This file is an Amendment 3 to a federal solicitation for the Pojoaque Basin Regional Water System (PBRWS) Phase II Design-Build project, issued by the Bureau of Reclamation's Upper Colorado Region. The amendment is effective September 15, 2025, with a contract ID of 140R4025R0032 and a period of performance from September 18, 2026, to April 10, 2030. The document includes a Questions and Answers section that clarifies key contractual requirements and scheduling parameters for prospective offerors.
The Q&A addresses critical schedule clarifications regarding the 180-day design window and 1,120-day construction completion timeline, totaling 1,300 contract days. The March 2027 design completion date is subject to actual contract award date and represents a target for early work packages, phased design and construction, or partial notices to proceed. The government defines the start of construction as the construction Notice to Proceed. Price Schedule C (Attachment 3), which identifies prioritized construction line items, will only be provided to contractors advancing to Phase 2 (Request for Proposals); however, contractors may reference the Statement of Objectives revised April 20, 2026, Section 1.07 (Principal Components of Work) for proposal planning purposes, as work portions are listed in priority order. Offerors must acknowledge receipt of the amendment prior to the hour and date specified in the solicitation using Standard Form 30 procedures.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a) By completing items 8 and 15, and returning or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
E. IMPORTANT: is not is required copies to the issuing office.
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE
2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)
7.ADMINISTERED BY (If other than Item 6) CODE
STANDARD FORM 30 (REV. 11/2016)
Prescribed by GSA FAR (48 CFR) 53.243
FACILITY CODE
9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED (SEE ITEM 11)
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED (SEE ITEM 13)
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in Item 14. is extended. is not extended.
12. ACCOUNTING AND APPROPRIATION DATA (If required) copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER
NUMBER IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15C. DATE SIGNED
15A. NAME AND TITLE OF SIGNER (Type or print)
16C. DATE SIGNED
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
PAGE
6. ISSUED BY CODE
8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X)
CODE
15B. CONTRACTOR/OFFEROR
(Signature of person authorized to sign)
16B. UNITED STATES OF AMERICA
(Signature of Contracting Officer)
Previous edition unusable
PAGESOF
Contractor
The hour and date specified for receipt of Offers to sign this document and return
Mary B. Maestas
See continuation page
Bureau of Reclamation Upper Colorado Region Regional Office 125 South State Street, Room 8100 Salt Lake City UT 84138
Bureau of Reclamation Upper Colorado Region Albuquerque Area Office 555 Broadway Blvd NE, Suite 100 Albuquerque NM 87102
R40
R4Q
140R4025R0032
140R4025R003209/15/2025
09/15/2025
1 4
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGES
NAME OF OFFEROR OR CONTRACTOR
SUPPLIES/SERVICES
(B)
UNIT
(D)
UNIT PRICE
(E)
AMOUNT
(F)
OPTIONAL FORM 336 (4-86)
Sponsored by GSA FAR (48 CFR) 53.110
ITEM NO.
(A)
QUANTITY
(C)
NSN 7540-01-152-8067
140R4025R0032/0003
Pojoaque Basin Regional Water System Phase II
Design-Build - Amendment 3
Questions and Answers
Period of Performance: 09/18/2026 to
04/10/2030
140R4025R0032 PBRWS Phase II Design-Build.
Amendment 3
Questions / Answers
1. Reference: Statement of Objectives (SOO), rev. 4/20/26, Section 1.03 “Objectives – Schedule” (180 days / 1,120 days) (pg. 2–3); Updated Sections L and M per Amendment 1 – Section L, Phase Two, Factor 1.b “Design Schedule” (March 2027 reference) (pg.
45); Original Solicitation – Section L (Design Schedule reference) (pg. 46).
Question: The revised SOO states that the Contractor is to begin construction within 180 days after contract award and complete design, construction, commissioning, and performance testing of the project components within the remaining 1,120 days after the start of construction (SOO 1.03, pg. 2–3). The updated Sections L and M per Amendment 1 also reference ensuring Reclamation is able to meet its design completion timeline of March 2027 (Section L, pg. 45), and similar design schedule language appears in the original solicitation (Section L, pg. 46).
Please clarify whether the March 2027 design completion date is a firm contractual requirement or a planning/target date for proposal evaluation purposes; is it Reclamation’s requirement to have all design packages complete within 180 calendar days after award? If not, how offerors should reconcile the 180-day construction start objective with the referenced design completion target (e.g., early work packages, phased design and construction, or partial notice(s) to proceed); and, for purposes of the 1,120-day timeframe, what event the Government intends to define as the “start of construction” (e.g., first field activity, issuance of a construction NTP, or commencement of an early work package).
Answer: The March 2027 design completion date is subject to the contract actual award date. The 180 day design window is to target early work packages, phased design and construction, or partial notice(s) to proceed to expedite project construction. The total contract length will be 1,300 days (180+1,120). The government considers start of construction to be at the construction Notice to Proceed.
2. Reference: Statement of Objectives (SOO), rev. 4/20/26, Section 1.03 “Objectives –
Schedule” (180 days / 1,120 days) (pg. 2–3); Updated Sections L and M per Amendment 1 – Section L, Phase Two, Factor 1.b “Design Schedule” (March 2027 reference) (pg.
45); Original Solicitation – Section L (Design Schedule reference) (pg. 46)
Question: The revised Statement of Objectives references "Achieve stakeholder facilitation and review of 90% design of the prioritized construction line items in Price Schedule C to begin construction within 180 days after contract award." and Section L references "Pricing Schedule
– Attachment 3". Please provide a copy of Price Schedule C or Attachment 3 so that Offerors may understand the order of the prioritized construction items.
Answer: The Price Schedule C or Attachment 3 will only be provided to contractors who advance to Phase 2 – Request for Proposals. In the Statement_of_Objectives_revised_4-20-26_000.pdf in section 1.07 - Principal Components of Work, contractors can assume for proposal planning and development that the portions of work are listed in priority order.
| Amendment of solicitation/modification of contract |
| Contract ID code |
| Amendment/modification number |
| Effective date |
| Requisition/purchase requisition number |
| Project number |
| Issued by |
| Code |
| Administered by |
| Code |
| Name and address of contractor |
| Code |
| Facility code |
| Amendment of solicitation number |
| Dated |
| Modification of contract/order number |
| Dated |
| This item only applies to amendments of solicitations |
| Accounting and appropriation data |
| This item applies only to modifications of contracts/orders. |
| This change order is issued pursuant to: |
| The above numbered contract/order is modified to reflect the administrative changes |
| This supplemental agreement is entered into pursuant to authority of: |
| Other |
| Important: |
| Description of amendment/modification |
| Name and title of signer |
| Contractor/offeror |
| Date signed |
| Name and title of contracting officer |
| Signature of Contracting Officer |
| Date signed |
| Previous edition unusable |
| Standard form 30 (rev. 11/2016) |
| Continuation sheet |