This document is a pre-bid conference presentation for the Navajo-Gallup Water Supply Project (NGWSP) Block 2-3 Pipeline Project, held on April 22, 2026. The NGWSP is a $2.3 billion federal infrastructure project authorized under Public Law 111-11 (Omnibus Public Land Management Act of 2009) and administered by the Bureau of Reclamation. The project encompasses two main laterals (Cutter and San Juan) totaling 300 miles of pipelines (20"-48" diameter), two water treatment plants with combined capacity of 43 MGD, 19 pumping plants, and numerous storage tanks, with construction beginning in June 2012. The Block 2-3 Pipeline Project specifically requires construction of 12 miles of water transmission pipe (6.0 miles of 42-inch diameter and 5.9 miles of 48-inch diameter), two 0.3-million-gallon ground-level storage tanks with yard and access road, wash crossings, bored crossings, precast manhole structures, concrete thrust collars and tapers, buried valves and appurtenances, road and utility crossings, erosion control measures, and cathodic protection systems.
The project involves four horizontal directional drilling (HDD) crossings with steel and HDPE pipe materials, ranging from 2,000 to 3,300 feet in length. Bidders should anticipate coordination with potentially five other concurrent contractors working on related components including Pumping Plant 1, San Juan Lateral Water Treatment Plant, Block 2-3 HDD, Reach 1 Bypass Tank, and Frank Crow Willetto Reservoir and Dam. The pre-bid conference included presentations on project overview, procurement details, planned site stops, and job hazard analysis. Emergency contacts include CDSR Contact Dalton Reese (505-512-8679), Hilda Castillo-Smith (505-239-4558), Supervisor Moncef Tihami (505-386-6751), with the nearest hospital being San Juan Regional Medical Center in Farmington, New Mexico. All questions regarding the project must be submitted in writing.
View the file
Other files
Show all 25
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Navajo-Gallup Water Supply Project (NGWSP)
April 22, 2026
Block 2-3 Pipeline Project Pre-Bid Conference
Agenda
• Overview Presentation (10:00 – 10:45)
• Introductions
• NGWSP Overview – Bart Deming and Ryan Gladden
• Block 2-3 Pipeline Project Overview – Moncef Tihami
• Procurement Details – Fred LaMone
• Planned Stops – Malcolm Begay
• JHA -- Hilda Castillo-Smith
• Travel to the site (10:45 to 11:00)
• Tour the site (11:00 – Noon)
• Adjourn
All Question must be submitted in writing
NGWSP Background
March 30, 2009
NGWSP Background
• Description
• Currently estimated at $2.3 Billion
• 2 Main Laterals (Cutter and San Juan) totaling 300 miles of Pipelines (20”-48”)
• 2 Conventional Water Treatment Plants with ultimate capacity of 5 & 38 MGD
• 19 Pumping Plants -- raw and finished water
• Numerous Storage Tanks
• Construction began – June 2012
• Complexities
• Cultural Resources and Environmental Compliance
• Land Acquisitions
• Bringing power to remote area
• Coordination with various Stakeholders and Jurisdictions
• Various Studies
NGWSP
Project Overview Map
Cutter Lateral
San Juan Lateral
Operational Completed Under Construction In Design (As of February 2024)
FCWR
WTP
Block 2-3 Pipeline
Project Overview Map - Raw Water System
FCWR
Intake and River Pumping Plant
Reach 1 Pipeline
Reach 2 Pipeline
Pumping Plant 1
SJLWTP Regulating Tanks
Reach 3 Pipeline
SJLWTP
- Block 2-3 HDD
Block 2-3
Block 2-3 Pipeline Project Scope
• 6.0 miles of 42-inch diameter buried water transmission pipe.
• 5.9 miles of 48-inch diameter buried water transmission pipe.
• Two 0.3-million-gallon ground level storage tanks, yard, & access road.
• Wash crossings, bored crossings, and precast manhole structures.
• Concrete thrust collars, tapers, and encased miter bends.
• Buried manholes, valves, air valves, and blowoffs.
• Road crossings, utility crossings, erosion control.
• Cathodic protection.
12 miles of pipe & 2 regulating tanks
Block 2-3 Pipeline Project
SJLWTP
Reach 3 ~8.1 Miles
Reach 2 ~3.8 Miles
SJLWTP Regulating Tanks~4.0 Miles
~4 .1 Miles
~1.0 Miles ~0.2 Miles
~1.1 Miles ~1.5 Miles
Reach 3 Pipeline
Reach 2 Pipeline
12 miles of pipe & 2 regulating tanks
Coordination with Other Contractors
SJLWTP
Reach 3 ~8.1 Miles
Reach 2 ~3.8 Miles
SJLWTP
Reg. Tanks
~4.0 Miles
~4 .1 Miles
~1.0 Miles
~0.2 Miles
~1.1 Miles ~1.5 Miles
- Block 2-3 HDD
FCWR
SJLWTP
SJLWTP Regulating Tanks
Reach 3 Pipeline
Reach 2 Pipeline
Pumping Plant 1 SJL Water Treatment Plant Block 2-3 HDD Reach 1 Bypass Tank FCW Reservoir & Dam
Potentially Working with 5 Other Contractors
Pumping Plant 1
Block 2-3 Horizontal Directional Drilling
HDD CROSSINGS
Item # HDD Crossing Name Length
(feet) Elevation
Difference (feet)
Pipe Diameter
(inch)
Reamed Diameter (inch)
Pipe Material
1 Reach 2 -- San Juan River 2,100 65 36 48 Steel 2 Reach 2 -- Nenahnezad Bluff 3,300 241 42 54 Steel 3 Reach 2 Shumway Wash 2,000 23 36 48 HDPE 4 Reach 3 -- Chaco Wash 2,000 3 36 48 HDPE
Pipe Connection Required
Procurement Details
Planned Stops
Job Hazard Analysis
| Navajo-Gallup Water Supply Project (NGWSP) |
| Agenda |
| NGWSP Background |
| NGWSP Background |
| NGWSP Project �Overview �Map |
| Project Overview Map - Raw Water System |
| Block 2-3 Pipeline Project Scope |
| Block 2-3 Pipeline Project |
| Coordination with Other Contractors |
| Block 2-3 Horizontal Directional Drilling |
| Procurement Details |
| Planned Stops |
| Job Hazard Analysis |
| Slide Number 14 |