1412206079 Appendix A - Scope of Work.pdf

PDF 2 MB Posted

Attached to
Progressive Design-Build Services for the Brandy Branch to Normandy 230kV Transmission Line
Solicitation number
1412206079
Issued by
Duval County, Florida

About this file

This Scope of Work document outlines the requirements for the Jacksonville Electric Authority (JEA) progressive design-build project to construct a new 230kV transmission line circuit (Circuit 979) connecting the Brandy Branch Substation at 15701 Beaver Street West, Jacksonville, Florida 32234 to the Normandy Substation at 9801 Crystal Springs Road, Jacksonville, Florida 32221. The project encompasses all engineering, permitting, surveying, design, structure and material procurement, and construction services necessary to install the overhead transmission circuit. The solicitation deadline for qualified design and construction teams is September 15, 2026. The project utilizes a progressive design-build delivery method, which allows for concurrent design and construction phases to streamline the overall project timeline and facilitate coordination between design and construction activities.

The scope of work document establishes the technical and contractual framework for bidders to understand project requirements, including engineering standards, permitting obligations, material specifications, and construction methodologies. Specific pricing terms, payment structures, and funding sources are to be detailed in the main solicitation documents. The progressive design-build approach typically involves an initial design phase followed by construction, with opportunities for value engineering and cost optimization throughout the project lifecycle. Contractors must demonstrate experience in transmission line design and construction, particularly with high-voltage systems, and must be capable of managing multiple disciplines including civil works, structural design, electrical engineering, and construction management.

View the file

Other files

Show all 14

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

1412206079 Appendix A Scope of Work Page 1 of 18

1412206079 Appendix A – Scope of Work

Progressive Design-Build Services for the Brandy Branch to Normandy 230kV Transmission Line

SECTION 1: OBJECTIVES AND DESCRIPTION OF PROJECT

1.1 General

JEA is seeking experienced and qualified design and construction teams to perform all engineering, permitting, surveying, design, structure/material procurement, and construction services needed to install a new overhead 230kV transmission circuit, designated as circuit 979, from the existing JEA Brandy

Branch substation located at 15701 Beaver St. W, Jacksonville FL, 32234 to the existing JEA Normandy

Substation located at 9801 Crystal Springs Road, Jacksonville FL, 32221. The project location is shown below in Figure 1.

Figure 1: Existing Transmission System Map Location

1.2 Background

JEA’s transmission system has been historically designed to transfer generated power at Brandy Branch

230 kV, and imported power through FP&L’s Duval substation, eastward using transmission circuit 940, 941, 944, 957, and 954 into Normandy 230 kV and Jax Heights 230 kV substations. JEA’s 2026 Ten Year

Site Plan filed with the Florida Public Service Commission indicates the importance of increasing this transmission capacity as JEA’s resource mix changes and native load increases in the future. Electric

T&D Planning has completed transmission studies indicating that the shared transmission poles for circuits 940 and 941 could present a transmission capacity concern. The loss of a single shared pole will result in both lines being out-of-service simultaneously, leading to overload conditions on circuits 944 and 957 during peak-load scenarios. Electric T&D Planning is requesting a new transmission circuit between the Brandy Branch 230 kV and the Normandy 230 kV substation to be built on dedicated transmission poles, to provide another eastward path for power into JEA and strengthen the transmission system in this area.

1412206079 Appendix A Scope of Work Page 2 of 18

1.3 Brandy Branch to Normandy 230kV Line Route Study Report

JEA hired an engineering firm, Chen Moore and Associates, to perform a high-level route study for a new high ampacity overhead 230kV transmission circuit between the Brandy Branch and Normandy substations. The study evaluated route options for a new transmission circuit that met the following criteria:

- The new circuit must utilize a high-performance conductor and hardware capable of providing a summer continuous rating between 2500-3000 amps.

- Avoid double circuit construction on common structures

- Tie in existing circuit 941(future circuit 975 once the Miller Interconnect is placed into service in

August 2026) to existing circuit 936 and bypass the Normandy Substation.

- Minimize environmental and social impacts

- Ensure compliance with national and local permitting requirements

Various route segments were analyzed as shown below in Figure 2.

Figure 2: Analyzed Route Segments

Upon completion of the route study, route option 1 was recommended as the preferred alignment because it avoids densely populated areas, minimizes environmental impacts, and follows existing utility and transportation corridors. Route Option #1 is shown below in Figure 3. As illustrated, this route represents the preferred alignment for the new circuit for which JEA is now seeking design and construction services. The design and construction team should take into consideration the Brandy Branch to

Normandy 230kV Line Routing Report and recommend to JEA the final route for the Brandy Branch to

Normandy project. The design and construction team must account for and be capable of designing and constructing the project as illustrated in route option #1 if directed to do so by JEA.

