A5 Attachment 4 Revised Section 01 33 00 Submittals.pdf
PDF 199 KB Posted
- Attached to
- Big Sandy Dam Reservoir Enlargement
- Solicitation number
- 140R4020R0015
About this file
This document provides specifications for submittals required for the Big Sandy Dam Reservoir Enlargement project solicited by the Bureau of Reclamation under solicitation number 140R4020R0015. Key submittals include a land use and landscape rehabilitation plan, safety data sheets, pollution prevention and spill prevention plans, traffic control plans, survey plans, quality control testing plans, drawings, schedules, reports, certifications for materials and personnel, and digital recordings. Submittals are due no less than 28 days before the related work begins and must be approved by the Contracting Officer or Contracting Officer's Representative. The specifications designate submittal types as either for action, requiring a response, or informational, and provide instructions for formatting, transmitting, reviewing, resubmitting, and distributing submittals electronically and via hard copy to the Contracting Officer, Contracting Officer's Representative, and Technical Service Center as applicable.
View the file
Other files
Show all 21
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Big Sandy Dam Reservoir Enlargement Eden Project, Wyoming Solicitation No. 140R4020R0015
Submittals 01 33 00 - 1
SECTION 01 33 00
SUBMITTALS
PART 1 GENERAL
1.01 MEASUREMENT AND PAYMENT
A. Cost:
1. Include in prices offered in the Price Schedule for other items of work.
1.02 REFERENCE STANDARDS
A. American Society of Mechanical Engineers (ASME)
1. ASME Y14.1-12 Decimal Inch Drawing Sheet Size and Format
B. National Institute of Building Sciences (NIBS)
1. NIBS NCS-14 United States National CAD Standards, Version 6
1.03 DEFINITIONS
A. Days: Calendar days.
B. Required Submittal Number (RSN): Identifies items to be submitted together as a complete submittal.
C. Submittal Types, as listed in Table 01 33 00A - List of Submittals:
1. A - Action:
a. Government will respond as to adequacy of submittal.
b. Action Submittals: Considered “shop drawings” within the terms of the clause at FAR 52.236-21, Specifications and Drawings for Construction.
2. I - Informational:
a. Government will acknowledge receipt of Informational submittals.
b. Government may reject an Informational submittal when the submittal does not satisfy contract requirements. Contractor shall correct mistakes or deficiencies in rejected Informational submittals and resubmit.
c. Informational Submittals: Considered “shop drawings” within terms of the clause at FAR 52.236-21, Specifications and Drawings for Construction, except that approval by Government is not required.
Eden Project, Wyoming Solicitation No. 140R4020R0015
01 33 00 - 2
1.04 SUBMITTAL REQUIREMENTS
A. In case of conflict between requirements of this section and requirements included elsewhere in these specifications, requirements included elsewhere take precedence.
B. General:
1. Prepare in English.
2. Label with contract number and title, and RSN.
3. Measurement Units: US Customary Units.
4. Provide a unique transmittal number for each submittal.
C. Drawings:
1. Minimum Identification in Title Block:
a. Contract number and title.
b. Contractor’s or supplier’s title and drawing number.
c. Date.
2. Reserve 3 inch by 3 inch space next to title block for review stamps.
3. Size:
a. D size (22 inches by 34 inches) as defined by ASME Y14.1.
b. Half size (11 inch by 17 inch).
4. Draw to scale using computer drafting or drafting equipment, unless otherwise specified.
a. Computer drafted drawings:
1) In accordance with NIBS NCS.
2) Electronic file format: Compatible with AUTOCAD, Version
2015 or later.
3) Compile using “eTransmit” utility in AUTOCAD.
b. Drawing prepared with drafting equipment, when allowed: Lettering shall be neat.
5. Drawings Designated as “Government Format” in Specifications:
a. Computer drafted.
b. Government will provide electronic AutoCAD format template.
c. Title block and sheet format:
1) As shown on standard drawing 40-D-7102.
2) Government will supply template.
Eden Project, Wyoming Solicitation No. 140R4020R0015
01 33 00 - 3
3) Government will provide specific title block information to be used.
6. Final Drawings:
a. Computer drafted.
b. Government will provide electronic AutoCAD format template.
c. Show as-built changes, including revision dates, made during installation.
Indicate changes by clouding.
