Amendment_0007_to_140R2026R0018_0007.pdf

PDF 1 MB Posted

Attached to
Bradbury Dam Outlet Valve Replacement
Solicitation number
140R2026R0018
Issued by
Not on record

About this file

This is Amendment 0007 to a federal construction solicitation for the Bradbury Dam Outlet Valve Replacement project issued by the U.S. Bureau of Reclamation's Mid-Pacific Region. The solicitation number is 140R2026R0018, and the amendment was effective August 17, 2026.

The amendment revises Sections H, L, and M of the original solicitation and extends the proposal due date from October 6, 2026, at 09:00 AM PDT to October 27, 2026, at 12:00 PM PDT. The amendment updates the wage determination from General Decision Number CA20260014 dated September 3, 2026, to the October 15, 2026, Amendment 0007 version. Key project requirements include completing all work within 450 calendar days of receiving the Notice to Proceed, with commencement required within 7 calendar days. The facility must control and release water through both new fixed-cone valves by December 15, 2027, with manual operation acceptable by that date. An interruption of service window is available only during September 1 through March 31. The solicitation is conducted under FAR Part 15 using a Lowest Price Technically Acceptable (LPTA) source selection process, with award anticipated as a firm-fixed price contract. Proposals must include three separate volumes: Business Proposal, Technical Proposal/Past Performance, and Pricing Proposal. The technical evaluation focuses on construction schedule/sequencing and contractor experience, with past performance also evaluated. A mandatory site visit is scheduled for September 2, 2026, at 10:00 AM PDT, and questions must be submitted within five days after the site visit at 5:00 PM PD.

View the file

Other files

Show all 22

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a) By completing items 8 and 15, and returning or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

E. IMPORTANT: is not is required copies to the issuing office.

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE

2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)

7.ADMINISTERED BY (If other than Item 6) CODE

STANDARD FORM 30 (REV. 11/2016)

Prescribed by GSA FAR (48 CFR) 53.243

FACILITY CODE

9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED (SEE ITEM 11)

10A. MODIFICATION OF CONTRACT/ORDER NUMBER

10B. DATED (SEE ITEM 13)

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in Item 14. is extended. is not extended.

12. ACCOUNTING AND APPROPRIATION DATA (If required) copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER

NUMBER IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15C. DATE SIGNED

15A. NAME AND TITLE OF SIGNER (Type or print)

16C. DATE SIGNED

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

PAGE

6. ISSUED BY CODE

8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X)

CODE

15B. CONTRACTOR/OFFEROR

(Signature of person authorized to sign)

16B. UNITED STATES OF AMERICA

(Signature of Contracting Officer)

Previous edition unusable

PAGESOF

Contractor

The hour and date specified for receipt of Offers to sign this document and return

Roxana Ahola

See continuation page

Bureau of Reclamation Mid-Pacific Region Regional Office Division of Acquisition Services 2800 Cottage Way, Room E-1815 Sacramento CA 95825-1898

R20

140R2026R0018

08/17/2026

08/17/2026

1 2

CONTINUATION SHEET

REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGES

NAME OF OFFEROR OR CONTRACTOR

SUPPLIES/SERVICES

(B)

UNIT

(D)

UNIT PRICE

(E)

AMOUNT

(F)

OPTIONAL FORM 336 (4-86)

Sponsored by GSA FAR (48 CFR) 53.110

ITEM NO.

(A)

QUANTITY

(C)

NSN 7540-01-152-8067

140R2026R0018/0007

A. TITLE: Bradbury Dam Outlet Valve

Replacement

B. PURPOSE: The purpose of this amendment is to revise Sections H, L, and M, incorporate the updated wage determination, and extend the proposal due date to October 27, 2026, at 12:00

PM PDT.

C. DESCRIPTION: This amendment hereby incorporates the following:

1) Revised Section H, page H-1

2) Revised Section L, page L-5

3) Revised Section M, page M-2

4) Remove General Decision Number CA20260014 dated September 3, 2026, and replace with

General Decision Number CA20260014 dated

October 15, 2026, Amendment 0007.

5) This amendment hereby extends the proposal due date from October 6, 2026, at 09:00am (PDT) to October 27, 2026, at 12:00pm (PDT).

6) All Amendments shall be acknowledged in accordance with Section 11 of this SF 30.

140R2026R0018 Bradbury Dam Outlet Valve Replacement

H-1

SECTION H – SPECIAL CONTRACT REQUIREMENTS

H.1 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK

The Contractor shall be required to

(a) commence work under this contract within 7 calendar days after the date the Contractor receives the notice to proceed,

(b) prosecute the work diligently, and

(c) complete the entire work ready for use not later than 450 calendar days after the date the Contractor receives the notice to proceed. The time stated for completion shall include final cleanup of the premises.

H.1.1 INTERMEDIATE MILESTONES AND LIMITATIONS

(a) The information provided below refers to the time period specified above under Commencement, Prosecution, and Completion of Work.

(b) Refer to Section 01 14 30, Interruption of Service, located in Section C of this solicitation.

