Attachment_2_-SJCP_RCT_Staircase_Section_B_Update_4-15-26_0004.docx
DOCX document 32 KB Posted
- Attached to
- SJC RIO CHAMA TRAIL STAIRCASE
- Solicitation number
- 140R4026R0012
About this file
This is a Price Schedule document for Section B of a solicitation for the SJC Rio Chama Trail Staircase project issued by the Department of the Interior Bureau of Reclamation (Solicitation Number: 140R4026R0012). Offerors must submit complete pricing for both Contract Line Item Numbers (CLINs) 010 and 020; partial offers will be considered nonresponsive. CLIN 010 encompasses fabrication and installation of the Rio Chama Trail staircase and hand railings, including mobilization and preparatory work, field verification surveying, inspection and pickup of government-furnished products, fabrication utilizing those products, delivery and installation, installation of government-furnished products with supplemental wedge anchors and hardware as needed, furnishing and installing an educational kiosk, final grading and seeding, and placement of 4,500 PSI structural concrete for pier or slab foundation improvements if required (27.0 cubic feet estimated). CLIN 020 covers removal of the existing staircase, hand railing, and cableway bridge, including demolition of the existing Rio Chama Trail cableway bridge and the existing staircase and hand railing panels. Both CLINs are subject to New Mexico Gross Receipts Tax at 6.625%. Offerors must provide lump sum pricing for each line item, with all pricing submitted in a single total for Price Schedule A. The contractor shall warranty all workmanship and installation work for a minimum of one year, with manufacturer warranties meeting industry standards for the kiosk, staircase fabrication, and all materials and supplies as detailed in the accompanying Statement of Work.
View the file
Other files
Show all 17
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SJC Rio Chama Trail Staircase
SECTION B – SUPPLIES OR SERVICES AND PRICES/COSTS
PRICE SCHEDULES
Offers will be considered for award on the following Price Schedule, but no offer will be considered for award on only a part of the Price Schedule.
Offerors shall complete Price Schedule A. Offers for less than the total of Schedule A will be considered nonresponsive and will not be evaluated for award.
Quantities in the Price Schedule are estimated quantities for comparison of offers only.
See the contract clause at WBR 1452.232-81, Payment for Mobilization and Preparatory Work, for CLIN 10.
DEFINITIONS
CLIN = Contract Line-Item Number Price Schedule A – Rio Chama Trail Staircase and Hand Railings
| CLIN |
| Supplies or Services |
| Quantity and |
Unit Price Amount
| 010 |
| Fabricate & Install Staircase and Hand Railings |
| Mobilization and Preparatory Work |
| For the lump sum of |
| $ |
| Surveying: Field Verify Design |
| For the lump sum of |
| $ |
| Inspect and Pickup Government Furnished Products (GFP) |
| For the lump sum of |
| $ |
| Fabricate Rio Chama Trail Staircase and Hand Railings. Utilizing Government Furnished Products as Appropriate. |
| For the lump sum of |
| $ |
| Delivery and Install Staircase and Hand Railings |
| For the lump sum of |
| $ |
| Install Government Furnished Products and if shorted, furnish Wedge Anchors and Hardware to Install Staircase and Hand Railings |
| For the lump sum of |
| $ |
| Furnish and Install Educational Kiosk |
| 1.0 Each |
| $ |
| $ |
| Final Grading and Seeding Disturbed Areas |
| For the lump sum of |
| $ |
| Furnish and Place 4,500 PSI Structural Concrete for Pier or Stab Foundation Improvements, if required. |
| 27.0 Cu. Ft. |
| $ |
| $ |
| NM Gross Receipts Tax |
| 6.625% |
| $ |
| Total for CLIN 010 = |
| $ |
| CLIN |
| Supplies or Services |
| Quantity and |
Unit Price Amount
| 020 |
| Removal of Existing Staircase, Hand Railing, and Cableway Bridge |
| Demolition of existing Rio Chama Trail Cableway Bridge |
| For the lump sum of |
| $ |
| Demolition of Existing Rio Chama Trail Staircase and Hand Railing Panels |
| For the lump sum of |
| $ |
| New Mexico Gross Receipts Tax |
| 6.625% |
| $ |
| Total for CLIN 020 = |
| $ |
Total for Price Schedule A (CLIN 010 and 020) = $
WARRANTED CHARACTERISTICS
The Offeror’s warranties in workmanship (installation) work for a minimum of one year.
(1) The manufacturer’s warranties shall meet industry standards for kiosk, fabrication of the staircase, and materials and supplies provided under the attached Statement of Work.
Price Schedule B - 1
File details come from the government source that posted it. Updated .