QA_19R0005_2.pdf

PDF 324 KB Posted

Attached to
Remodel of Barracks at the Murcielago Police Academy
Solicitation number
19AQMM19R0005
Issued by

About this file

The attached file contains 6 additional vendor questions (#29-34) and answers. All solicitation terms and conditions remain unchanged.

View the file

Other files

File Type Posted
QA_19R0005_3.pdf PDF
A004_SF30.pdf PDF
A003_SF30.pdf PDF
A003_Attachments.zip ZIP file
QA_19R0005.pdf PDF
19AQMM19R0005_A002.pdf PDF
19AQMM19R0005_A001.pdf PDF
J-1-3_Past_Performance_and_References.xlsx XLSX spreadsheet
J-2-5_Submittal_Form.xlsx XLSX spreadsheet
J-2-6_Bidding_Chart.xls XLS spreadsheet
19AQMM19R0005.pdf PDF
J-2-4_Exoneration_Form_(Tax_Exemption).pdf PDF
J-2-3_Incident_Reports.docx DOCX document
J-2-1_Mat_Prod_Substitution_Form.pdf PDF
J-3-1_Drawings.zip ZIP file
J-2-2__Firm_and_Project_Information.pdf PDF
J-1-2_Past_Performance_Questionnaire_(PPQ).pdf PDF
J-1-1_Statement_of_Work.pdf PDF
Show all 18

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Q&A # Questions Responses 29 According to sheet S.4, confirm that currently no solera beam was placed in the indicated area and there is no problem with placing the beam type VCM1, giving the fact that it is totally new structure.

It is not necessary to place a new VCM1 beam above the existing walls, due to a similar beam already existing.

30 Confirm that the roof structure of the existing area should only be cleaned and repainted and not changed in its entirety. The roof structure shall not be intervened, other than cleaned and repainted, except for the beams in the roof’s valley, as indicated in the area marked grey in sheet S5.1.

31 Confirm that the entire area of roof cover must be replaced and not only reshape the area The entire roof cover must be replaced with a “sandwich” system, as indicated in drawing A-05.

32 Confirm all windows remain as they are now and we will only install mosquito mesh. All of the accessories and fixtures shown in drawings shall be considered, including any accessory necessary for the correct functioning of the different mechanical systems.

33 Indicate whether we need to do any work whatsoever for existing systems on sheet shown in G-02 area. The work to be performed includes the connection to the existing system and the testing of the plumbing, to ensure adequate functioning of all connections.

34 Should the air conditioning and extraction system be included in our cost? As stated in Section C.1.9 of the SOW, the Contractor shall build the air conditioning system. The air conditioning and extraction system shall be in accordance with drawing E1.3. The Contractor should include all labor, materials, equipment and services necessary to accomplish the construction required by the Contract.