142010-26-0138_BUF_UA_Observatory_Roof_Replacement_Statement_of_Work_Attachment_6.docx
DOCX document 39 KB Posted
- Attached to
- Roof Replacement Cheektowaga, NY
- Solicitation number
- 1305M326Q0358
About this file
This is a Statement of Work (SOW) for WFO (Weather Forecast Office) and NEXRAD UPS Battery Replacements under a NOAA roof replacement project in Cheektowaga, NY. The SOW outlines eight deliverables with specific timelines and responsible parties for project execution and closeout.
The contractor must submit a Draft Project Plan and Schedule within thirty calendar days after award, followed by a Final Project Plan and Schedule within thirty business days after the Post Award Conference. Additional deliverables include submittals as identified in the Project Schedule, daily verbal site completion updates before leaving the site, and weekly field activity reports submitted within three business days after each week's work. The contractor is responsible for monthly progress reports, manufacturer's warranty inspection and government walkthrough as identified in the schedule, and closeout documents including UL lightning protection system re-certification, operations and maintenance manuals, and as-built drawings. The Contracting Officer's Representative (COR) and Logistics Point of Contact (LPOC) serve as the primary distribution recipients for all deliverables.
View the file
Other files
Show all 11
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Rev. 05 19 2023.0
NATIONAL OCEANIC AND ATMOSPHERIC ADMINISTRATION (NOAA)
STATEMENT OF WORK (SOW) FOR WFO and NEXRAD UPS Battery Replacements
| ITEM |
| SOW REFERENCE |
| DELIVERABLE / EVENT |
| DUE BY |
DISTRIBUTION
| 1 |
| 4.6 / 4.7 |
| Draft Project Plan & Schedule Discussion |
Post Award Conference
| Within thirty (30) calendar days after date of award |
| COR |
| 2 |
| 4.6 |
| Final Project Plan & Schedule |
| Within thirty (30) business days after Post Award Conference |
| COR |
| 3 |
| 2.1 |
| Submittals |
| As identified in the Project Schedule |
| COR |
| 4 |
| 4.8 |
| Site Completion Update |
| Daily Verbal: before leaving site |
| COR, LPOC |
| 5 |
| 4.8 |
| Site Completion Field Activity Report |
| Weekly within three (3) business days after the following week’s work |
COR, LPOC
| 6 |
| 4.9 |
| Progress Reports |
| Monthly within three (3) business days after the following week’s work |
| COR |
| 7 |
| 2.5 |
| Manufacturer’s Warranty Inspection and Government Walkthrough |
| As identified in the Project Schedule (punch list, acceptance, documentation) |
COR
| 2.6 |
| Closeout Documents |
| UL lightning protection system re-certification, O&M manuals, as-builts |
| COR |