7. Electronic Files: On CD or DVD discs or other electronic file transfer means approved by the COR.
D. Product Data:
1. Mark manufacturer's data for commercial products or equipment, such as catalog cut sheets.
a. Identify manufacturer's name, type, model, size, and characteristics.
b. Illustrate that product or equipment meets requirements of specifications.
c. Mark items to be furnished in a manner that will photocopy (no highlighter).
d. Strike through items that do not apply.
e. Submittals containing superfluous information will be returned to the
Contractor for revision without further review.
E. Certifications:
1. Certifications by a Registered Professional: Signed and sealed by registered professional.
2. Manufacturer’s Certifications: Signed by authorized representative of manufacturer.
F. Manuals:
1. Copies:
a. Printed copies: Bound and indexed.
b. Electronic copies: Adobe pdf on CD or DVD discs.
1) Bookmark longer files to assist in navigating file.
2. Contents:
a. Parts identification lists, lists of special tools, and accessories.
b. Schematics and wiring diagrams.
c. Detailed instructions for installing, operating, lubricating, and maintaining equipment.
Eden Project, Wyoming Solicitation No. 140R4020R0015
01 33 00 - 4
d. As-built drawings, photographs, and test records or reports as required by the specifications.
G. Digital Pictures:
1. Digital: High resolution digital color for each listed view.
a. Caption with date.
1) Include contract name.
2. Include digital files on CD, DVD, or flash drive in .jpeg or similar format.
3. Digital files may be submitted using alternate methods to CD, DVD, or flash drive with COR approval.
H. Sample Submittals:
1. Label with complete manufacturer's product identification.
2. Include type and quantity of materials specified in the referenced section in each
“set” of samples.
3. Samples: Representative of product to be installed.
4. Label each sample or sample kit with contract number and title.
1.05 SUBMITTALS PROCEDURES
A. Submit only checked submittals. Submittals without evidence of Contractor's approval will be returned for resubmission.
B. Submit complete sets of required materials for each RSN as specified in “Submittals
Required” column in Table 01 33 00A - List of Submittals. A complete set includes listed items for RSNs with multiple parts.
C. Submit sets specified in “Sets to be sent:” columns in Table 01 33 00A - List of
Submittals.
1. Electronic submittals:
a. In Portable Document Format (.pdf).
b. Include RSN transmittal letter.
c. Do not include Personally Identifiable Information (PII) in electronic submittals.
d. Submittal method (sized based):
1) Government can receive e-mails up to 10 MB. Receipt of e-mails exceeding 10 MB (extra-large) may be possible. Extra-large electronic submittals may occur only after the process and size limit for transmittal of extra-large electronic submittals have been verified by COR.
Eden Project, Wyoming Solicitation No. 140R4020R0015
01 33 00 - 5
2) Submittals too large to be electronic transmittal: CD or DVD or by other means approved by the COR.
D. Include the following information in transmittal letters:
1. Contract number and title.
2. RSN for each attached submittal.
3. Responsible code.
4. Identify submittal as initial or resubmittal.
E. Resubmittal of submittals not approved:
1. Mark changes such that they are readily identifiable and show revision date.
2. Describe reasons for significant changes in transmittal letter.
3. Resubmit returned submittals within 14 days after receiving the comments, unless otherwise directed.
4. Requirements for initial submittals apply to resubmittals.
F. More than one RSN may be submitted under a transmittal letter, provided responsible code is same.
1.06 REVIEW OF SUBMITTALS
A. Time Required:
1. Submittal review will require 28 days for review of each submittal or resubmittal, unless otherwise specified.
2. Time required for review of each submittal or resubmittal begins when complete sets of materials required for a particular RSN are received and extends through return mailing date.
B. Time in Excess of Specified:
1. CO may extend contract completion date to allow additional time for completing work affected by excess review time.
a. Time extension will be to extent that excess review time caused delay to contract completion date.
b. Time extension will not exceed time used in excess of specified number of days for review of submittals or resubmittals.
c. Concurrent days of excess review time resulting from review of 2 or more separate submittals or resubmittals will be counted only once in extending contract completion date.
2. No time extension will be allowed if Contractor fails to make complete action submittals in sequence and within time periods specified.
Eden Project, Wyoming Solicitation No. 140R4020R0015
01 33 00 - 6
3. Adjustment for delay will be made only to extent that:
a. Approval was required under the contract, and requests for approval were properly and timely submitted and were approved.
