This is a Questions and Responses document (Amendment 2) for Carville Solicitation 1605AE-27-Q-00001, a firm-fixed-price caretaker services contract for a Department of Labor facility in Carville, Louisiana. The document addresses 43 questions from prospective contractors covering contract scope, pricing, staffing, equipment, insurance, and evaluation criteria.
Contract Scope and Pricing: The contractor will provide comprehensive facility management services including security (minimum two armed guards 24/7), general maintenance, grounds keeping, custodial work, and equipment maintenance. Utility costs average $12,400 monthly and are included in the fixed contract price, not reimbursable. HVAC equipment rental and generator rental expenses are incorporated into the fixed monthly price; the contractor must assume existing rental agreements and place them in the contractor's name, though the current vendor is not transferable. CRA B1b/B1a funding has been removed as of Amendment 2. Repairs and maintenance identified outside the contract scope are reimbursed via contract change requests with COR concurrence and CO written approval. Pre-existing facility deficiencies, historic tree work, security camera repair/replacement, hurricane preparation, and kitchen equipment maintenance are excluded from contractor responsibility. The contractor maintains and refuels all government-owned equipment (lawn equipment, golf carts, generators). Wage Determination WD 2015-5177 (Rev 32) applies with no collective bargaining agreement. Security licenses are not required at quotation but must be provided by end of transition period. Property inventory completion is required within 14 calendar days after transition.
Evaluation and Award: Award will be made on a best value basis to the responsible offeror whose quote conforms to solicitation requirements, with pricing evaluated on total CLIN amounts including all option periods for completeness and reasonableness. All non-price evaluation factors (technical approach, caretaker services contract experience, safety and quality control, and past performance) combined are greater than price. Factor 2 requires at least one project valued at $350,000 or greater completed within the last five years; ongoing projects with at least one year of performance are acceptable. Projects performed as joint venture partners or subcontractors may be considered if officially recognized. Price format must include a breakdown of monthly CLIN pricing by labor, subcontracts, and other direct costs. Office space is available for contractor staff; the Project Manager is not required to be on-site but must be local and within driving distance for periodic site visits. The contracting officer will make award on the basis of initial quotes without discussions.
View the file
Other files
Show all 12
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Carville Solicitation
1605AE-27-Q-00001
Amendment 2
Questions and Responses
#1. The documents listed in the PWS section XII. Appendices were not included in the solicitation package. Can the government provide the following appendices?
Appendix A – Facility Survey Volume I Appendix B – Facility Survey Volume II Appendix C – Minimum Preventive Maintenance Requirements Appendix D – Transition Checklist Appendix E.1 – Brightly Asset Summary List for Carville Appendix E.2 – Government Property Asset Summary List for Carville
Response: See attchments added to SAM.gov RFQ Attachmnets Section
#2. Should utility expenses be included in the firm-fixed-price quotation, or will they be funded or reimbursed separately? Please provide the most recent 12–24 months of utility usage and billing history and identify any required account deposits. Can the government share the average monthly utility cost for the site? Or is it reimbursable at actual cost? What is included in the monthly utility costs (electricity, water, gas, etc.)?
Response: Based on the most recent years utilities the average cost for the Utilities is $12,400/month. The utility cost is part of the fixed contract price,and is not reimbursable. The monthly utility cost includes electric, water and gas.
#3. The solicitation indicates that the incoming contractor will be responsible for assuming existing rental agreements for HVAC equipment. Please clarify whether the Government intends for these rental expenses to be reimbursed as Other Direct Costs (ODCs) or included in the contractor's Firm-Fixed-Price (FFP) proposed pricing. If the HVAC equipment rental expenses are intended to be reimbursable, will the Government amend the solicitation to establish a separate cost-reimbursable ODC CLIN?
Response: The HVAC equipment rental will be included in the contract FFP price, not a separate reimbursable.
#4 Is the contractor expected to put the HVAC and generator rental contracts in its name?
Response: Yes
#5. Maintenance and repairs: Please define which maintenance and repair costs must be included in the fixed price, which qualify for separate B1a/B1b CRA funding, and which remain the lessor’s responsibility. Are there dollar thresholds or approval requirements for each category?
Response: Reference Section IV Performance Work Statement, Paragraph 2 through 8, 10-13, and 15 for items to be included in the fixed price. Also reference the Preventive Maintenance Requirements in attached Appendix C of the Solicitation. Additionally, Repairs and maintence that are identified outside of the contract scope, and priced by the caretaker, and concurred by the COR, and approved in writing by the CO, will be reimbursed outside of the original contract award amount via contract change request/modification
#6. Who holds the property insurance? (Contents and Buildings) (Fire, Flood, Weather Events, Theft/Vandalism) What type of insurance will be required from the Caretaker? Also confirm the limits. Also is the insured DOL or the owner of the property? Required insurance types and minimum coverage limits for the prime contractor and subcontractors. Any required endorsements, including additional-insured status or waiver of subrogation. Whether proof of insurance is required with the quotation, before award, or before performance begins.
