This document provides answers to questions regarding solicitation number 140R4020R0015 from the Department of the Interior Bureau of Reclamation for the Big Sandy Dam Reservoir Enlargement project. Reclamation seeks to enlarge the existing reservoir through construction activities including installation of a cement-bentonite cutoff wall, HDPE piping, and toe drains. The pre-bid questions and answers clarify specifications such as the required DR rating for 42-inch HDPE pipe, manufacturers for slide gates, and excavation equipment specifications. Revisions to specifications and drawings are attached regarding the cutoff wall, piping, and drain details. The total project value is between $10-25 million. Proposals are due October 28, 2020 with this opportunity designated as a total small business set-aside.

View the file

Other files

Show all 21

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SOLICITATION NO. 140R4020R0015

AMENDMENT 0006

BIG SANDY DAM

RESERVOIR ENLARGEMENT

INTERIOR REGION 7 • UPPER COLORADO BASIN

SALT LAKE CITY REGIONAL OFFICE

ACQUISITION MANAGEMENT DIVISION

PROVO AREA OFFICE PROJECT

SOLICITATION NO. 140R4020R0015 BIG SANDY DAM RESERVOIR ENLARGEMENT

INFORMATIONAL PAGE

The purpose of Amendment 0006 is as follows:

1. Provide answers to questions that were submitted in writing by October 9, 2020. The questions and answers are located on pages 4 through 7 of the document titled A6 Attachment 1 Informational Page.

Note: Question 10 will be answered via Amendment 0007.

2. Specification Sections 31 56 20, 33 11 18, and 33 46 36 have been revised and are now available as attachments to this amendment. Changes are in red/blue/black and are marked with a vertical line on the left-hand margin. The revised Sections are titled as follows:

• A6 Attachment 2 Section 31 56 20 Cement-Bentonite Cutoff Wall

• A6 Attachment 3 Revised Section 33 11 18 HDPE Pipe

• A6 Attachment 4 Revised Section 33 46 36 Toe Drains

3. Past Performance Questionnaire’s (PPQ) are being received by the Contracting Officer for several different firms. If the firm name on the PPQ does not match the name of the firm who will be proposing as the prime contractor on this project (ex: a PPQ for a subcontractor), please inform the Contracting Officer by email at lrock@usbr.gov and include the following: 1) Name of the Firm on the PPQ, 2) Name and email of the person who sent it to the Contracting Officer, and 3) Name of the prime contractor that the PPQ should be included with during the Government’s review.

4. As of Amendment 0005, the Bureau of Reclamation is no longer FedConnect. The Solicitation and Amendments 0001 through 0004 can still be found on fedconnect.net; however, beginning with Amendment 0005 and onward, all documents for this project will only be available on beta.sam.gov.

REMINDERS

1. Point of Contact:

Name: Ms. Lynette H. Rock, Contracting Officer Email: lrock@usbr.gov Phone: 385-228-8535

All correspondence and voicemails must reference Solicitation No. 140R4020R0015 Big Sandy Dam Reservoir Enlargement. Please do not send any correspondence via beta.sam.gov or any other system as it will not be received.

2. Proposal Due Date: Wednesday, October 28, 2020 Proposal Due Time: 1400 (2:00 PM) Mountain Time

ONLY ELECTRONIC SUBMISSIONS WILL BE ACCEPTED for this Solicitation. Please see WBR 1452.215-81 for submission information.

3. Solicitation No. 140R4020R0015 is a TOTAL SMALL BUSINESS SET-ASIDE (please see 52.219-6 for more information) and shall be procured in accordance with Parts 15 and 36 of the Federal Acquisition Regulation (FAR). The Solicitation document, as a whole, and the Attachments in Section J provide specific information for the work required under this solicitation.

Please thoroughly read 52.219-14 “Limitations on Subcontracting (Deviation 2019-01)” to ensure that the Small Business Prime Contractor meets the performance of the contract percentage requirements as outlined within 52.219-14(e)(3).

4. The associated NAICS Code is 237990 Other Heavy and Civil Engineering Construction with a Size Standard of $39.5M to classify as a Small Business.

5. In accordance with FAR 36.204 and supplemented by WBR 1436.204 “Disclosure of the Magnitude of Construction Projects,” the magnitude of this project is between $10,000,000 and $25,000,000.

mailto:lrock@usbr.gov mailto:lrock@usbr.gov

6. A Bid Guarantee is required for this Solicitation. Please see Standard Form 1442 Box 13 within Section A and 52.228-1 “Bid Guarantee” within Section L for more information.

7. Please see WBR 1452.215-81 “General Proposal Instructions – Bureau of Reclamation” in Section L for specific guidelines on the general contents of the proposal, arrangement of proposal, separation of volumes and submission instructions.