4. Adjustment will be subject to terms of paragraphs (b) and (c) of the clause at FAR
52.242-14, Suspension of Work; however, no such delay shall be deemed to be a “suspension order” as the term is used in that clause. Adjustment will be subject to terms of clause at FAR 52.242-17, Government Delay of Work.
C. Return of Submittals:
1. Return of submittals will be electronic response or by hard copy, as applicable.
2. Action Submittals: Submittals required for action will be returned either approved, approved with comments, or not approved.
a. Revise and resubmit submittals not approved.
b. Do not modify approved submittals without approval of CO.
c. Resubmit any qualifications for any previously approved Submittal.
3. Informational Submittals: Government will acknowledge Informational submittals.
a. Informational submittals will not be returned when they satisfy contract requirements.
b. Informational submittals that do not satisfy contract requirements may be returned for resubmittal or additional information may be requested.
1.07 TRANSMITTAL
A. Addresses for codes receiving paper copy submittals listed in Table 01 33 00A - List of
Submittals:
1. Contracting Officer, Bureau of Reclamation, 125 South State Street, Room 8100, Salt Lake City, Utah 84138-1147.
2. Contracting Officer’s Representative, Bureau of Reclamation, 302 East 1860
South, Provo, Utah 84606-7317.
3. Technical Service Center (TSC), Bureau of Reclamation, Attn: 86-681608510, P.O. Box 25007, Denver CO 80225-0007; Express Mail: Sixth and Kipling, Building 67, Room 152.
B. Electronic submittals listed in Table 01 33 00A – List of Submittals:
1. Government contact information will be provided to the Contractor after award.
C. Send original transmittal letter with appropriate number of sets to office listed in
“Responsible Code” column in Table 01 33 00A - List of Submittals.
Eden Project, Wyoming Solicitation No. 140R4020R0015
01 33 00 - 7
1. Responsible codes starting with “86-6” are located in Technical Service Center.
Send these submittals to TSC address shown above.
D. Send copy of transmittal letter with appropriate number of sets to offices that are not responsible code, but show “Sets to be sent” in Table 01 33 00A - List of Submittals.
E. When “Sets to be sent” is 0, send a copy of transmittal letter to that office.
F. Submittals required by specifications, but not listed in Table 01 33 00A - List of
Submittals:
1. Submit in accordance with this section.
2. Submit to COR, unless otherwise specified.
PART 2 PRODUCTS
Not Used
PART 3 EXECUTION
Not Used
Table 01 33 00A. - List of Submittals
* Submittal Types: A - Action, I - Information ** CO indicates Contracting Officer, COR indicates Contracting Officer’s Representative, and TSC indicates Technical Service Center. Electronic indicates electronic submittal.
*** Include one hard copy of each submittal.
RSN
Clause or
Section Title
Submittals required
Due date or delivery time
Type
Respon-sible code
No. of sets to be sent to: **
CO COR
*** TSC
01 14 10-1 Use of Site Land Use And Landscape Rehabilitation Plan
At least 28 days before use of Government land
A COR Electronic
01 31 19-1 Project Management and Coordination
Written Summary of Work
Monthly A COR Electronic
01 32 10-1 Construction Program
Representative Information
Within 7 days after receipt of Notice of Award
A COR 1 1 1
01 32 10-2 Construction Program
Baseline Schedule Within 21 days after receipt of Notice to Proceed
A COR 1 1 1
01 32 10-3 Construction Program
Updated Schedule Reports
With monthly requests for progress payments
I COR Electronic
Eden Project, Wyoming Solicitation No. 140R4020R0015
01 33 00 - 8
** CO indicates Contracting Officer, COR indicates Contracting Officer’s Representative, and TSC indicates or
Respon-sible code
No. of sets to be sent to: **
CO COR
*** TSC
01 32 10-4 Construction Program
Time Impact Analysis
Within 28 days after the CO directs a contract change with schedule impacts.
