Amendment_2.pdf
PDF 188 KB Posted
- Attached to
- Operation of Sacramento Job Corps Center
- Solicitation number
- 1630J6-18-R-00001
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Amendment_8.pdf | ||
| Amendment_7.pdf | ||
| Amendment_6.pdf | ||
| Amendment_5.pdf | ||
| Price_Detail_Template_(Attachment_J-1_Revised_1-25-2018).xlsx | XLSX spreadsheet | |
| Revised_Pricing_Schedule_(1-11-2018).docx | DOCX document | |
| Amendment_4.pdf | ||
| Amendment_3.pdf | ||
| Price_Detail_Template_(Attachment_J-1_Revised_1-9-2018).xlsx | XLSX spreadsheet | |
| Amendment_1.pdf | ||
| Price_Detail_Template_(Attachment_J-1_Revised_12-21-2017).xlsx | XLSX spreadsheet | |
| Solicitation.docx | DOCX document | |
| Utilities.pdf | ||
| Master_Itemized_Property_Report.pdf | ||
| Utility_Analysis_for_2016.xls | XLS spreadsheet | |
| Mileage_and_Fuel_Usage_(2016).xls | XLS spreadsheet | |
| Property_Summary_Report.pdf | ||
| Vehicle_Log.xls | XLS spreadsheet | |
| Facility_Planning_Report_(Vol._1).pdf | ||
| Facility_Planning_Report_(Vol_2).pdf |
Show all 20
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE
Page Of Pages
1 4
2. AMENDMENT/MODIFICATION NO. 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQ. NO. 5. PROJECT NO. (If applicable)
Amendment No. 2 See Block 16C.
6. Issued by CODE JC009 7. ADMINISTERED BY (If other than Item 6) CODE JC009 U.S. Department of Labor Employment and Training Administration Office of Contracts Management 90 7th Street Suite 18-300 San Francisco, CA 94103
SAME
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code) (X)CODE (X)
9A. AMENDMENT OF SOLICITATION NO.
1630J6-18-R-00001
TO ALL POTENTIAL OFFERORS CONCERNING REQUEST FOR PROPOSAL FOR
SACRAMENTO JOB CORPS CENTER
9B. DATED (SEE ITEM 11)
12-20-2017
10A. MODIFICATION OF
CONTRACT/ORDER NO.
10B. DATED (SEE ITEM 11)
CODE FACILITY CODE
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended, is not extended. Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods: (a) By completing items 8 and 15 and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate correspondence which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by written correspondence provided each correspondence makes reference to the solicitation and this amendment and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
Not Applicable
13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
CHECK ONE
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER
NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings including solicitation/contract subject matter where feasible.)
This amendment provides clarification to the questions on the following pages.
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
Chin-Jen Chang Contracting Officer
15B. CONTRACTOR/OFFEROR
15C. DATE
SIGNED
16B. UNITED STATES OF AMERICA
16C. DATE
SIGNED
(Signature of person authorized to sign) (Signature of Contracting Officer) 1-5-2018
Solicitation No. 1630J6-18-R-00001 Amendment No. 2
1. Refer to Attachment J-4 (Staffing Chart). Line 05 (Career Success Personnel) on the J-4 does not list the Residential Counselor position which is required by Job Corps Policy and Requirements Handbook (PRH). Please verify if the PRH requirement supersedes Attachment J-4 to the RFP.
Offerors shall abide by the PRH requirement for Residential Counselors. Offerors may add this position to Attachment J-4 (Staffing Chart).
2. Refer to Page 18 of the RFP. The RFP specifies counties for Career Transition Services
(CTS) but does not identify a specific area for Outreach/Admissions (O/A). Is there a specific area for O/A within California? Or will the O/A services for this contract recruit throughout the entire state of California?
The following is the tentative list of counties that constitute the Geographic Assignment Plan (GAP) for Sacramento Job Corps Center:
Alpine
Amador
Butte
Calaveras
Colusa
Del Norte
El Dorado
Glenn
Humboldt
Lake
Lassen
Marin (Also assigned to Treasure Island Job Corps Center.)
Mariposa
Mendocino
Modoc
Mono
Napa (Also assigned to Treasure Island Job Corps Center.)
Nevada
Placer
Plumas
Sacramento
San Joaquin
Shasta
Sierra
Siskiyou
Solano
Sonoma
Sutter
Tehama
Trinity
Tuolumne
Yolo
Yuba
3. Refer to Pages 22-23 of the RFP. The Career Technical Training (CTT) offerings do not include Facilities Maintenance. However, Facilities Maintenance is listed as Career Technical Training that qualifies for Career Technical Skills Training funds. Please clarify if Facilities Maintenance is a CTT that will be offered at Sacramento Job Corps Center, or if it is listed as qualifying for CTST funding in error.
Facilities Maintenance is a CTT offering which qualifies for CTST funding.
4. Is there a current Collective Bargaining Agreement in place?
There is currently no Collective Bargaining Agreement.
5. Is SIATech providing the Academic Services on this Center?
SIATech administers one of the high school diploma programs offered by the center and provides a dedicated staff to do this.
6. Refer to Page 63 of the RFP (Section H.30). This section states: ”Incentives that are charged to the contract shall not exceed one percent (1%) of total gross wages of center staff including those occupying professional positions in Paragraph H6 and shall not exceed $5,000 per individual.”
Please verify that this statement does not include OA/CTS in this calculation as these are firm-fixed-price components and only the specified line item will be chargeable to the contract.
This restriction does not apply to O/A and CTS.
7. Is the child development center being utilized? If so, who operates this and will you please provide a copy of the agreement?
The Sacramento Employment and Training Agency (SETA) currently operates its Head Start Child Development Program on the Sacramento Job Corps Center. The partnership is expected to continue. A new and revised Memorandum of Understanding between U.S. Department of Labor and SETA is currently being established. A copy of the agreement is not available at this time.
8. Are any of the vehicles on center utilized for Driver’s Education/Training? If not, are vehicles being leased by the center to fulfill this training requirement?
GSA vehicles are available on center to fulfill this training.
9. What are the plans for the former Culinary Arts building?
No plans at this time.
10. The holidays listed in the Price Detail Template states: “Please specify additional proposed Holidays.” Please clarify if the listed holidays must remain and additional holidays can be added. Or can offerors replace existing holidays on the list with other holidays.
The listed holidays must remain, but offerors may propose additional holidays.
11. Are there any major facility issues and equipment concerns?
There are always a number of ongoing maintenance and equipment issues at the center. Other than Operations and Maintenance (O&M) funds, additional repairs will be funded through the request system for Construction, Rehabilitation, and Acquisition (CRA).
12. Are there any additional trade changes expected other than the recent changes?
No additional trade changes are expected at the moment.
13. The RFP states that offerors must tab each specific factor, sub-factors, and elements.
For the Technical Approach, this will result in a bound document of over 36 tabs and may limit the number of pages the offeror has for answering requirements due to page breaks and font size. Will the Government revise the requirement to only provide tabs for the factor and sub-factor level?
The requirement is hereby changed. Tabs will now be required for the factor and sub-factor levels only.
14. Refer to Page 4 of the RFP (Section B.2). Will the contractor receive payments for arrivals or placements exceeding the goals?
Contractors will only receive the fixed-price amounts on the contract for O/A and CTS. However, any performance that is “over and above” could be noted in non-monetary ways (e.g. past performance evaluation).
File details come from the government source that posted it.