1412206079 Appendix A Scope of Work Page 3 of 18

Figure 3: Recommended Route Option#1

1.4 Conductor Study Analysis Report

JEA hired an engineering firm, Chen Moore and Associates, to perform a conductor study to identify a new high performance, low sag, high temperature conductor to be added to JEA’s standard conductors for new 230kV construction. The goal is to use this new high-performance conductor to build the proposed new 230kV circuit 979 between the Brandy Branch and Normandy substations. The selected new conductor will also be used on future 230kV transmission greenfield and brownfield projects. The new conductor will be used in place of JEA’s standard 1590 ACSR “Falcon” conductor. Since the chosen conductor will be used in the future to reconductor other existing 230kV circuits, the new conductor must meet the following requirements to avoid and/or reduce the need for future pole replacements by reducing structure loads when compared to the standard 1590 ACSR “Falcon” conductor:

- Must have similar or smaller diameter (1.545 inches)

- Must have similar or smaller weight/foot (2.0421 lbs/ft)

- Must have similar or higher rated breaking strength (54,500 lbs)

- Must have similar or smaller sags at maximum rated temperature

- Must provide a minimum continuous rating between 2,500 and 3,000 Amps (3,000 Amps is preferred) using JEA’s rating methodology as identified in JEA-FAC-008 documents.

- Must consider overall costs (purchase price, maintenance costs, supporting hardware costs, etc.)

- Must consider lead times and availability for this specific circuit 979 installation

- Must consider overall impacts (ease of installation, material handling, availability, reliability, track record, reputation, etc.)

Per the study and at the time of its completion, Chen Moore and Associates recommended that JEA utilize either the 2118 TS “Blanca” M9 or the 1590 Southwire ACCS/TW/C7 “Zion” conductor. The design and construction team should take into consideration the Conductor Study Report and recommend to JEA the conductor to be used on the circuit 979 Brandy Branch to Normandy and future projects. A list of top considered conductors is shown below in Figure 4; however, the design and construction team may also consider a conductor that is not listed.

1412206079 Appendix A Scope of Work Page 4 of 18

Figure 4: Summary of top conductors considered

1.5 Project Description

The project will modify the existing circuit configurations between JEA’s existing Brandy Branch, Normandy, and SJRPP substations, while also upgrading conductor and existing infrastructure. For reference, the existing circuit configuration is shown below in figure 5. Please note that not all circuits are shown for simplicity. The objectives of the project are as follows:

Figure 5: Existing Circuit Configuration

1412206079 Appendix A Scope of Work Page 5 of 18

1.5.1 The project shall construct approximately 8.3 miles of new 230kV transmission circuit 979 between the existing Brandy Branch substation and the intersection of existing circuit 936 with

Beaver Street, utilizing a new high-performance conductor (see section 1.4 above). The routing of this new circuit shall consist of segments BBN01, BBN02, BBN06, BBN08, BBN12, AND

BBN17 (see section 1.3 above). An alternate route path may be proposed and recommended to

JEA by the design and construction team.

1.5.2 Existing circuit 936 from SJRPP to Normandy and existing circuit 941(soon to be 975) from

Miller to Normandy, shall be split at their respective W Beaver Street crossings. Approximately

0.82 miles of new 230kV transmission circuit shall be built between the split of circuit 941 (soon to be 975) and the split of circuit 936, combining the two circuits together to form new circuit 936 from Miller to SJRPP. New high-performance conductor shall be utilized to connect the two circuits together over the 0.82-mile section, the reminder of the circuits will remain as-is. For clarity, this new section of circuit 936 is shown in yellow, below in figure 6.

Figure 6: New Section of Circuit 936

1.5.3 A section of existing circuit 941 (soon to be 975) from the W Beaver Street crossing to the

Normandy substation shall be either removed or abandoned in place. If abandoned, the conductors shall be dead ended where applicable, and the span directly into the Normandy substation shall be removed. For clarity, this to be abandoned or removed section of circuit 941

(soon to be 975) is shown in dashed yellow, below in figure 7.

