This is a Statement of Work (SOW) for WFO (Weather Forecast Office) and NEXRAD UPS Battery Replacements under a NOAA roof replacement project in Cheektowaga, NY. The SOW outlines eight deliverables with specific timelines and responsible parties for project execution and closeout.

The contractor must submit a Draft Project Plan and Schedule within thirty calendar days after award, followed by a Final Project Plan and Schedule within thirty business days after the Post Award Conference. Additional deliverables include submittals as identified in the Project Schedule, daily verbal site completion updates before leaving the site, and weekly field activity reports submitted within three business days after each week's work. The contractor is responsible for monthly progress reports, manufacturer's warranty inspection and government walkthrough as identified in the schedule, and closeout documents including UL lightning protection system re-certification, operations and maintenance manuals, and as-built drawings. The Contracting Officer's Representative (COR) and Logistics Point of Contact (LPOC) serve as the primary distribution recipients for all deliverables.

View the file

Other files

Show all 11

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Rev. 05 19 2023.0

NATIONAL OCEANIC AND ATMOSPHERIC ADMINISTRATION (NOAA)

STATEMENT OF WORK (SOW) FOR WFO and NEXRAD UPS Battery Replacements

ITEM
SOW REFERENCE
DELIVERABLE / EVENT
DUE BY

DISTRIBUTION

1
4.6 / 4.7
Draft Project Plan & Schedule Discussion

Post Award Conference

Within thirty (30) calendar days after date of award
COR
2
4.6
Final Project Plan & Schedule
Within thirty (30) business days after Post Award Conference
COR
3
2.1
Submittals
As identified in the Project Schedule
COR
4
4.8
Site Completion Update
Daily Verbal: before leaving site
COR, LPOC
5
4.8
Site Completion Field Activity Report
Weekly within three (3) business days after the following week’s work

COR, LPOC

6
4.9
Progress Reports
Monthly within three (3) business days after the following week’s work
COR
7
2.5
Manufacturer’s Warranty Inspection and Government Walkthrough
As identified in the Project Schedule (punch list, acceptance, documentation)

COR

2.6
Closeout Documents
UL lightning protection system re-certification, O&M manuals, as-builts
COR