Response: Contractor will be required to carry standard insurance. Proof of insurance with the quotation is not required.
#7. Since the site is leased by DOL, is the contractor expected to put the lease in its name?
Response: No
#8. Whether separate requirements apply to security services, the patrol vehicle, government property, or rental HVAC equipment.
Response: Contractor shall comply with the requirements set forth is the Performance Work Statement.
#9. Please also confirm whether FAR 52.228-5, “Insurance—Work on a Government Installation,” is intended to apply.
Response: No, this Center is not a Government Installation.
#10. Relevant project experience: Factor 2 states that at least one project must have “a value between 500,000,” but the range appears incomplete. Please provide the intended dollar-value requirement.
Response: At least one project must have a value of $350,000 or greater.
#11. Under Preventive & Corrective Maintenance - if any repairs are identified and priced, are the cost reimbursed outside of the base bid? (change order?) Can the government please confirm that corrective maintenance will be covered in additional task orders. Can the government please confirm that corrective maintenance will be covered in additional task orders. Please confirm that repair and replacement parts and subcontracted repairs are funded through CRA B1a/B1b and are not part of the monthly price. Please also define which consumables the monthly price must cover.
If any repairs are identified and priced, are the cost reimbursed outside of the base bid? (change order?)
Response: CRA B1b/B1a usage is removed from this solicitation as of Amendment 2.
Repairs and maintence that are identified outside of the contract scope, priced by the caretaker, concurred by the COR, and approved by the CO, in writing, are reimbursed outside of the original contract award amount via contract change request/modification.
#12. Under Grounds Maintenance, if there are any services required for trees (trim and/or removal) due to weather or deemed to be necessary for safety/building maintenance, is that cost part of the fixed base bid? If trees are damaged due to weather events, who holds the liability for cleanup?
replacement?
Response:Outside of normal ground maintenance, repairs and maintence that are identified as outside of the contract scope, and priced by the caretaker, and concurred by the COR, and approved by the CO, in writing, are reimbursed outside of the original contract award amount via contract change request/modification.
#13. What is the scope for the custodial work?
Response: See Part 1 Custodial in attached Appendix C of the Solicitation
#14. Is working, but currently shut off kitchen equipment part of the general maintenance?
Response: No, this equipment is not included in the general maintenance work requirements.
#15. How many personnel are expected for general maintenance/security?
Response: For Security personnel requirements reference Section IV Performance Work Statement, Paragraph 1. For General maintenance, provide the number of personnel required to comply with the requirements of Section IV Performance Work Statement, Paragraph 2 through 9, 10 through 13 and 15.
#16. Are the pad locks going to be transferred to the new Caretaker?
Response: The pad locks and keys will be transferred from the current caretaker to the new caretaker towards the end of the transition period.
#17. Will the new Caretaker need to provide new lawnmowing/golfcarts equipment, or will it be transferred from the current contract to the new contract… to assist with provision of security/roaming services?
Response: The DOL owned lawnmowing/golfcarts will be transferred from the current caretaker to the new caretaker for their use following the transition period. Reference Page 50 of 85 in Appendix E.2 of the solicitation.
#18. Does DOL have an inventory of all the furniture and other equipment on Center?
Response: See Appendix E.2 of the solicitation.
#19. Are pre-existing such as ceiling water damage and floor (IE at the gymnasium) to be repaired by the new Caretaker.
Response: No, any pre-existing deficiencies such as ceiling damage from water leaks will not be the responsibility of the caretaker to repair.
#20. Is the tree limb that is broken (on one of the historic trees) to be removed by the new Caretaker?
Response: No, work on the historic trees at Carville including the downed tree limb near the back of the Center will not be the responsibility of the caretaker.
#21. Is the Center on a single electric meter of are each building metered separately?
Response: Seven (7) of the buildings are individually metered, only Receiving Building 7 and Guard House Building 9 are not individually metered.
#24. Will the Government repair/replace the non-working security cameras?
Response: No, this work is not included in the contract.
#25. Relative to the Project Manager position, is this an on-site or remote position?
Response: The Project Manager is not required to be on-site but should be local to the area and within driving distance in-order to perform periodic site visits as required to ensure compliance with the Performance Work Statement.
#26. Is there office space available for contractor staff
Response: Yes
#27. Are the lawn equipment (zero turns, tractors), golf carts, and service equipment government-owned and available for the contractor to use in performing the contract? If so, who maintains and fuels them?
Response: Contractor maintains and refuels all government owned equipment used at the Center.
#28. PWS lists the security cameras as nonfunctional. To what extent is the contractor expected to repair or replace them?
Response: Repair or replacement of the nonfunctional security cameras are not in the Caretaker solicitation/contract.
#29. What mowing and edging frequency does the government expect?
Response: Grounds keeping frequency is outlined in Part 6 GROUNDS / SNOW REMOVAL in Appendix C of the solicitation.