Or With proposal for future modification, value engineering proposal, or request or claim for equitable adjustment to the contract
A COR 0 3 5
01 35 10-1 Safety Data Sheets
Complete LHM And SDS
At least 14 days before jobsite delivery of hazardous material
A COR Electronic
01 35 10-2 Safety Data Sheets
Updated LHM And
SDS
At least 14 days before jobsite delivery of hazardous material not previously listed
A COR Electronic
01 35 20-1 Safety and Health
Safety Program Submitted and accepted before beginning onsite work. See Section 3 of
RSHS
A COR Electronic
01 35 20-2 Safety and Health
Certificates Submitted and accepted at least 28 days before beginning onsite work
A COR Electronic
01 35 20-3 Safety and Health
Monthly Reports Monthly A COR Electronic
01 35 30-1 Contractor‘s Onsite Safety Personnel
Resumes Prior to employment I COR 1 1 0
01 35 30-2 Contractor’s Onsite Safety Personnel
Safety Inspection Reports
At least once each week I COR Electronic
01 46 00-1 Quality Procedures
Contractor Field Quality Testing Plan
At least 21 days before beginning onsite work
A COR Electronic
01 52 10-1 Field Office Delivery Schedule At least 21 days before beginning onsite work
I COR Electronic
01 52 10-2 Field Office Office Equipment At least 21 days before beginning onsite work
A COR Electronic
01 55 00-1 Vehicular Access and Parking
Temporary Bridge Design
At least 21 days before beginning onsite work
A 86-68150 Electronic
Eden Project, Wyoming Solicitation No. 140R4020R0015
01 33 00 - 9
** CO indicates Contracting Officer, COR indicates Contracting Officer’s Representative, and TSC indicates or
Respon-sible code
No. of sets to be sent to: **
CO COR
*** TSC
01 55 00-2 Vehicular Access and Parking
Initial Digital Recording
At least 21 days before beginning onsite work
A COR Electronic
01 55 00-3 Vehicular Access and Parking
Post Construction Digital Recording
At least 21 days before leaving site
A COR Electronic
01 55 00-4 Vehicular Access and Parking
Post Repair Digital Recording
Within 14 days of making repairs
A COR 1 1 0
01 55 20-1 Traffic Control Traffic Control Plan At least 35 days before affecting public traffic
A COR 1 1 0
01 56 10-1 Protection of Existing Installations
Plan for Protecting Existing Installations
At least 28 days before start of onsite construction work
A COR Elec-tronic
1 0
01 56 10-2 Protection of Existing Installations
Outlet Works Interior Existing Conditions Recording
At least 14 days before beginning excavation adjacent to outlet works
A COR 0 1 0
01 56 10-3 Protection of Existing Installations
Outlet Works Exterior Existing Conditions Recording
Within 3 days after completing excavation adjacent to outlet works
A COR 0 1 0
01 57 20-1 Environmental Controls
Copy of applicable Air Quality Permit
At least 28 days before beginning onsite work
A COR Electronic
01 57 30-1 Water Pollution Control
Pollution Prevention Plan
At least 28 days before start of onsite construction work
A COR Electronic
01 57 30-2 Water Pollution Control
Spill Prevention, Control, and Countermeasure (SPCC) Plan
At least 28 days before delivery or storage of oil
A COR Electronic
01 57 50-1 Tree and Plant Protection
Protection Plan At least 28 days before commencing on site construction work
A COR 0 1 0
01 71 20-1 Surveying Surveying Plan At least 28 days before beginning survey work
A COR Electronic
01 71 20-2 Surveying Resumes At least 28 days before beginning survey work;
At least 28 days before personnel change
A COR 1 1 0
01 71 20-3 Surveying Accuracy Check Results
At least 14 days before beginning survey work
A COR Electronic
Eden Project, Wyoming Solicitation No. 140R4020R0015
01 33 00 - 10
** CO indicates Contracting Officer, COR indicates Contracting Officer’s Representative, and TSC indicates or
Respon-sible code
No. of sets to be sent to: **
CO COR
*** TSC
01 71 20-4 Surveying Completed And Reduced Survey Notes
Within 2 days of completing and reducing notes
I COR Electronic
01 71 20-5 Surveying Quantity Survey Notes And Computations
Accompanying progress payment requests
I COR Electronic
01 71 20-6 Surveying Workday's Survey Notes