Figure 7: To be Abandoned or Removed Circuit 941/975

1412206079 Appendix A Scope of Work Page 6 of 18

1.5.4 An approximately 0.8-mile section of existing circuit 936 from the W Beaver Street crossing to the Normandy substation shall be rebuilt with new high ampacity conductor and new independent pole structures. This new section shall be connected to the reminder of circuit 979, shown in yellow, below in figure 8. Existing circuit 947 will need to be modified at the crossing of W

Beaver Street, so that new circuits 979 and 936 can cross it, shown in orange, below in figure 8.

Circuit 947 that currently shares structures with circuit 936, shall be separated so that new circuit

979 does not share any common structures with existing circuit 947. Where feasible existing structures shall be reused for either new circuit 979 or existing circuit 947 to the extent possible, while meeting EMF and clearance requirements.

Figure 8: Circuits 947 Crossing and 936 Rebuild

1.5.5 To meet the Electric and Magnetic Field (EMF) requirements per the Florida Administrative

Code, Chapter 62-814, it is expected that existing sections of circuit 832 from the Moncrief

Switching Station to the Normandy Substation and circuit 835 from the Ritter Park Substation to the Normandy Substation will need to be rebuilt from the W Beaver Street crossing to the

Normandy Substation, shown in yellow, below in figure 9. If required, both Circuits shall be rebuilt utilizing a configuration that is most feasible on new pole lines with standard 954 ACSR

“Cardinal” conductors and 3#6 AW shield wires. In addition, circuit phase orientation of circuits

832, 835, 920, 921, 927, 936, 940, 941, and 947 may need to be rearranged to meet EMF requirements for the corridors impacted by this project.

Figure 9: Circuits 832 and 835 Rebuild

1412206079 Appendix A Scope of Work Page 7 of 18

1.5.6 The project shall include the construction of a new A-frame termination structure, PTs, conduit, cables, and a new breaker at The Brandy Branch Substation to facilitate the addition of new circuit 979. Circuit 941 will need to be modified and moved onto the new A-frame termination, shown in orange, below in figure 10. New Circuit 979 will terminate at the existing A-frame of circuit 941, shown in yellow, below in figure 10.

Figure 10: Brandy Branch Modifications

1.5.7 The construction of new Circuit 979 will tie in the new circuit into the Normandy Substation at the current termination point of existing circuit 936, shown in yellow in figure 11 below. To improve reliability, the termination of circuit 940 will need to swap bays with the termination of circuit 941 (soon to be 975). Circuit 940 will need to be modified and moved onto the existing A-frame termination of the to be abandoned/removed circuit 941 (soon to be 975), shown in orange in figure 11 below.

Figure 11: Normandy Modifications

1412206079 Appendix A Scope of Work Page 8 of 18

1.5.8 The construction of new Circuit 979 is expected to require the crossing of existing circuits 940, 941, 947, and 975 at several locations. At two (2) locations, at the Miller Interconnect and at the intersection of Otis Road, it is expected that there will be double circuit crossings. At crossings of double circuits, the new circuit should cross underneath the double circuits, where feasible.

At project completion, the final orientation of the circuits shall be as shown below in figure 12. The desired In-Service-Date is 9/29/2028.

Figure 12: Proposed Circuit Configuration

SECTION 2: SCOPE OF SERVICES

JEA intends to award one (1) contract to the most highly qualified team that meets the minimum qualifications to submit a proposal and with which JEA can successfully negotiate a contract. The project delivery method will be a progressive design build, with the goal of substantially completing the project in its entirety by September 29th, 2028. The desired in-service date is aggressive as JEA needs circuit 979 to be placed in service as soon as possible. However, given current material lead times, JEA will consider and accept a later in-service date if identified as such in the bid documents. New Transmission structures, framing materials, insulators, conductors, shield wire, and any other miscellaneous materials shall be procured by the bidder. All labor, construction materials, and equipment needed to complete the project shall be supplied by the bidder. JEA will provide PLS-CADD models and any other existing historical structure / foundation drawings and/or models that exist upon award of the contract or shortly thereafter.

JEA has or expects to have the following files available:

- PLS-CADD LiDAR models from 2022 of Circuits 832, 835, 921, 927, 936, 940, 941, and 947 o Files to be provided after award.

- Transmission construction drawings for the Miller Interconnect, currently under construction.

1412206079 Appendix A Scope of Work Page 9 of 18 o File will be provided during the bid. The file name is “Miller Interconnect Drawings –

TR1400"

- PLS-CADD design file for the Miller Interconnect.

o The PLS-CADD backup file will be provided during bid. The file name is “JEA Miller

230kV Interconnection with FRP Structure 061726.bak”.

