sum.

c. Payment Covers: Costs associated with all labor, materials, equipment, and appurtenances required for installing inlet structure including excavation, backfill (material containing rocks greater than 3” in diameter shall not be placed within 1 ft of the structure), compaction, and testing of structural fill and other earthwork materials, subgrade preparation, formwork, epoxy covered reinforcement installation, concrete testing, jointing, finishing, curing, weather protection, water stops, shoring, and bracing. Payment also includes the manufacturing, fabrication, delivery, field welding, and installation of all steel components for the trash rack, and all other incidentals as may be required to complete this item and produce the work shown in the plans and as specified herein.

26. Furnish and Install 6” UTBC – Trail Near Primary Intake – Bid Item #26

a. Reference Specification: APWA 33 05 20, 31 05 15, 31 23 26, 32 11 23.

b. Measurement: Cubic Yard.

c. Payment Covers: Costs associated with labor, materials, equipment, and appurtenances required for furnishing, hauling, placing, shaping, compacting, and testing six inches of untreated base course material as specified in the plans and specifications. Payment also includes excavation, hauling, and disposing of excavated materials as well as grading and subgrade preparation. Payment also covers all other incidentals as may be required to complete this item and produce work shown in the plans and as specified herein. Untreated base course used under sidewalk, curb and gutter, and for pipe backfill is not included in this pay item but is included in those respective pay items.

27. Furnish and Install Scour Protection Plate – Bid Item #27

a. Reference Specification: APWA 05 53 00.

b. Measurement: Lump Sum.

00 43 00 - 13 appurtenances required for furnishing and installing a stainless steel scour protection plate, including threaded anchor rods, drilled holes, and all other incidentals as may be required to complete this item and produce the work shown in the plans and as specified herein.

28. Furnish and Install D-Ring – Bid Item #28

a. Reference Specification: General Structural Notes, Sheet 19-20

b. Measurement: Each.

c. Payment Covers: Costs associated with all labor, materials, equipment, and appurtenances required for furnishing and installing a corrosion resistant D-ring to the interior of the outfall structure wall with appropriate concrete anchors for harnessing and safety purposes, and all other incidentals as may be required to complete this item and produce the work shown in the plans and as specified herein. Costs cover required safety equipment for individuals performing the installation.

29. Remove and Replace Manhole Step – Bid Item #29

a. Reference Specification: APWA Plan 331.2

b. Measurement: Each.

c. Payment Covers: Costs associated with all labor, materials, equipment, and appurtenances required for removing, disposing of, and installing a new manhole step that matches existing and all other incidentals as may be required to complete this item and produce the work shown in the plans and as specified herein. Costs cover required safety equipment for individuals performing the installation.

30. Furnish and Install Level Sensor and Wireless Alarm System – Bid Item #30

a. Reference Specification: 40 72 00.

b. Measurement: Lump Sum.

c. Payment Covers: Costs associated with all labor, materials, equipment, and appurtenances required for furnishing and installing a corrosion resistant water level sensor and wireless alarm system with cellular capabilities which includes mounting the sensor, testing the functionality of the electronic components, and setting up communication with designated personnel.

31. Furnish and Install 54" Slide Gate, Frame, Submersible Gear Boxes, Link Rods, and Non-Rising Stem – Bid Item #31

a. Reference Specification: 40 05 59.

b. Measurement: Lump Sum.

a. Payment Covers: Costs associated with all labor, materials, equipment, and appurtenances required for furnishing and installing the sliding gate, including the gate, frame, stem guides/brackets, non-rising stems, link rods, submersible gear boxes, mounting hardware, concrete coring, testing, and all other incidentals as

00 43 00 - 14 may be required to complete this item and produce the work shown in the plans and as specified herein.

32. Furnish and Install Stainless Steel Protective Housing – Bid Item #32

a. Reference Specification: APWA 05 12 00.

b. Measurement: Lump Sum.

c. Payment Covers: Costs associated with all labor, materials, equipment, and appurtenances required for fabricating the custom steel components, anchoring ledgers and supports into the concrete walls, and accessing the installation location and installing the protective housing in place and all other incidentals as may be required to complete this item and produce the work shown in the plans and as specified herein.

33. Furnish and Install Link Rods, Stems, and Submersible Gear Boxes – Bid Item #33

a. Reference Specification: 40 05 59.

b. Measurement: Lump Sum.

c. Payment Covers: Costs associated with all labor, materials, equipment, and appurtenances required for removing existing operator and installing a new gearbox onto the existing pedestal, removing and installing a new stem, and furnishing and installing link rods, a non-rising stem, an additional submersible gear box, stem guides, brackets, mounting hardware, and coring concrete, and all other incidentals as may be required to complete this item and produce the work shown in the plans and as specified herein.

