This is Addendum 4 to an Invitation for Bid issued by Jacksonville Electric Authority (JEA) for the purchase, fabrication, and delivery of spun concrete transmission poles for the New World Substation 230kV Transmission Line project. The addendum clarifies specifications for Structure Number 068-954, correcting the pole designation from a 120'/25' - 24kip pole to a 120'/25' - 36kip pole, as indicated in the PLS-Pole model and consistent with JEA's Bid Summary Sheet. The original solicitation encompasses 32 poles across eleven line items, ranging from 120 to 125 feet in length with load ratings between 20 and 36 kip. The mandatory pre-response meeting was held on September 29, 2026 at 1:00 PM EST, and bids are due October 13, 2026 at 12:00 PM EST. This is a one-time purchase with no renewal options, and JEA reserves the right to award one or multiple contracts at its discretion based on the lowest responsive and responsible bidder.
All poles must be centrifugally spun concrete with circular cross-sections, spiral steel reinforcement, and specific dimensional requirements including tip diameters between 15 and 21 inches and minimum wall thickness of 3.5 inches. Concrete must achieve 28-day compressive strength of 8500 psi with a maximum water-cement ratio of 0.40. Bidders must be pre-qualified manufacturers on JEA's Approved Manufacturers List, currently limited to Valmont and Trinity Meyer, and cannot appear on Florida's Convicted Vendor List, Suspended Vendor List, or Jacksonville's Disqualified Vendor List. Bid security of 5% of the bid amount and 100% contract bond are required. Goods are warranted free from defects for two years from delivery, with DDP destination pricing covering all packaging, marking, and transportation costs. JEA offers optional payment terms of 1% discount within 20 days or net 30, or 2% discount within 10 days or net 30. Insurance requirements include workers' compensation, commercial general liability ($1 million each occurrence / $2 million aggregate), automobile liability ($1 million combined single limit), and excess/umbrella liability ($1 million), with JEA named as additional insured. Bidders must acknowledge receipt of this addendum on their proposal forms.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 066A-954.lca | — | |
| 065-960.bak | BAK file | |
| 066-960.bak | BAK file | |
| 050 - 960.lca | — | |
| 084-954.lca | — | |
| 048 - 960.bak | BAK file | |
| 084 - 954.bak | BAK file | |
| C1261.lca | — | |
| 083-954.lca | — | |
| 068-954.lca | — | |
| 083 - 954.bak | BAK file | |
| 065-960.lca | — | |
| 066A-954.bak | BAK file | |
| 079 - 954.bak | BAK file | |
| C1261.bak | BAK file | |
| 1412223278 Addendum 3.pdf | ||
| 067-954.lca | — | |
| 068-954.bak | BAK file | |
| 066B-960.lca | — | |
| 079-954.lca | — | |
| 050 - 960.bak | BAK file | |
| 067-954.bak | BAK file | |
| 1412223278 Addendum 2.pdf | ||
| 048 - 960.lca | — | |
| 1412223278 Appendix B - Bid Forms.pdf | ||
| 1412223278 Solicitation.pdf | ||
| Project Specific Tech Specs for the New World Substation 230kV (Spun Concrete Poles) 07.30.26.pdf | ||
| GENERAL TECH SPECS SPUN CONCRETE (rev 1.3).pdf | ||
| 1412223278 Addendum 1.pdf |
Show all 29
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Procurement Department Bid Section
October 7, 2026
ADDENDUM NUMBER: FOUR (4)
TITLE: 1412223278 (IFB) Spun Concrete Transmission Poles for The New World Substation 230kV Transmission Line
PROPOSAL DUE DATE: October 13, 2026
TIME OF RECEIPT: 12:00 PM EST
THIS ADDENDUM IS FOR THE PURPOSE OF MAKING THE FOLLOWING CHANGES OR
CLARIFICATIONS:
1. Question: Can JEA confirm that Structure Number 068-954 – 120’/25’ is a 24kip Pole as listed on their Bid Summary Sheet.
The PLS-Pole model provided is modeling said structure with a 120’/25’ – 36kip pole.
Answer: Structure 068-954 should be a 120'/25' - 36kip pole.
ACKNOWLEDGE RECEIPT OF THIS ADDENDUM ON THE PROPOSAL FORM.