- PLS-CADD LiDAR survey of the proposed route option #1 identified in the route study, flown on 2/7/2026, along with associated weather data.

o PLS-CADD backup file to be provided during bid. Transmission circuit ampacity data and weather data is available and will be provided after award. The file name is

“JEA_Brandy_Branch_Normandy_2026_02_07.bak”

- Any available drawings for circuits 832, 835, 940, 941, 947, 975 and 936 o Files to be provided after award. It is anticipated that some files will be unavailable, such as existing pole strength data for some or all circuits, which will need to be estimated.

- Brandy Branch to Normandy 230kV Line Route Study Report performed by Chen Moore and

Associates.

o The report is being provided as-is, please see the disclaimer in report. The file name is

“Brandy Branch to Normandy Route Study”.

- Conductor Study Analysis Report performed by Chen Moore and Associates.

o The report is being provided as-is, file name is “Conductor Study Analysis Report”.

- Sketch and Description of a proposed easement on parcel RE #001648-0010, to be purchased by

JEA Real Estate o File will be provided during bid. The file name is “Proposed Easement for Parcel

001648-0010".

- Sketch and Description of a proposed easement on parcel RE #006840-0000, to be purchased by

JEA Real Estate. Only a portion of this easement will be purchased, exact size to be determined.

o File will be provided during bid. The file name is “Proposed Easement for Parcel

006840-0000".

During all phases of construction and inspection, work hours on site shall be as directed by any permits.

Typical workdays shall be from Monday to Friday 7:00 am to 5:00 pm.

2.1 Existing Conductors and Ratings:

The following are existing conductors and ratings of circuits that will be impacted by this project. The ratings of each circuit are per official JEA FAC-008 documents. Ratings of existing circuits will need to be considered and accounted for when performing Electric and Magnetic Field (EMF) calculations that will be needed per the Florida Administrative Code, Chapter 62-814.

2.1.1 Circuit 832 existing conductor and rating:

Circuit 832 is a 138kV circuit presently built with 954 ACSR “Cardinal” phase conductors and

3#6 AW shield wires. The maximum continuous summer rating for this circuit is 1091 amps, with an emergency 10-minute rating of 1397 amps, both at 1800F. The maximum continuous winter rating for this circuit is 1420 amps, with an emergency 10-minute rating of 1891 amps, both at

1800F.

2.1.2 Circuit 835 existing conductor and rating:

Circuit 835 is a 138kV circuit presently built with 954 ACSR “Cardinal” phase conductors and

3#6 AW shield wires. The maximum continuous summer rating for this circuit is 1209 amps, with an emergency 10-minute rating of 1550 amps, both at 2000F. The maximum continuous winter

1412206079 Appendix A Scope of Work Page 10 of 18 rating for this circuit is 1501 amps, with an emergency 10-minute rating of 2001 amps, both at

2000F

2.1.3 Circuits 921, 927, 936, 940, 941, and 947 existing conductors and ratings:

Circuit 921, 927, 936, 940, 941, and 947 are 230kV circuits presently built with 1590 ACSR

“Falcon” phase conductors and 3#6 AW shield wires. The maximum continuous summer rating for all these circuits is 1676 amps, with an emergency 10-minute rating of 2080 amps, both at

2000F. The maximum continuous winter rating for this circuit is 2080 amps, with an emergency

10-minute rating of 2400 amps, both at 2000F

2.2 Proposed Conductors and Ratings:

The following are proposed conductors and ratings of circuits that shall be used for the project. Ratings of circuits at their final configurations will need to be considered and accounted for when performing

Electric and Magnetic Field (EMF) calculations that will be needed per the Florida Administrative Code, Chapter 62-814.

2.2.1 Circuit 832 proposed conductor and rating:

Circuit 832 is a 138kV circuit, a section of this circuit is to be rebuilt from W Beaver Street to the

Normandy Substation with 954 ACSR “Cardinal” phase conductors and 3#6 AW shield wire. The maximum continuous summer rating for this circuit will remain at 1091 amps, with an emergency

10-minute rating of 1397 amps, both at 1800F. The maximum continuous winter rating for this circuit will remain at 1420 amps, with an emergency 10-minute rating of 1891 amps, both at

1800F.

2.2.2 Circuit 835 proposed conductor and rating:

Circuit 835 is a 138kV circuit, a section of this circuit is to be rebuilt from W Beaver Street to the

Normandy Substation with 954 ACSR “Cardinal” phase conductors and 3#6 AW shield wire. The maximum continuous summer rating for this circuit will remain at 1209 amps, with an emergency

10-minute rating of 1550 amps, both at 2000F. The maximum continuous winter rating for this circuit will remain at 1501 amps, with an emergency 10-minute rating of 2001 amps, both at

2000F.

