19-Attachment C - COT Water UWS WUR-26-0036.pdf

PDF 537 KB Posted

Attached to
Intersection Improvements for East County Line Road at Grand Hampton Drive
Solicitation number
IFB-26-00398
Issued by
Hillsborough County, Florida

About this file

This is a Utility Work Schedule form prepared by the City of Tampa-Water Department as the Utility Agency/Owner (UAO) for the East County Line Road at Grand Hampton Drive intersection improvement project (WUR-26-0036) in Hillsborough County, Florida. The project, estimated at $1,239,930.07, involves intersection improvements located in Section 2 Township 27S, Range 19E in Tampa. The plans are dated May 18, 2026, with CIP Number 69600319. According to the utility work schedule, no construction items or non-construction items requiring preliminary work, material procurement, right-of-way acquisition, or other utility-related activities are anticipated for this project. The City of Tampa-Water Department representative is Benjamin Freamon (813-274-3301), with KCI serving as the County's representative (813-740-2300 Ext. 2960). The document was authorized on June 22, 2026, with final approval by Lisa Strout, Capital Utility Coordinator.

The schedule identifies critical coordination requirements and blackout dates during which the City of Tampa cannot perform water shutdowns: November 18-28, 2026, and December 16, 2026, through January 3, 2027. The contractor must request an approved Critical Path Method (CPM) schedule within five days of FDOT approval and submit written notification to WaterUtilityCoordination@TampaGOV.net for any valve box adjustments requiring 1.5 weeks of material lead time. All water infrastructure adjustments must be staked for final concrete elevation and preceded by five working days' notice. Materials can be obtained from the City of Tampa Water Department at 3901 E. 26th Ave, Tampa, Florida 33605. In connection with this solicitation, a 5% Small Business Enterprise (SBE) participation goal has been established for subcontractors. Emergency contact for the City of Tampa Water Department is available 24 hours at 813-274-7400.

View the file

Other files

File Type Posted
7-Subcontractors Statement of Satisfaction.pdf.pdf PDF
31-Performance Bond.pdf PDF
5-Consent of Surety-Change Order.pdf.pdf PDF
32-Payment Bond.pdf PDF
4-Application for Payment.pdf.pdf PDF
16-Subcontractor Letter of Intent .pdf PDF
25-Bid Bond.doc.doc DOC document
8-Consent of Surety to Final Payment.pdf.pdf PDF
26-Attachment F - Supplemental Specifications.pdf PDF
11-Substitute W9 Form.pdf.pdf PDF
27-Attachment A - Construction Sign 2025 6x4.pdf PDF
28-Attachment A - Construction Sign 2025 4x6.pdf PDF
6-Payment Assistance (SBE Set-Aside).pdf.pdf PDF
9-Change Order Form.pdf.pdf PDF
30-1.Terms Conditions.pdf PDF
20-Attachment D - Project Map.pdf PDF
1-Drug Free Workplace Form.doc.doc DOC document
12-Direct Deposit Authorization Form 5.15.2025.pdf.pdf PDF
21-Attachment E - TrafficControlOfficer 6.10.docx DOCX document
18-Attachment B - Geotech report.pdf PDF
24-Agreement - Construction - Stand Alone-IFB-26-00398.docx DOCX document
3-Allowance Authorization Release Form.pdf.pdf PDF
14-Contractors Affidavit for Payment of Debts and Claims 02.18.2026.pdf PDF
22-Attachment G - Insurance Requirements.pdf PDF
17-SBE Goal Participation SBE-1 Form Tutorial.mp4 MP4 file
10-Insurance Certificate.doc.doc DOC document
15-AFFIDAVIT OF COMPLIANCE - Denying Doing Business with a Foreign Country of Concern 02.26.2026.docx DOCX document
23-Attachment H - Plans 20260424 SS.pdf PDF
13-SBE Subcontractors Material Suppliers List SBE-1 Form.pdf PDF
2-Vendor Eligibility Check Prior to Contract Award.pdf.pdf PDF
29-Attachment A - Construction Sign 2025 8x4.pdf PDF
Show all 31

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Hillsborough County County Road: County Line Road Plans Dated: 05/18/2026

CIP Number: 69600319 Project Name: East County Line Road at Grand Hampton Drive [WUR-26-0036]

Utility Agency/Owner (UAO): City of Tampa—Water Department

NON-CONSTRUCTION ITEMS

ESTIMATED

*CALENDAR DAYS

CONSTRUCTION ITEMS

ESTIMATED

*CALENDAR DAYS

Total Preliminary 0 Prior to County Project Construction 0

Total Material Procurement 0 During County Project Construction 0

Total Right-of-Way Acquisition 0 As-Built Information ______0______

Total Other 0 * Calendar Days = UAO Work Days x 7/5 and takes into consideration simultaneous activities listed on Part “C” of this Schedule

This document has been developed as the method for a Utility Agency/Owner (UAO) to transmit to Hillsborough County, the roadway contractor, and other right-of-way users, the location, relocation, adjustment, installation, and/or protection of facilities, on this Hillsborough County project. The following data is based on the plans dated as listed in the Title Block.

Any deviation by Hillsborough County or its Contractor from plans, as provided may render this work schedule null and void.