At conclusion of workday when requested by Government
I COR Electronic
01 74 00-1 Cleaning and Waste Management
Waste Production And Disposal Plan
At least 28 days before starting onsite work
A COR Electronic
01 74 00-2 Cleaning and Waste Management
Waste Production And Disposal Records
Within 7 days of waste disposal
I COR Electronic
01 74 00-3 Cleaning and Waste Management
Environmental Consultant Resume
At least 35 days before beginning environmental assessment
I COR 0 1 0
01 74 00-4 Cleaning and Waste Management
Environmental Site Assessment
Within 14 days of completion of work
I COR Electronic
01 78 30-1 Project Record Documents
Final As-built Drawings
Within 14 days of completion of work
I COR Electronic
02 41 07-1 Removal and Disposal of Existing Features
Removal and Disposal of Existing Features Plans
At least 28 days before beginning removal and disposal of existing features
A COR Electronic
02 41 10-1 Removal of Existing Concrete Structures
Removal of Existing Concrete Structures Plan
At least 28 days before beginning removal of existing concrete structures
A COR Electronic
02 41 10-2 Removal of Existing Concrete Structures
Plan for Breaking Removed Concrete
At least 28 days before beginning breaking removed concrete
A COR Electronic
03 15 12-1 PVC Waterstop Purchase Orders At least 28 days before furnishing PVC waterstop
I COR Electronic
Eden Project, Wyoming Solicitation No. 140R4020R0015
01 33 00 - 11
** CO indicates Contracting Officer, COR indicates Contracting Officer’s Representative, and TSC indicates or
Respon-sible code
No. of sets to be sent to: **
CO COR
*** TSC
03 15 12-2 PVC Waterstop Samples At least 28 days before furnishing PVC waterstop
A COR 0 1 1
03 15 12-3 PVC Waterstop Certification At least 28 days before furnishing PVC waterstop
A COR Electronic
03 15 12-4 PVC Waterstop Instructions At least 28 days before furnishing PVC waterstop
I COR Electronic
03 15 14-1 PVC Retro-Fit Waterstop
Approval Data At least 28 days before furnishing PVC retro-fit waterstop
A COR Electronic
03 15 14-2 PVC Retro-Fit Waterstop
Instructions At least 28 days before furnishing PVC retro-fit waterstop
I COR Electronic
03 15 17-1 Hydrophilic Strip Waterstop
Product Data At least 28 days before furnishing hydrophilic strip waterstop
A 86-68130 Electronic
03 20 00-1 Concrete Reinforcing
Reinforcement Diagrams and Lists
At least 28 days before beginning reinforcing fabrication and placement
A 86-68130 Electronic
03 20 30-1 Grouted Anchor Bars
Qualifications At least 28 days before beginning grouted anchor bars installation
A COR Electronic
03 20 30-2 Grouted Anchor Bars
Approval Data At least 28 days before beginning grouted anchor bars installation
A COR Electronic
03 20 30-3 Grouted Anchor Bars
Instructions At least 28 days before beginning grouted anchor bars installation
I COR Electronic
03 20 30-4 Grouted Anchor Bars
Pull Out Test Procedures
At least 28 days before beginning grouted anchor bars installation
A COR Electronic
03 20 30-5 Grouted Anchor Bars
Test Data and Results
Within 1 day after completing each test
I COR Electronic
03 30 00-1 Cast-In-Place Concrete
Approval Data At least 28 days before beginning concrete placement
A 86-68530 Electronic
03 30 00-2 Cast-In-Place Concrete
Concrete Placement Drawings
At least 28 days before beginning concrete placement
A 86-68130 Electronic
Eden Project, Wyoming Solicitation No. 140R4020R0015
01 33 00 - 12
** CO indicates Contracting Officer, COR indicates Contracting Officer’s Representative, and TSC indicates or
Respon-sible code
No. of sets to be sent to: **
CO COR
*** TSC
03 30 00-3 Cast-in-Place Concrete
Concrete Placement Schedule
At least 28 days before beginning concrete placement
A 86-68130 Electronic
03 30 00-4 Cast-In-Place Concrete
RSMC Temperature Control Plan
At least 28 days before beginning concrete placement
A 86-68530 Electronic
03 30 00-5 Cast-In-Place Concrete
Certifications At least 28 days before beginning concrete placement
A 86-68530 Electronic
03 30 00-6 Cast-In-Place Concrete
Estimating Concrete Strength by Maturity Method Plan
At least 28 days before beginning concrete placement