2.2.3 Circuits 921 and 927 proposed conductor and rating:

Circuits 921 and 927 are 230kV circuits presently built with 1590 ACSR “Falcon” phase conductors and 3#6 AW shield wires. These circuits shall remain as-is. The maximum continuous summer rating for all these circuits will remain at 1676 amps, with an emergency 10-minute rating of 2080 amps, both at 2000F. The maximum continuous winter rating for these circuits will remain at 2080 amps, with an emergency 10-minute rating of 2400 amps, both at 2000F

2.2.4 Circuits 936 and 941(soon to be 975) proposed conductor and rating:

Circuits 936 and 941 (soon to be 975) are all 230kV circuits, a new section of circuit, connecting existing circuit 936 to circuit 941 (soon to be 975), is to be built with new high-performance phase conductors and 3#6 AW shield wire. The maximum summer rating for the final circuit will still be limited by existing sections that are not to be rebuilt at this time. The maximum summer rating for this circuit will remain at 1677 amps, with an emergency 10-minute rating of 2080 amps, both at 2000F. The maximum continuous winter rating for this circuit will remain at 2080 amps, with an emergency 10-minute rating of 2400 amps, both at 2000F

2.2.5 Circuit 940 and 941 proposed conductor and rating:

1412206079 Appendix A Scope of Work Page 11 of 18

Circuits 940 and 941 are 230kV circuits presently built with 1590 ACSR “Falcon” phase conductors and 3#6 AW shield wires. These circuits shall be modified as needed to cross underneath or over the new proposed circuit 979. The maximum summer rating for these circuits will remain at 1677 amps, with an emergency 10-minute rating of 2080 amps, both at 2000F. The maximum continuous winter rating for this circuit will remain at 2080 amps, with an emergency

10-minute rating of 2400 amps, both at 2000F

2.2.6 Circuit 947 proposed conductor and rating:

Circuit 947 is a 230kV circuit presently built with 1590 ACSR “Falcon” phase conductors and

3#6 AW shield wires. This circuit currently shares structures with circuit 936. This circuit shall be separated from circuit 936, utilizing existing structures and conductors if feasible. Circuit 947 shall also be modified so that circuit 979 and 936 can cross over it. The maximum summer rating for this circuit will remain at 1677 amps, with an emergency 10-minute rating of 2080 amps, both at 2000F. The maximum continuous winter rating for this circuit will remain at 2080 amps, with an emergency 10-minute rating of 2400 amps, both at 2000F

2.2.7 Circuit 979 proposed conductor and rating:

Circuit 979 will be a new 230kV circuit built with new high-performance conductors and 3#6

AW shield wires. Circuit 979 shall also be designed and constructed with a new underbuilt ADSS

144 Count Fiber Optic Cable. This circuit will connect to a section of existing circuit 936, which will need to be entirely rebuilt. The maximum summer rating for this circuit shall be between

2,500 – 3,000 amps at a to be determined Maximum Operating Temperature. The Emergency and

Winter ratings are to be determined during design.

2.3 Outages:

During design, the bidder shall develop, with close input from JEA’s SOCC (System Operations and

Control Center), the JEA Transmission Planning Department, and the consultant’s contractor, a proposed feasible outage schedule. The design needs to consider construction techniques and outage durations on all existing circuits. The winning bidder will need to come up with a design solution with their contractor’s input that limits outage durations. Outages are typically most feasible in the Spring and Fall months. An addendum will be issued during the bid to demonstrate JEA’s anticipated outage schedule.

2.4 Engineering and Construction Scope of Work:

2.4.1 Scope:

The scope of work includes the pursuit of all site investigations, badge access (JEA Badge access to JEA Substations), surveys, site design, transmission design, substation design, foundation and geotechnical engineering, electrical design, grounding design, all permitting, post design construction inspection services, post design engineering aid during construction, construction services, all material procurement, as-built surveys, and as-built LiDAR models for circuits 832, 835, 936, 940, 941, 947, 975 and 979. The project location is in Duval County, between the

Brandy Branch Substation located at 15701 Beaver St. W, Jacksonville FL, 32234 and the existing JEA Normandy Substation located at 9801 Crystal Springs Road, Jacksonville FL, 3222.