Upon notification by, Hillsborough County of such change, this utility may require additional days for assessment and negotiation of a new work schedule. This UAO is not responsible for events beyond the control of the UAO that could not reasonably be anticipated by the UAO and which could not be avoided by the UAO with the exercise of due diligence at the time of the occurrence. The UAO agrees to notify Hillsborough County in writing prior to starting, stopping, resuming, or completing work. The UAO is to provide As-Built information.

The UAO shall obtain a utility permit and comply with the requirements of the Hillsborough County UAM.

During the project, the UAO shall locate their facilities within 48 hours of notice to their Representative: KCI _ Telephone Number: 813-740-2300 Ext- 2960

UAO Project Representative: Benjamin Freamon Telephone Number: 813-274-3301

UAO Field Representative: Telephone Number:

This document is a printout of a Hillsborough County form maintained in an electronic format and all revisions thereto by the UAO in the form of additions, deletions or substitutions are reflected only in an Appendix entitled “Changes to Form Document” and no change is made in the text of the document itself. Hand notations on affected portions of this document may refer to changes reflected in the above-named Appendix but are for reference purposes only and do not change the terms of the document. By signing this document, the UAO hereby represents that no change has been made to the text of this document except through the terms of the Appendix entitled “Changes to Form Document”.

You MUST signify by selecting or checking which of the following applies:

No changes to forms document.

Appendix “Changes to Forms Document” is attached. Number of Attachment Pages.

Authorized Utility Agent: **Engineer of Record (EOR): Acceptance by Hillsborough

County:

(Signature) (Signature) (Signature)

Benjamin Freamon

Jorge A. Guerra Rodriguez, PE

Steffanie Workman, PE

(Printed Name) (Printed Name) (Printed Name)

Engineer Technician III

Engineer of Record

County Design Project Manager

(Title) (Title) (Title)

5/18/2026

(Date) (Date) (Date)

Final Approval by Hillsborough County:

(Signature) (Date)

Lisa Strout Capital Utility Coordinator (Printed Name) (Title)

(**When requested by the County, the EOR will attest to compatibility of plans, specifications and Utility Work Schedule)

6/22/2026

WorkmanS Text Box 06/22/26

Special Conditions and Constraints

1. City of Tampa Water requests (via e-mail to WaterUtilityCoordination@TampaGOV.net) a copy of the approved contractors CPM (Critical Path method) schedule is requested within 5 days of FDOT approval.

2. In the event of a general water emergency, contact the City of Tampa Water Department's 24-hour emergency number at:

(813) 274-7400 and WaterDistributionScheduling@TampaGov.net

3. Adjustments to valve boxes, required due to resurfaced roadway adjacent to those boxes, will be made as follows:

a) Material Lead Time: The City of Tampa will need 1.5 weeks (8 working days) notification PRIOR to work at the location of the water meter boxes, valve boxes, tops, and or risers. Such notification may occur during the project construction meetings, but all requests must be presented in writing for record keeping purposes. E-mail to WaterUtilityCoordination@TampaGOV.net is preferred.

b) If there is a case where any of the items listed above is damaged and material is requested, (see Material Lead Time above) the City can provide the required items at:

3901 E. 26th Ave, Tampa Florida 33605 **Delivery can be coordinated, but a specific DATE must be provided.**

c) All material acquisition requests for the City originating from the Hillsborough County contractor will be directed to the City of Tampa Water Department Field contact. When different, the UAO Project Rep will be carbon copied (CC) on all project related correspondence.

d) After resurfacing operations have been completed, FDOT or its Contractor will ensure all Water valve boxes, meter box lids, hydrants, and all other City of Tampa maintained appurtenances are left in a condition allowing easy operation and access for maintenance. City of Tampa appurtenances will not be paved over, unadjusted, or left in any state where maintenance would be considered unduly difficult or hampered.

e) For the sake of coordination with the City of Tampa Water (and project progression in a reasonable manner) to perform any adjustment to City of Tampa Water infrastructure, the Contractor must stake the final concrete elevation per each relocation instance. The City of Tampa requests notification 5 work days before such work is necessary via e-mail, or following the weekly construction meeting.

4. "Stations" and "offsets" provided in Section C will be understood to be referenced from the project Hillsborough County surveyed construction baseline (Baseline of Construction), as identified in the associated dated HC project plans.

5. City of Tampa Black-out Dates: During these dates, the City of Tampa cannot perform water shutdowns (and work is limited):

11/18/2026 – 11/28/2026 & 12/16/2026 – 1/3/2027

C. Disposition of Facilities (List All Existing & Proposed) on Project

TYPE / SIZE /

MATERIAL / OFFSET

TO BASELINE FROM

STA TO STA

DESCRIPTION

OF

UTILITY WORK

DEPENDENT

ACTIVITIES

M.O.T.

PHASE

NUMBER

CONSECUTIVE

CALENDAR

DAYS

Prior During No utility work required.

2026-06-22T12:23:51-0400
Jorge A Guerra Rodriguez
2026-06-22T13:42:11-0400
Steffanie L. Workman
2026-06-29T14:27:27-0400
Lisa Strout

File details come from the government source that posted it. Updated .