A 86-68530 Electronic
03 30 00-7 Cast-In-Place Concrete
Cementitious Materials Certification and Test Reports
At least 28 days before beginning concrete placement
I 86-68530 Electronic
03 30 00-8 Cast-In-Place Concrete
Test Reports Within 2 days of completing each test
I COR Electronic
03 62 20-1 Nonshrink Grout for Equipment and Metalwork
Packaged Nonshrink Grout Data
At least 28 days before using packaged nonshrink grout
A COR Electronic
03 81 10-1 Concrete Removal
Concrete Removal Plan
At least 28 days before beginning concrete removal
A COR Electronic
03 81 14-1 Concrete Repair
Material Approval Data
At least 28 days before beginning concrete repair
A 86-68530 Electronic
03 81 14-2 Concrete Repair
Applicator’s References and Qualifications
At least 28 days before beginning concrete repair
A 86-68530 Electronic
03 81 14-3 Concrete Repair
Placement Plan At least 28 days before beginning concrete repair
A 86-68530 Electronic
31 03 10-1 Diversion and Care of Reservoir Releases During Construction
Water Control Plan At least 28 days before beginning onsite work
A COR Electronic
Eden Project, Wyoming Solicitation No. 140R4020R0015
01 33 00 - 13
** CO indicates Contracting Officer, COR indicates Contracting Officer’s Representative, and TSC indicates or
Respon-sible code
No. of sets to be sent to: **
CO COR
*** TSC
31 03 33-1 Removal of Water from Excavation
Removal of Water from Excavation Plan
At least 28 days before beginning onsite work
A COR Electronic
31 09 12-1 Embankment Measurement Points
Survey Reports and Drawings
Within 14 days after completing installation
I COR Electronic
31 09 22-1 Protecting Existing Instrumentation
Protecting Existing Instrumentation Plan
At least 28 days before beginning onsite work
A COR Electronic
31 09 22-2 Protecting Existing Instrumentation
Surveys Within 7 days after completing each survey
I COR Electronic
31 23 02-1 Compacting Earth Materials
Test Results Within 1 day after completing each test
I COR Electronic
31 23 11-1 Earthwork for Structures
Compacted Backfill Construction Plan
At least 28 days before beginning onsite work
A 86-68312 Electronic
31 23 14-1 Excavating Existing Dam Slope Protection Material
Excavating and Stockpiling Existing Dam Slope Protection Material Plan
At least 28 days before beginning excavating existing dam slope protection material
A COR Electronic
31 23 16-1 Excavation of Existing Embankments and Foundation
Excavation Plan At least 28 days before beginning excavation of existing embankments and foundation
A COR Electronic
31 23 19-1 Excavation from Borrow
Borrow Area Use Plan
At least 28 days before beginning excavation from borrow
A COR Electronic
31 23 70-1 Controlled Low Strength Material
(CLSM)
Approval Data At least 28 days before beginning placement of controlled low strength material
A COR Electronic
31 23 70-2 Controlled Low Strength Material
(CLSM)
Contractor Field Quality Testing Results
Within 1 day after completing each test
I COR Electronic
31 24 12-1 General Earthfill Construction
Embankment Construction Plan
At least 28 days before beginning onsite work
A 86-68312 Electronic
31 24 14-1 Filter, Zone 2A Material
Certifications and Laboratory Test Results
At least 28 days before furnishing filter, zone 2A material
A 86-68312 Electronic
Eden Project, Wyoming Solicitation No. 140R4020R0015
01 33 00 - 14
** CO indicates Contracting Officer, COR indicates Contracting Officer’s Representative, and TSC indicates or
Respon-sible code
No. of sets to be sent to: **
CO COR
*** TSC
31 24 15-1 Gravel Drain, Zone 3A Material
Certifications and Laboratory Test Results
At least 28 days before furnishing gravel drain, zone 3A material
A 86-68312 Electronic
31 32 32-1 Geotextile Manufacturer’s Certification
At least 28 days before furnishing geotextile
I 86-68540 Electronic
31 32 32-2 Geotextile Samples At least 28 days before furnishing geotextile
A 86-68540 0 1 1
31 32 32-3 Geotextile Protection Method At least 28 days before furnishing geotextile
A 86-68540 Electronic
31 33 13-1 Spillway Anchors
Resumes At least 28 days before beginning installation
A 86-68312 0 1 1
