Attachment 001 - Site Visit Meeting Minutes.pdf
PDF 301 KB Posted
- Attached to
- Replace Roofing Staff Housing - FCI Safford
- Solicitation number
- 15B60924Q00000008
- Issued by
-
Department of Justice Bureau of Prisons
About this file
This document contains the Site Visit Meeting Minutes for a Request for Quote (RFQ) to Replace Roof Staff Housing at the Federal Correctional Institution (FCI) in Safford.
The key details are:
- The RFQ number is 15B60924Q00000008.
- The purpose of the site visit was to familiarize contractors with the unique requirements of a correctional setting. No additional information beyond the issued solicitation was provided.
- Work hours are 7:30 AM to 3:30 PM, Monday through Friday, excluding weekends and federal holidays. Contractors are responsible for understanding the working hours and conditions.
- All questions must be submitted via email to the Supervisory Contract Specialist by July 19, 2024, to allow sufficient time for responses prior to the bid due date.
- Construction materials and tools must be stored in a designated area agreed upon with the Contracting Officer's Representative (COR). Strict accountability and control of all contractor tools and hazardous materials must be maintained.
- The scope includes removal and replacement of the flat and pitched roof sections of the staff housing complex, including new shingles, fascia, soffit, gutters, and other related work. The housing will remain occupied during construction.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SITE-VISIT MEETING MINUTES
RFQ: 15B60924Q00000008 Replace Roof Staff Housing
FCI Safford
Date: Tuesday, July 16, 2024, at 9:00a.m. MST
Contracting Officer Nicasio Garcia:
I. Introductions:
Introductions with all attendees.
Attendance:
Representing the Government:
Nicasio Garcia, Supervisory Contract Specialist Tucker Lucas, General Foreman Christopher Cleland, Engineering Technician
Representing Vendors:
Jonathan Prellwitz – Rock Roofing Jesus Santana – Rock Roofing Jace Howard – AZ Tech Contracting Corey Taylor – Copper Sky Roofing Seth Carsen – AZ Tech Contracting Emilio Verdugo – Big Buckle Roofing
II. Purpose of Site Visit:
Familiarize the contractor with the unique circumstances and requirements surrounding a correctional setting. This visit is also to explain the solicitation, as issued, and not to furnish additional information.
State - nothing said during the visit shall be interpreted as a change to the solicitation without the issuance of a formal amendment through the Supervisory Contract Specialist, Nicasio Garcia.
III. MINUTES:
Minutes will be recorded and distributed via www.sam.gov.
IV. SITE VISIT INFORMATION:
Walk to selected site for Replacing Staff Housing Roofing immediately following introductions. The tour was greeted with a reminder that any questions posed throughout the visit needed to be addressed via amendment to solicitation, to allow all potential bidders availability of the questions and answers.
SITE-VISIT MEETING MINUTES
RFQ: 15B60924Q00000008 Replace Roof Staff Housing
V. General Topics:
• Work Hours: Work Hours for the contractor are 7:30 AM – 3:30 PM, Monday - Friday, excluding weekends and federal holidays. It shall be the responsibility of the Contractor to familiarize himself, his employees, and his subcontractors of the working hours and conditions in the correctional facility, as working hours may not constitute a full eight-hour workday.
• Questions: Oral questions asked at Site Visit of a technical nature are not acceptable due to the possibility of misunderstanding or misinterpretation. All questions shall be sent via email to Nicasio Garcia, Supervisory Contract Specialist. To provide sufficient response time prior to the bid due date, the Government has establishing that questions be submitted no later than Friday, July 19, 2024.
• Storage of Materials: All construction materials/tools shall be stored in a designated area mutually agreed upon between the COR and the contractor.
• Tool Accountability: Strict accountability and control of all contractor tools and hazardous materials must be always maintained. All contractor tools to be used outside the secure perimeter must be inventoried and accounted for at the conclusion of the workday. Contractor tools may not be stored on-site overnight. The contractor should provide for enough time at the conclusion of the workday for the return and accounting of all tools issued during the workday.
Lost or missing tools must be reported to the COR the Captain immediately.
Meeting minutes recorded by:
Nicasio Garcia, Supervisory Contract Specialist
NOTICE:
MEETING MINUTES ARE PROVIDED FOR INFORMATIONAL PURPOSES ONLY. THEY ARE NOT
INTENDED TO CHANGE ANY SPECIFICATIONS, TERMS OR CONDITIONS OF THE
SOLICITATION. ANY AND ALL CHANGES TO THE SOLICITATION SHALL BE ISSUED IN
SUBSEQUENT AMENDMENTS ISSUED BY THE CONTRACTING OFFICER ON A STANDARD
FORM 1449 (SF-1449).