2.4.2 Conductor and Wire Clearance Requirements:

Perform the design needed to install new 230kV circuit 979, and perform modifications to 138kV

/ 230kV circuits 832, 835, 936, 940, 947 and 941 (soon to be 975). The minimum conductor and wire clearances shall be as dictated by the Rural Utilities Service (RUS) Design Manual for High

Voltage Transmission Lines, and the latest edition of the National Electric Safety Code (NESC).

1412206079 Appendix A Scope of Work Page 12 of 18

SECTION 3: TASK PLAN

3.1 Surveying:

The winning bidder will be responsible for obtaining all surveys needed for the successful completion of a design package. These shall include:

3.1.1 Topographical Survey

3.1.2 As-built Survey including as-built LiDAR Modeling

3.1.3 Tree Survey

3.1.4 Wetland Survey

3.1.5 Improvement Survey

3.1.6 Underground Facility Locates

3.1.7 Any other surveys the bidder deems necessary to complete all tasks.

3.2 Permitting:

The winning bidder will be responsible for obtaining all permits needed for design and construction. Any work related to environmental permitting shall be coordinated with JEA’s Environmental Department to ensure proper JEA procedures are followed. These shall include:

3.2.1 All U.S. Army Corps of Engineers permits, if needed.

3.2.2 All U.S. Fish and Wildlife Service permits, specifically the Endangered Species Act, Section 7

Consultation, the Migratory Bird Treaty Act, and the Bald and Golden Eagle Protection Act.

3.2.3 Any Permits needed for removal of existing structures/utilities, such as USEPA’s Asbestos

National Emission Standards for Hazardous Air Pollutants if necessary.

3.2.4 All Department of Environmental Management permits

3.2.5 All Environmental Resource (ERP) Permitting effort, including the ERP modeling for use in the

ERP Permit submittal.

3.2.6 All Department of national Resources Historic Preservation and Archeology Office permits, specifically the National Historic Preservation Act, Section 106 Archaeological and historic

Consultation if necessary.

3.2.7 All Department of Natural Resources Permits, if needed.

3.2.8 All Department of Environmental Protection Permits as needed.

3.2.9 Any Federal Aviation Administration permits, specifically compliance with FAA Advisory

Circular AC70.7460-1L: Obstruction Marking and lighting, and the code of Federal regulations

Title 14, part 77; Safe, Efficient Use, and Preservation of the Navigable Airspace.

1412206079 Appendix A Scope of Work Page 13 of 18

3.2.10 Any FDOT and/or City permits

3.2.11 Any local road traffic control permits

3.2.12 Any required Electric and Magnetic Field Reports for the new circuit configurations as required by the Florida Administrative Code, Chapter 62-814.

3.2.13 City of Jacksonville: 10 set drawing review and approval, landscape/irrigation, tree clearing, tree removal, tree mitigation as required.

3.2.14 Any other required City of Jacksonville submittals and review sessions, including the preparation of a drainage analysis summary for 25-year level of service and demonstrating that post project drainage conditions are similar or better than pre project drainage conditions using a hydrologic and hydraulic model. This shall also include any required responses to City of Jacksonville comments, and modeling fill/cut requirements needed to balance flood plains if required.

3.2.15 Any required or anticipated Railroad Permits and/or studies. In addition to Railroad crossing permits that may be needed for decommissioning / abandoning circuits 941/975, circuits 979 and a new section of circuit 936 are expected to parallel with a CSX railroad for approximately 4.5 miles. An Electromagnetic Compatibility (EMC) study for the AC interferences between the proposed 230kV transmission circuits and the existing railroad is to be included in the Task Plan.

Pre and post energization studies/ measurements may be required. It is expected that the bidder will need to work with CSX throughout the project to meet their requirements.

3.2.16 Any other Environmental, Wildlife, Dairy related permits, and local permits as deemed necessary.

3.3 Geotechnical Data:

The winning bidder will be responsible for defining and obtaining all soil borings and any other geotechnical explorations needed for the design of new structure foundations and any other tasks needed for design. The amount and location of all soil boring is up to the designer.

3.4 General Arrangement:

The bidder will be responsible for designing the general arrangement of the transmission circuits. And substation alterations. The design shall be coordinated with structures and equipment provided by JEA’s suppliers where feasible.

3.4.1 The design shall include, but not be limited to, the following: Design of steel structures, structure foundations, concrete structures, insulator type and configuration, conductor/wire type, site access, etc.

3.4.2 Design shall conform to the latest edition of the Rural Utilities Service (RUS) Design Manual for

High Voltage Transmission Lines, and the latest edition of the National Electric Safety Code

(NESC).

