The attached file contains 6 additional vendor questions (#29-34) and answers. All solicitation terms and conditions remain unchanged.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| QA_19R0005_3.pdf | ||
| A004_SF30.pdf | ||
| A003_SF30.pdf | ||
| A003_Attachments.zip | ZIP file | |
| QA_19R0005.pdf | ||
| 19AQMM19R0005_A002.pdf | ||
| 19AQMM19R0005_A001.pdf | ||
| J-1-3_Past_Performance_and_References.xlsx | XLSX spreadsheet | |
| J-2-5_Submittal_Form.xlsx | XLSX spreadsheet | |
| J-2-6_Bidding_Chart.xls | XLS spreadsheet | |
| 19AQMM19R0005.pdf | ||
| J-2-4_Exoneration_Form_(Tax_Exemption).pdf | ||
| J-2-3_Incident_Reports.docx | DOCX document | |
| J-2-1_Mat_Prod_Substitution_Form.pdf | ||
| J-3-1_Drawings.zip | ZIP file | |
| J-2-2__Firm_and_Project_Information.pdf | ||
| J-1-2_Past_Performance_Questionnaire_(PPQ).pdf | ||
| J-1-1_Statement_of_Work.pdf |
Show all 18
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Q&A # Questions Responses 29 According to sheet S.4, confirm that currently no solera beam was placed in the indicated area and there is no problem with placing the beam type VCM1, giving the fact that it is totally new structure.
It is not necessary to place a new VCM1 beam above the existing walls, due to a similar beam already existing.
30 Confirm that the roof structure of the existing area should only be cleaned and repainted and not changed in its entirety. The roof structure shall not be intervened, other than cleaned and repainted, except for the beams in the roof’s valley, as indicated in the area marked grey in sheet S5.1.
31 Confirm that the entire area of roof cover must be replaced and not only reshape the area The entire roof cover must be replaced with a “sandwich” system, as indicated in drawing A-05.
32 Confirm all windows remain as they are now and we will only install mosquito mesh. All of the accessories and fixtures shown in drawings shall be considered, including any accessory necessary for the correct functioning of the different mechanical systems.
33 Indicate whether we need to do any work whatsoever for existing systems on sheet shown in G-02 area. The work to be performed includes the connection to the existing system and the testing of the plumbing, to ensure adequate functioning of all connections.
34 Should the air conditioning and extraction system be included in our cost? As stated in Section C.1.9 of the SOW, the Contractor shall build the air conditioning system. The air conditioning and extraction system shall be in accordance with drawing E1.3. The Contractor should include all labor, materials, equipment and services necessary to accomplish the construction required by the Contract.