The Contracting Officer reserves the right to remove any pages from Volumes I and II which contain pricing information; therefore, do not include ANY pricing information within Volumes I and II. All pricing information shall be submitted under Volume III as specified within the Reclamation Provision.

8. Please see WBR 1452.215-82 “Technical Proposal Instructions – Bureau of Reclamation” in Section L for Technical Proposal format, general content, and all Evaluation Factors and Subfactors with their commensurate criteria.

Please see WBR 1452.215-85 “Evaluation Factors for Award Quality Predominance – Bureau of Reclamation” in Section M for the relative importance of the factors and all Evaluation Factors and Subfactors with their commensurate evaluation standard.

Please see WBR 1452.215-83 AI “Pricing Proposal Instructions – Bureau of Reclamation (Alternate I)” in Section L for specific Pricing Proposal information, format and content requirements and other pertinent information.

QUESTIONS AND ANSWERS

TECHNICAL RELATED

1. Sub factor 3D in the solicitation asks for the preliminary construction schedule to be submitted in Microsoft Project format. Specification section 01 32 10 asks for the project schedule to be submitted in Primavera P6 format. Can the contractor submit the preliminary schedule in P6 in lieu of Microsoft Project?

a. Yes

2. Please specify what DR rating the 42” HDPE comprising the Feeder Canal will be required to be and if it is DIPS or IPS.

a. 42-inch (DIPS), DR 32.5. Section 33 11 18 – HDPE Pipe has been revised to include these requirements.

3. Please provide a manufacture and model name/number for the 42” slide gate and actuator as a design standard reference.

a. This is an incomplete list of manufacturers that produce a cast iron slide gate that can meet the specification. Each gate manufacturer works with hoist manufacturers to provide a hoist and gate as a package that can meet the specification. Note that it is the Contractors responsibility to work with the gate manufacturer to ensure that the supplied cast iron slide gate meets the specifications and size restraints.

i. Hydro Gate, Heavy Duty HG560

ii. Waterman, Heavy-Duty Cast Slide Gates, AWWA C560

iii. Rodney Hunt, Cast Iron Sluice Gates

4. Specification Section 01 57 30 states the Dredge Fill Permit will be obtained by the BOR and transferred to the Contractor. If the conditions of the permit require additional or unanticipated work by the Contractor, will the costs to comply with the permit be reimbursed by the BOR?’

a. The 404 permit does not currently require any work outside the current scope.

5. In reference to Amendment 0005 Question and Answer 8: Would the evaluation team reconsider this requirement and allow several relevant past projects to demonstrate the work elements collectively? Additionally, the Cement Bentonite Cut-off Wall is highly specialized work and is often demonstrated in proposals by a key subcontractor. Would you consider allowing a key subcontractor’s experience be used to meet this criterion as an additional project beyond the minimum 3 past projects?

a. Yes, the evaluation team will consider several relevant past projects to demonstrate the work elements collectively. Key subcontractors’ experience can be used to meet the project criterion.

6. Will you please provide clarification on the fittings for the pvc pipe? The specs state manufacturer pipe recommendation; however, pipe manufacturers don’t really recommend fittings. We can do gasketed pvc fittings, or ductile fittings with mj glands or restraints. But without any additional spec or information it is kind of all up in the air.

Ductile fittings with glands will be significantly cheaper. However, it would need to be stated if they should be epoxy and then if they needed SS hardware and if they could just be a gland due to no pressure, or if they needed to be restrained.

a. Specification section 33 46 36 2.01.D has been modified to be more specific:

D. Fittings and Couplings:

1. Shall meet the requirements of AWWA C900 2016.

2. Epoxy-coated ductile iron.

3. Mechanically restrained.

4. Exterior protected with Poly Wrap.

5. Elbows shall be 22.5 degrees or less.

7. Contract Drawings 153-D-60010 to 153-D-60013 show the bottom elevation of the C-B

Cutoff Wall approximately 20 ft below the top of the bedrock. Note 1 of drawing 153-D- 60010 mentions that the “final elevation of bottom of cutoff wall could be higher […] if refusal is encountered as defined in the specifications […] [or] deeper than shown if highly weathered or fractured bedrock exists locally.”

The refusal criteria as defined in SS 31 56 20 paragraph 1.02 C. is as follow: “Inability of the Contractor’s production equipment to excavate more than 1 foot of depth over a bottom trench length of 20 feet within a time period of 60 minutes. Production equipment is in proper and effective operating condition and excavator bucket is equipped with ripper teeth on the back of the bucket.”

