18th Ave and Pierce St Lane shift.xlsx

XLSX spreadsheet 4 MB Posted

Attached to
ITB 25-041-PW Grant St and Pierce St Water Main Replacement
Solicitation number
S-P00140-00013065
Issued by
Lane County, Oregon

About this file

This document is a notification and work plan for a lane shift project involving Eugene Water & Electric Board (EWEB) at 18th Avenue and Pierce Street in Eugene, Oregon. The work involves chlorinating an already installed water main, requiring a three-shift project scheduled from 8:15am to 4:00pm with 48-hour advance notifications to local emergency services, including Fire/EMS, Eugene Police Department, and City of Eugene Signal Operations. The project requires maintaining work zone safety with flaggers, preserving 10-foot minimum travel lanes, using appropriate signage (UWA, CLCA, LSR, RTO), and ensuring continuous communication and access for businesses and pedestrians.

The notification connects to a broader infrastructure project (ITB 25-041-PW) for water main replacement on Pierce Street from E 18th Ave to E 23rd Ave and Grant Street from the 2000 block to E 22nd Ave. The comprehensive water infrastructure upgrade will involve installing approximately 2,690 feet of 12-inch water main, 1,425 feet of 8-inch water main, and 30 feet of 6-inch water main. Project components include water valves, fittings, connected water services, and fire hydrants. Key contacts for the project include Nate Wahto (541-579-9359), Nolan Melendrez (541-914-8109), and Tyler Kennedy (541-520-5141), who will oversee the technical and logistical aspects of the infrastructure improvements.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sheet1

Notifications : 48 hours before work is to begin

FIRE/EMS; EPD 541-682-5111

LTD 541-682-6199

City of Eugene Signal OPs 541-954-8382 N Duration : 3 shifts Work times : 8:15am-4:00pm

EWEB

18th Ave & Pierce St (Lane shift) Contact : Nate Wahto 541-579-9359 *Nolan Melendrez 541-914-8109 Tyler Kennedy 541-520-5141

RTO

Nature of Work : EWEB will be chlorinating the already installed water main.

See ROW permit application project description for more information.

A worker to be available to maintain the work zone. Flaggers to maintain visual or radio contact at all times.

Crew to maintain a 10' minimum per travel lane.

Cones to be spaced to allow for driveway access.

Lanes to be re-opened and signs to be turned or removed at the end of the work day.

Contact buisinesses or residents if access is to be affected

Pedestrians will be escorted through the work zone as needed.

UWA = Utility Work Ahead = 3 CLCA = Center Lane Closed Ahead = 2 LSR = Lane Shifts Right = 2 RTO = Right Turn Only = 1 Sign Spacing = 100' Area to be worked in =

UWA

CLCA

UWA

CLCA

UWA