3.4.3 Design shall be limited to existing JEA and public right of way/easements to the extent that is feasible. New easements shall be considered by the bidder along Otis Road and Beaver Street for conductor blow out and new structure locations. The bidder shall work with JEA Real Estate to create sketches, descriptions and renderings if required to aid in the purchase of new easements.

1412206079 Appendix A Scope of Work Page 14 of 18

Easements will also be required on parcels RE #001648-0010 and RE #006840-0000, for which

JEA does not anticipate additional assistance.

3.4.4 All transmission structures and standard framing materials, hardware, conductors, and wires shall be procured by the bidder through the bidder’s internal procurement processes. All framing materials shall be forecast at least one (1) year prior to start of construction.

3.4.5 Civil/geotechnical design shall include clearing, patrol road, culverts, foundations, etc. and permanent access to the new transmission structures for construction and maintenance where feasible. Culvert piping shall be capable of handling HS-20 loading. Any proposed RCP shall be class V. End-walls and mitered ends shall be per FDOT standards. The need for all surveying and, crore borings, etc. shall be included in the proposal.

3.4.6 Structure layout shall be created with the use of steel poles with foundations and directly embedded spun concrete poles. The exact configuration and type shall be up to the bidder to determine based on best design practices.

3.4.6.1 If directly embedded poles shall be used, the embedment shall be designed with the use of FLA DOT (57) crushed stone for backfill only, unless otherwise specified by the

JEA project representative or required by subsurface conditions.

3.4.6.2 Design shall include the exact location of new transmission structures, spacing shall be as determined by the design. Plan drawings shall show exact structure/foundation locations by use of Easting and Northing Coordinates per the State Plane NAD83

Coordinate system, 901: Florida East, and latitude/ longitude.

3.4.6.3 Proposal shall include the review and approval of all shop drawings from structure manufacturer(s) and any non JEA standard framing materials.

3.4.7 Structure design shall account for any required underbuilt distribution in accordance with JEA

Overhead Distribution Construction Standards that may be required. Where no present JEA distribution exists, provisions for future underbuilt distribution shall be provided where feasible.

3.4.8 Design for electrical parameters shall include the following:

3.4.8.1 Impedance calculations of new circuit configurations in ASPEN Line Database software. These impedances will be needed at the conclusion of final design. New impedances will be needed for circuits 832, 835, 921, 927, 936, 940, 941, 975, and 979.

The existing ASPEN Line database will likely need to be updated at JEA’s office using a JEA laptop. Time and travel shall be allocated for these tasks.

3.4.8.2 Length is in miles

3.4.8.3 Type and size of conductor is to be as described in sections 2.1 and 2.2.

3.4.8.4 Electric and Magnetic Field (EMF) calculations and reporting per the Florida

Administrative Code, Chapter 62-814. The bidder will be required to submit EMF reports to the FDEP on behalf of JEA.

3.5 Site Development:

1412206079 Appendix A Scope of Work Page 15 of 18

The bidder shall design all transmission site clearing, grading, pavement, fencing, drainage features as needed to successfully compete the project. The bidder will be responsible for determining and designing any site access improvements needed for cosntruciton. The bidder shall also consider site access.

3.6 Foundation Design:

The bidder shall design all foundations for all new transmission structures using the best design techniques and practices.

3.7 Engineering Specifications:

3.7.1 The bidder shall work with the JEA Project Manager to create a “Transmission Specification” for the purpose of construction.

3.7.2 The bidder shall work with the JEA Project Manager to create a “Right of Way Clearing

Specification” for the purpose of construction.

3.7.3 The bidder shall work with the JEA Project Manager to create a “Patrol Road Specification” for the purpose of construction.

3.7.4 The bidder shall work with the JEA Project Manager to create a “Steel Pole Specification” for the purpose of procurement of required steel poles.

3.7.5 The bidder shall work with the JEA Project Manager to create a “Spun Concrete Pole

Specification” for the purpose of procurement of required spun concrete poles.

3.7.6 The bidder shall work with the JEA Project Manager to create any necessary “Conductor and/or wire Specifications” for the purpose of procurement of non-JEA Standard Conductors and/or wires.

3.7.7 The bidder shall work with the JEA Project Manager to create a “Plating Exhibit”. Bidder shall utilize existing JEA standards to design and develop a Bill of Materials (BOM) of JEA standards framing materials to be sourced by the bidder. This “Plating Exhibit” will reflect the unique conditions of the transmission project and will be based on the proposed structure framing.