31 33 13-2 Spillway Anchors
Manufacturer’s Product Data and Installation Plan
At least 28 days before beginning installation
A 86-68312 Electronic
31 33 13-3 Spillway Anchors
Soil Nail, Soil Anchor, and Strand Anchor Certification
At least 28 days before beginning installation
I 86-68312 Electronic
31 33 13-4 Spillway Anchors
Spillway Anchor Bar Tensioning and Testing Plan
At least 28 days before beginning installation
A 86-68312 Electronic
31 33 13-5 Spillway Anchors
Packaged Non- Shrink Grout Data
At least 28 days before beginning installation
A 86-68312 Electronic
31 33 13-6 Spillway Anchors
Grout Testing Program
At least 28 days before beginning installation
A 86-68312 Electronic
31 33 13-7 Spillway Anchors
Baseline Survey Within 2 days of completing survey and prior to any tensioning
I COR Electronic
31 33 13-8 Spillway Anchors
Intermediate and Final Surveys
Within 2 days of completing each survey
I COR Electronic
31 56 20-1 Cement- Bentonite Cutoff Wall
Qualifications At least 28 days before beginning cutoff wall construction
A 86-68312 0 1 1
31 56 20-2 Cement- Bentonite Cutoff Wall
Cement-Bentonite Cutoff Wall Plan
At least 28 days before beginning cutoff wall construction
A 86-68312 Electronic
31 56 20-3 Cement- Bentonite Cutoff Wall
Material Approval Data
At least 28 days before beginning cutoff wall construction
A 86-68312 Electronic
31 56 20-4 Cement- Bentonite Cutoff Wall
Calibration Certifications
At least 28 days before beginning cutoff wall construction
A 86-68312 Electronic
Eden Project, Wyoming Solicitation No. 140R4020R0015
01 33 00 - 15
** CO indicates Contracting Officer, COR indicates Contracting Officer’s Representative, and TSC indicates or
Respon-sible code
No. of sets to be sent to: **
CO COR
*** TSC
31 56 20-5 Cement- Bentonite Cutoff Wall
Mix Design At least 28 days before beginning cutoff wall construction
A 86-68312 Electronic
31 56 20-6 Cement- Bentonite Cutoff Wall
Laboratory Test Results
Within 1 day after completing each test
I COR Electronic
32 15 10-1 Gravel Surfacing
Certification At least 28 days before furnishing gravel surfacing
I COR Electronic
32 31 10-1 Chain Link Fence
Certifications At least 28 days before furnishing chain link fence materials
I 86-68120 Electronic
32 92 20-1 Seeding Seeding Plan At least 28 days before furnishing seed
A COR Electronic
32 92 20-2 Seeding Certifications At least 28 days before furnishing seed
I COR Electronic
33 11 18-1 HDPE Pipe Approval Data At least 28 days before furnishing HDPE pipe
A 86-68130 Electronic
33 11 18-2 HDPE Pipe Certification At least 28 days before furnishing HDPE pipe
I 86-68130 Electronic
33 11 18-3 HDPE Pipe Fusion Procedures At least 28 days before furnishing HDPE pipe
A 86-68130 Electronic
33 11 18-4 HDPE Pipe Pipe Acceptance At least 7 days before beginning concrete encasement
I COR Electronic
33 11 18-5 HDPE Pipe Pipe Measurements Within 7 days after completing pipe installation and concrete encasement
I COR Electronic
33 46 36-1 Toe Drains Approval Data At least 28 days before furnishing toe drain pipe
A 86-68312 Electronic
33 46 36-2 Toe Drains Certifications At least 28 days before furnishing toe drain pipe
I 86-68312 Electronic
33 46 36-3 Toe Drains Samples At least 28 days before furnishing toe drain pipe
A 86-68312 0 3 3
33 46 36-4 Toe Drains Inspection Videos Within 7 days after completing each video
I COR 0 1 1
35 22 10-1 Slide Gate and Actuator
Approval Data At least 28 days before beginning installation
A 86-68420 Electronic
Eden Project, Wyoming Solicitation No. 140R4020R0015
01 33 00 - 16
** CO indicates Contracting Officer, COR indicates Contracting Officer’s Representative, and TSC indicates or
Respon-sible code
No. of sets to be sent to: **
CO COR
*** TSC
35 22 10-2 Slide Gate and Actuator
Final Material Within 14 days after completing installation
I 86-68420 Electronic
END OF SECTION
| SECTION 01 33 00 SUBMITTALS |
| 1.02 REFERENCE STANDARDS |
| 1.03 DEFINITIONS |
| 1.04 SUBMITTAL REQUIREMENTS |
| 1.05 SUBMITTALS PROCEDURES |
| 1.06 REVIEW OF SUBMITTALS |
| 1.07 TRANSMITTAL |
| PART 2 PRODUCTS |
| PART 3 EXECUTION |
| END OF SECTION |