34. Furnish and Install Stainless Steel Manual Operating Components – Bid Item #34

a. Reference Specification: 40 05 57.

b. Measurement: Each.

c. Payment Covers: Costs associated with all labor, materials, equipment, and appurtenances required for furnishing and installing stainless-steel manual operating components above the concrete outfall structure, which includes, a shaft, a bushing, a square tube adapter, and all other incidentals as may be required to complete this item, and produce the work shown in the plans and as specified herein. Payment also includes coordination with Salt Lake County personnel to choose the appropriate square tube adapter that would be compatible with County equipment.

35. Furnish and Install Orifice Closure – Bid Item #35

a. Reference Specification: APWA 05 12 00.

b. Measurement: Lump Sum.

c. Payment Covers: Costs associated with all labor, materials, equipment, and appurtenances, required for furnishing and installing channel features, seals, and other and associated mounting hardware for attaching stop gate rails to existing concrete, providing aluminum plate sized for temporary closures, and all other

00 43 00 - 15 incidentals as may be required to complete this item and produce the work shown in the plans and as specified herein.

36. Furnish and Install Tamperproof Stainless Steel Enclosure – Bid Item #36

a. Reference Specification: APWA 05 56 00.

b. Measurement: Each.

c. Payment Covers: Costs associated with all labor, materials, equipment, and appurtenances required for furnishing and installing a tamperproof stainless steel enclosure, associated hardware, and all other incidentals as may be required to complete this item and produce the work shown in the plans and as specified herein.

37. Furnish and Install Post and Split Rail Fence – Emergency Spillway – Bid Item #37

a. Reference Specification: APWA 32 01 10.

b. Measurement: Linear Foot.

c. Payment Covers: Costs associated with all labor, materials, equipment, and appurtenances required for furnishing and installing post and split rail fence, including post excavation, concrete foundation, post placement, rail placement, associated hardware, and all other incidentals as may be required to complete this item and produce the work shown in the plans and as specified herein. Chain link fabric for the fence at the emergency spillway will be provided and installed by Salt Lake City Public Lands under a separate contract and is not included in this bid item.

38. Furnish and Install Double Swing Gate – Emergency Spillway – Bid Item #38

a. Reference Specification: APWA 32 31 13.

b. Measurement: Each.

c. Payment Covers: Costs associated with all labor, materials, equipment, and appurtenances required for furnishing and installing double swing gate including excavation, concrete foundations, tubular steel pipe posts. Rails, vertical braces, and locking mechanisms with associated hardware, hinges, and black vinyl coating, and all other incidentals as may be required to complete this item and produce the work shown in the plans and as specified herein. Chain link fabric for the fence at the emergency spillway will be provided and installed by Salt Lake City Public Lands under a separate contract and is not included in this bid item.

Alternative Bid 1

1. Furnish and Install Electrical Components – Bid Item #1.1

a. Reference Specification: APWA 26 05 00, 26 05 34.

b. Measurement: Lump Sum.

appurtenances required to complete installation of all electrical components

00 43 00 - 16 shown on the plans and described in the specifications for a functional system, including furnishing and installing all conduit, trenching, backfilling, compacting, removing, and disposing of excess material, surface restoration (this includes asphalt, sidewalk, topsoil, and sod replacement), mounting rigid conduit on the outlet structure (including mounting hardware), and junction boxes. This also includes furnishing and installing pull tape as required in conduits, coordination with utility companies and installing equipment and materials provided by them, including any concrete pads on which equipment will be mounted, furnishing and installing electric power meter base and socket, including post and mounting hardware, furnishing and installing electrical cabinets and panels and specified components within them, furnishing, installing, configuring, and testing electronic equipment, furnishing and installing electrical conductors, including grounding, furnishing and incorporating all required hardware, adapters, connectors, etc. and making all electrical connections, configuration, and testing. Costs also cover coordination with the utility company and any additional fees required to install and energize electrical components on the network side of the meter.

2. Furnish and Install Stainless Steel Slide Gate Electric Actuator – Bid Item #1.2

a. Reference Specification: APWA 05 56 00.

b. Measurement: Each.

c. Payment Covers: Costs associated with all labor, materials, equipment, and appurtenances required for furnishing and installing a stainless-steel slide gate actuator, a pedestal, mounting hardware, and all other incidentals as may be required to complete this item, properly connect to the threaded stem, and produce the work shown in the plans and as specified herein.

END OF DOCUMENT