This Addendum 1 modifies the progressive design-build services solicitation issued by Jacksonville Electric Authority (JEA) for the Brandy Branch to Normandy 230kV Transmission Line project in Duval County, Florida. The project requires comprehensive engineering, permitting, surveying, design, procurement, and construction services to install a new overhead 230kV transmission circuit (Circuit 979) connecting the existing Brandy Branch Substation (15701 Beaver Street West, Jacksonville, FL 32234) to the existing Normandy Substation (9801 Crystal Springs Road, Jacksonville, FL 32221). The scope encompasses all phases from initial planning through full construction completion, with proposals originally due September 15, 2026. Design phase milestones include 10% design completion by February 26, 2027, 30% design by April 9, 2027, and final design by September 30, 2027, with the project required to reach in-service by September 29, 2028.

The contract utilizes a two-phase Guaranteed Maximum Price structure, with Phase I covering planning and design deliverables at 10%, 30%, 60%, and final design stages, and Phase II encompassing final design documents, permitting, and full construction. Minimum qualifications require respondents to have successfully completed or be currently completing three Engineering, Procurement, and Construction projects within the past ten years involving overhead transmission lines at 115kV or higher in NESC Light or Medium Loading Districts, with all firms maintaining an Experience Modification Rating of 1.0 or less for the past three years. Evaluation criteria allocate 100 points across Professional Staff Experience (15 points), Similar Project Experience with three reference projects (30 points), Project Schedule (20 points), Design Approach (15 points), Construction Approach and Resource Availability (15 points), and Jacksonville Small Emerging Business participation (5 points). Liquidated damages are set at $1,000 per calendar day for design phase milestone delays, capped at ten percent of total contract price, and performance bonding requirements include 100% Performance Bond and 100% Labor and Material Payment Bonds.

View the file

Other files

Show all 14

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Procurement Department Bid Section

August 26, 2026

ADDENDUM NUMBER: ONE (1)

TITLE: 1412206079 (RFP) Progressive Design-Build Services for the Brandy Branch to Normandy 230kV Transmission Line

PROPOSAL DUE DATE: September 15, 2026

TIME OF RECEIPT: 12:00 PM EST

THIS ADDENDUM IS FOR THE PURPOSE OF MAKING THE FOLLOWING CHANGES OR

CLARIFICATIONS:

1. Clarification: It was noted during the pre-bid call that JEA was exploring internal options to transmit the large

“.bak” files; however, a viable solution could not be reached. As originally communicated, please contact Jason

Behr at behrjv@jea.com and provide a secure file transfer link to obtain the files. The file sizes are 461 MB and

2.33 GB.

2. Addition: JEA adds “1412206079 Addendum 1 Appendix C - Brandy Branch to Normandy.kmz” file.

This is a google earth .kmz file showing the desired path of the new circuit and proposed modifications to circuits 940, 941/975, 947, 936, 832, and 835. The file is not surveying grade accurate and is only being provided to illustrate the scope of this project. Anticipated new structures are shown in red and new circuits / modifications are shown in yellow.

3. Question: Can you extend the bid due date?

Answer: At this time, JEA will not extend the bid due date.

4. Question: Is it possible to have a site visit to the existing ROW in the area between Brandy Branch and Otis

Road?

Answer: At this time, JEA will not be able to provide a site visit for this area. Site access will be granted once we award a design contract. For the purpose of formulating the proposals, please base them on available data provided.