This document is a question and answer (Q&A) file related to a Request for Quote (RFQ) for a recording studio renovation project for the Department of State's Public Diplomacy Section (PDS) in Panama City.

The key details are:

  • The RFQ number is 19PM0724Q0057.
  • The project involves renovating the PDS recording studio, including replacing HVAC equipment, acoustic insulation, and lighting.
  • The Q&A addresses various installation and construction details, such as waste disposal, door reuse, HVAC work coordination, wall reinforcement, and use of flexible ductwork.
  • The contract does not include providing furniture for the work tables.
  • All reinforcement required will be per the International Building Code, specifically for the windows and doors.

View the file

Other files for this federal contract opportunity

Other files attached to Public Diplomacy Section (PDS) - Recording Studio, newest first.
File Type Posted
24Q0057_PreproposalMinutes_(PDS) - Recording Studio.pdf PDF
24Q0057 - QA.pdf PDF
24Q0057 - SF18 - Cover Page.pdf PDF
24Q0057 - Attachment 2 - DRAWINGS.pdf PDF
24Q0057 - Attachment 3 - SPECIFICATION.pdf PDF
24Q0057 - Invitation letter.pdf PDF
24Q0057 - Attachment to SF18 - PDS - RECORDING STUDIO.pdf PDF
24Q0057 - Attachment 1 - SAMPLE BREAKDOWN OF PRICE BY DIVISIONS OF SPECIFICATIONS.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

NEC – RFQ# 19PM0724Q0057 - – Public Diplomacy Section (PDS) - Recording Studio

UNCLASSIFIED

Question and Answer

1. What is the schedule for waste disposal?

The schedule for waste disposal, is the timing in the project to dispose of waste during the project. How many times a week the contractor will be required to dispose waste during the week.

2. Door D2, it seems that the position before and after the remodeling is the same. Is it necessary to uninstall and reinstall it?

The door D2 will not be necessary to remove but in case needed the contractor shall remove it and no additional charge will be allowed. The contractor is responsible for the care of every reused element of the room, and they shall make a survey to understand the initial status of every element.

3. When replacing the supply ducts and replacing VAV-0-187, will the air handling units be turned off?

No, the AHU can’t be turned off and the contractor will have to coordinate all works with COR, prior any job related to the HVAC. In case that the contractor, needs the AHU shut down, this will need to be on a weekend to avoid disruptions.

4. As it is not indicated on the plans. Should the internal face of the gypsum wall facing corridor 184 be removed to replace the acoustic insulation?

This is an installation method and will be the contractor’s call once he/she sees the structure inside the wall. If the COR notes that the method requires to remove this face of the wall is more efficient, then this will need to be done.

The initial intention of the insulation installation is to simply remove an area from the insulation, but, if necessary, this action will be required at no cost.

5. It was indicated in the meeting that the doors to be installed will be reused, are the hinges and locks also being reused?

Yes, doors and hinges will be reused.

6. Are the new air conditioning ducts to be supplied and installed only those that are after

VAV-0186 and VAV-0187?

• Only ducts that are before and after VAV’s will be included in the contract. No main duct will be touched and this will need to be coordinated with COR.

7. The 2" piping and the wiring that goes from the Electrical Panel NLR/12A to the

Junction Box "J" and breakers 58, 60, and 61: will they be supplied and installed by the

Embassy?

No, this will be included in the contract. The embassy will refer the routing and how to manage the way to go to the electrical room.

All wall penetrations shall be sealed with a fire-resistant caulking, better or equal than HILTI

FIRE PRODUCTS.

8. If the answer to point 7 is negative, how much distance is there between these two points?

Approximately 35 meters, this will be including any deviation.

9. For the installation of the linear diffusers, there are two that are installed on the wall facing corridor 184. For one of the other two, should a lintel be made?

Yes, for both through grilles will be necessary to install a lintel.

10. To feed the linear diffusers, should they be fed with a flexible duct?

It’s permitted, but following ASHRAE STANDARDS on flexible ducts and through grilles installations.

11. The countertops to be used as a work table, will they be supplied and installed by the

Embassy?

No furniture will be supplied by the contractor.

12. Internally, do the gypsum walls require any type of reinforcement for hanging or installing? For example, the countertops indicated in point 11?

All reinforcement will be as per INTERNATIONAL BUILDING CODE and will be only for the windows and doors.