#30. Who performs the annual inspection and testing of the fire alarm, sprinklers, and extinguishers?
Response: The Caretaker is responsible for ensuring all required inspections are properly completed as outlined in Appendix C of the solicitation.
#31. Are hurricane preparation and post-storm cleanup included in the fixed price?
Response: No, this work is not included in the contract/solicitation.
#32. What is the basis of award (lowest price technically acceptable or best value), and how are the factors weighed against price? Section 5 lists Factors 1 through 4 but does not state the basis for award. Will award be made on a best value tradeoff or on a lowest price technically acceptable basis? What is the relative importance of the non-price factors compared with price? How will price be evaluated: the total of the base and all four option periods, or the base period only?
Response: Basis of Award - Award will be made to the responsible offeror whose quote conforms to the requirements of the solicitation and is determined to be the best value to the Government. The offeror must be responsible according to the requirements in RFO 9.104-1. In addition, the quote must be determined to be acceptable, and the quote must comply in all material respects with the requirements of law, regulation, and the conditions set forth in this solicitation to be eligible for award. The Government will evaluate quotes for award purposes by adding the total of all CLIN prices, including all options, to ensure that pricing is not unbalanced. Price will be evaluated for completeness and reasonableness. The Government intends to make award on the basis of initial quotes, without discussions or any opportunity to make further submission. Each initial offer should contain the Offeror’s best terms from a price and technical standpoint. All evaluation factors (technical approach, caretaker services contract experience, safety and quality control, and past performance) other than price, when combined, are greater than price.
#33. When will the contractor be required to complete the property inventory after award (e.g., 14 days after the transition period)?
Response: Yes, property inventory will be required to be complete within 14 calendar days after the end of the transion period.
#34. Factor 2 asks for caretaker projects completed in the last five years. Will ongoing projects with at least one year of performance be considered?
Response: Yes, ongoing projects with at least one year of performance may be included in the RFQ response for consideration.
#35. Please provide the current staffing levels, if releasable.
Response: Staffing levels shall be as required to meet the requirements outlined in the Performance Work Statement.
#36. Price format: Is a breakdown of the monthly price required (labor, subcontracts, other direct costs), or only the monthly price for each CLIN?
Response: The breakdown of the monthly price for the CLIN amount is required.
#37 Wage Determination: Please confirm that WD 2015-5177 (Rev 32) applies, and whether the current workforce is covered by a collective bargaining agreement. If there is a Collective Bargaining Agreement applicable to this contract, can the government provide a copy?
Response: The Wage Determination, WD 2015-5177 (Rev 32) is applicable for this requirement. No Collective Bargaining Agreement is applicable for this requirement.
#38. Please confirm the requirement is for unarmed security only, with a minimum of two guards on duty at all times, 24/7, including holidays. Are post orders available?
Response: For Security personnel requirements reference Section IV Performance Work Statement, Paragraph 1.
#39. Must the security subcontractor hold its Louisiana security agency license at quote submission, at award, or by the start of performance?
Response: Security licences are not required with quotation submissions. For the awarded vendor, security licence documentation submission will be required by the end of the transition period.
#40. Please provide the current rental agreements, equipment inventory, and recent invoices for the eight temporary HVAC units. Must the awardee assume the existing agreements, or may it arrange equivalent replacement rentals? Please also clarify responsibility for installation, removal, accessories, and maintenance. . Regarding the HVAC Equipment rental, could you identify who the equipment is rented from? Is the lease agreement transferable? Is the rental cost of the temporary HVAC units reimbursed separately, or included in the monthly price? Please provide the current rental vendor, monthly cost and rental term, and indicate whether the current rental agreement will transfer to the new contractor. If offerors are required to incorporate HVAC equipment rental expenses into their FFP pricing, will the Government provide the existing rental agreements, including the current rental rates, payment terms, and remaining agreement durations? At a minimum, please provide a complete inventory of the rented equipment, including the quantity, equipment type, manufacturer/model, capacity/specifications, and applicable rental periods, to enable offerors to develop accurate and competitive pricing.
Response: The rental cost should be included in the FFP monthly price.
The current HVAC rental equipment and vendor information will not be provided at this time.
There is no requirement to use the current HVAC rental vendor. The current rental agreement will not transfer. See the PSW for HVAC system specifications and maintence requirements.
#41. Who ensures the rental equipment (HVAC Units)?
Response: The caretaker is responsible for the HVAC rental equipment. Rental equipment could be covered by Insurance provided from the rental company. The cost of the rental equipment included in the submitted quote will cover all related cost fo the HVAC rental.
#42. Are the rental HVAC units and rental generators included in the monthly utility costs?
Response: There will be one monthly fixed amount for all cost including the HVAC rental and utilities.
#43. Factor 4 asks offerors to identify projects performed as the prime. Will the Government consider projects performed as a joint venture partner, or by a proposed subcontractor for its portion of the work (for example, security)?
Response: Yes, if officially recognized as a joint venture entity, projects performed as a joint venture partner/subcontractor will be considered.