3.7.8 The bidder shall work with the JEA Project Manager to create a “Framing Exhibit”. JEA’s general framing standards within the Transmission and Distribution Standards may need to be modified with input and comments from the bidder to reflect the unique conditions of this project.

It is possible that non-JEA standard framing will need to be created by the bidder.

3.8 Engineering and Inspection Assistance During Construction:

3.8.1 The bidder shall provide engineering assistance during cosntruciton of the project on an as-requested basis. This will include attending pre-construction meetings, meetings onsite during construction, meeting with relay technicians, and availability to resolve any field issues.

3.8.2 The bidder shall also provide professional construction inspection services for the entire duration of the cosntruciton process to oversee the contractor’s work and help resolve any issues in a timely manner.

1412206079 Appendix A Scope of Work Page 16 of 18

3.9 Engineering Drawings:

3.9.1 The following is a list of drawings that the winning bidder shall provide. All drawings shall be placed in JEA Construction Title blocks. It is requested that all transmission drawings shall be created in Auto CAD. The use of reference files is recommended to avoid widespread conflicts due to changes that may arise during submittal reviews and other means. Please note that the list below is not intended to be complete, it will be up to the bidder to ensure all necessary drawings are created.

3.9.1.1 Cover Sheet

3.9.1.2 General Notes, Standards, Legend

3.9.1.3 Site – Plans and Details

3.9.1.4 Clearing Plans

3.9.1.5 Grading and Drainage – Plans and Details

3.9.1.6 Traffic Control and Site Plans for Access

3.9.1.7 Sodding – Plan and Details

3.9.1.8 Transmission Line Plan and Profile Plans for each circuit or set of circuits.

3.9.1.9 Erosion Prevention Plans

3.9.1.10 Fencing – Plans and Details

3.9.1.11 Foundation – Plans and Details

3.9.1.12 Patrol Road – Plans and Details

3.9.1.13 Structure – Plans and Details

SECTION 4: ENGINEERING DELIVERABLES

4.1 Drawings:

The winning bidder shall provide complete sets of civil, architectural, transmission, structure, and electrical drawings as needed for construction, procurement, and analysis.

4.1.1 Provide signed and sealed electronic files in AutoCAD as specified above. Provide PDFs scalable to 11”x17” as well as 24”x36” including a combined PDF of the drawing set.

4.1.2 Provide printed 11”x17” and 24”x36” copies for use by the contractor, inspector, and JEA project manager during construction.

4.1.3 Provide as-built drawing sets (signed digital copies in AutoCAD and PDF as directed by JEA project manager) per field markups.

1412206079 Appendix A Scope of Work Page 17 of 18

4.2 Electronic Files:

4.2.1 Electronic files of all surveys specified section 3 in PDF and AutoCAD format.

4.2.2 Electronic files of soil boring reports in PDF format

4.2.3 Electronic files of foundation, structural, and all other applicable engineering calculations in PDF format

4.2.4 Complete permits as specified in section 3 in PDF format.

4.2.5 Construction, material, and structure estimates at different design stages of the project

4.2.6 Construction schedule in Microsoft project and PDF format at different design stages of the project

4.2.7 PLS-CADD backup files of the proposed designs as well as as-built LiDAR PLS-CADD files, to reflect any changes during construction.

4.3 Engineering Review and Schedule Requirements:

The bidder shall submit 10%, 30%, 60%, 90%, and 100% design documents and drawings as shown in table 1 below. The milestone schedule shall be refined and finalized during the first few initial design meetings / teleconferences:

Milestone

~Due Date Design Documents to be Submitted for Review (not all inclusive)

Bid Opened 9/15/2026 Bid Docs

Bid Graded 10/02/2026 N/A

Negotiate 10/30/2026 Proposal fee and rates

PO Issued 11/30/2026 N/A

10% 2/19/2027 Site surveys, material and construction estimate, construction schedule.

30% 4/02/2027 Clearing Plan, Grading and Drainage - Plan and Details, General Structure Arrangement

60% TBD Driveways and Rocking - Plan and Details, Transmission - Plan and Profile Drawings, Patrol Road - Plan and Profile Drawings, Structure and Conductor procurement bids.

At this point the winning bidder shall provide a GMP for construction

90% TBD Sodding – Plan and Details, Foundation – Plan and Details, Erosion Prevention Plan, Applicable Permits, Pole Framing Details, Plating Specs

1412206079 Appendix A Scope of Work Page 18 of 18

100% 9/30/2027

Final construction package to include all project drawings, specifications, calculations, etc.

Start Construction

12/06/2027 TBD

Substantial Completion

9/29/2028 As-Built Drawings