Slurry Wall Contractors use different type of excavators to excavate cutoff walls and it is important to specify the minimum break-out force at the bucket necessary for the implementation of the refusal criteria. On a previous project where the cutoff wall excavation was designed to be keyed in partially weathered rock or weak rock formations, the specifications required that the Contractor to demonstrate that its equipment has a break-out force at the bucket of at least 45,000 pounds at the maximum design depth.

We recommend that specifications include a minimum break-out force at the bucket.

a. The following specification clauses have been revised:

31 56 20 1.04.C.3:

3. Description of proposed method of trench excavation, including equipment and sequence of constructing the cutoff wall.

a. Include the power rating curve for the excavator that will be used to excavate the cutoff wall.

31 56 20 3.01.B:

B. Excavating equipment:

1. Capable of excavating 3.0-foot-wide trench through compacted embankment, overburden soil and underlying weathered foundation rock. Refer to Section 53 10 00 – Geologic investigations.

2. Capable of continuously excavating 3.0-foot-wide trench to the full depth shown on the drawings.

3. The Contractor shall modify or replace equipment when necessary, as determined by the COR, to maintain productions rates in accordance with the Contractor’s construction schedule.

4. A large excavator, having a minimum of 475 HP, shall be used to excavate the cutoff wall.

8. SS 31 56 20 paragraph 3.02 B. 1. b. mentions that the minimum trench width is 30 inches. Construction Drawing 153-D-60014 shows the width of the cutoff wall being 3.0

ft. Please confirm the minimum width of the cutoff wall.

a. See response to question 7. The correct dimension is 3.0 feet. The specifications have been revised to reflect this dimension.

9. Can CAD files be provided to bidders to allow for more accurate and consistent takeoff quantities?

a. No.

10. Sheet 153-D-60036 Detail 2 and Sheet 153-D-60043 Detail 1 calls for 6” water stop at the Inlet and Impact Basin interface with the Pipe encasement. 40-D-60003 General Notes cover portion attached calls for 2” minimum clearance on bar #8 or less. The 3” projection of the 6” water stop into the structure will be in conflict with the rebar. How will this be addressed so it can be constructed per the specifications?

a. This question will be answered via Amendment 0007.

11. If the 9” min coverage is utilized at the Feeder Canal Headworks conduit encasement as called out on sheet 153-D-60040,41, proper placement and consolidation will not be possible due to rebar congestion. Is this the intent of the design?

a. The concrete shall be placed and finished within tolerances specified in 03 30 00 in the Specifications.

12. There are no construction joints identified on the Drop Structures plans, it is assumed the invert slabs will be placed monolithically with the cutoff walls. During the site visit it was noted that the structures are to be replaced in sandy soils unable to hold a vertical cut. Please confirm it is the design intent to over-excavate the foundation, import structural backfill with the ability hold this vertical, and re-excavate at these locations.

Please confirm it is the design intent to add construction joints at the tops of the cutoff walls.

a. The location of construction joints shall be determined by the contractor and submitted for approval to the COR, in accordance with Section 03 30 00 – Cast-

In-Place Concrete, paragraph 3.06 and RSN 03 30 00-2, Concrete Placement Drawings.

b. The contractor shall form as needed so that the completed work meets specified structural deviations, surface tolerances, and finish requirements in accordance with Section 03 30 00 – Cast-In-Place Concrete, Table 03 30 00C – Deviations from Specified Lines, Grades, and Dimensions. Forming against earthfill is allowed as long as minimum reinforcement cover is met.

13. On Drawings 20 & 22, the cleanout detail specifies a “24-inch dia. protective casing”.

However, in spec section 33 46 36-5 (Toe Drains), part 2.03.B. (Caps) states "sized to fit cleanout pipe”. Can a detail be provided for the protective casing at the cleanouts? Can the detail also provide how the casing is secured within the lean concrete?

a. 12” diameter protective steel covers are acceptable for toe drain cleanouts. The design intent was to have something similar to the well cover shown below.

When using a 12” steel cover with 12” C900, a Marmac type of coupler or specialty MJ fitting can be used to connect the steel pipe to the C900 and the connection would then be encased in concrete as shown on the drawings. When using with 8” C900, the 12” protective cover would fit over the PVC pipe, similar to what is shown on the drawings.

https://ectmfg.com/product/12-round-well-protector-12-x-5-steel-safety-yellow/

14. Regarding the Chain Link Fence Bid Item (CLIN # 00010-42), spec section 32 31 10, Part 1.01.A.1.a. requires a lump sum price for the existing fence at the spillway crest access road. Given that the bid drawings do not show the extent of the existing fence at the spillway crest access road, can this existing chain link fence be quantified by the

BOR?

a. At the spillway crest access road, Reclamation estimates that the existing gate needs to be removed (8 feet high, 15 foot single swing, assume remove of 2 gate posts) and that 10-feet (8 feet high, 1 terminal fence post) of fence needs to be removed.