1. Interruption of service window available to Contractor:

a) Government will unwater penstocks to accommodate Contractor-requested and approved interruption of service only during the following interval.

1) September 1 through March 31.

b) Facility shall be able to control and release water through both new fixed-cone valves by December 15, 2027. Manual operation of the valves by this date is acceptable.

(c) Requirements of Section 01 14 30, Interruption of Service, carry the full weight of Section H with requirements of Section H, above, taking precedence.

H.2 WBR 1452.242-80 POSTAWARD CONFERENCE— MAR 2022

BUREAU OF RECLAMATION

(a) Prior to the contractor starting work, a post-award conference (as described in FAR Subpart 42.5), will be convened by the contracting activity or contract administration office. The contractor's project manager shall attend the conference. If the contract involves subcontractors, a representative of each major subcontractor is also required to attend.

(b) The conference will be held at the via MS Teams invite.

(c) The contracting officer and the contractor will agree to the date and time of the conference after award of the contract. In event of a conflict in schedules, the contracting officer shall establish the date for the conference.

(d) The contractor shall not be entitled to the reimbursement any costs associated with attendance at the conference beyond the agreed-to contract price.

(End of clause)

Amendment 0007

H-2

H.3 SITE VISIT(CONSTRUCTION)

(a) The clauses at 52.236-2, Differing Site Conditions, and 52.236-3, Site Investigations and Conditions Affecting the Work, will be included in any contract awarded as a result of this solicitation. Accordingly, offerors are urged and expected to inspect the site where the work will be performed.

(b) Site visit is scheduled for September 2, 2026, at 10:00 am PDT.

In order to anticipate the number of interested attendees to attend a site visit, Contractors shall register by contacting Sean Frische at sfrische@usbr.gov. Please also cc: the Contract Specialist, Charlesetta Seibure at charlesetta_seibure@ios.doi.gov The registration email must include the following:

• Name of Company

• Number of Participants

• Names of Participants

• Main point of contact

Offerors attending the site visit shall wear hard hat, safety toe boots (no open toe shoes), sturdy attire, safety glasses, and hearing protection.

Deadline for submission of questions is five (5) days after the site visit at 1700 PD.

Amendment 0007 mailto:sfrische@usbr.gov mailto:charlesetta_seibure@ios.doi.gov

L-1

SECTION L - INSTRUCTIONS, CONDITIONS AND NOTICES TO OFFERORS

FAR 52.252-1 SOLICITATION PROVISIONS INCORPORATED FEB 1998

BY REFERENCE

This solicitation incorporates one or more solicitation provisions by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. The offeror is cautioned that the listed provisions may include blocks that must be completed by the offeror and submitted with its quotation or offer. In lieu of submitting the full text of those provisions, the offeror may identify the provision by paragraph identifier and provide the appropriate information with its quotation or offer. Also, the full text of a solicitation provision may be accessed electronically at this/these address(es):

https://www.acquisition.gov/browse/index/far (FAR 52.XXX-XX formatted clauses) https://www.acquisition.gov/diar (DIAR 1452.XXX-XX formatted clauses)

Provision Title Date FAR 52.204-7 System for Award Management (RFO DEVIATION) MAR 2026 FAR 52.214-34 Submission of Offers in the English Language APR 1991 FAR 52.214-35 Submission Of Offers In U.S. Currency APR 1991 FAR 52.215-1 Instructions to Offerors—Competitive Acquisition NOV 2021

FAR 52.225-10

Notice of Buy American Requirement- Construction Materials MAY 2014

DIAR 1452.215-71 Use and Disclosure of Proposal Information APR 1984

FAR 52.216-1 TYPE OF CONTRACT APR 1984

The Government contemplates award of a firm-fixed price contract resulting from this solicitation.

(End of provision)

FAR 52.215-1 Instructions to Offerors - Competitive Acquisition - Addendum

Inquiries. All inquiries pertaining to this solicitation (except where noted for the onsite site visit) shall be submitted via email to the Contract Specialist, Charlesetta Seibure at charlesetta_seibure@ios.doi.gov and cc Contracting Officer, Roxana Ahola at roxana_ahola@ios.doi.gov due five days after site visit at 5:00 pm PD. Responses pertinent to all prospective offerors will be included in an amendment to the solicitation.

FAR 52.222-5 CONSTRUCTION WAGE RATE REQUIREMENTS - MAY 2026

SECONDARY SITE OF THE WORK (RFO DEVIATION)

(a)(1) The offeror shall notify the Government if the offeror intends to perform work at any

Amendment 0007 https://www.acquisition.gov/diar mailto:charlesetta_seibure@ios.doi.gov

L-2 secondary site of the work, as defined in paragraph (a)(1)(ii) of the FAR clause at 52.222-6, Construction Wage Rate Requirements, of this solicitation.

(2) If the offeror is unsure if a planned work site satisfies the criteria for a secondary site of the work, the offeror shall request a determination from the Contracting Officer.

(b)(1) If the wage determination provided by the Government for work at the primary site of the work is not applicable to the secondary site of the work, the offeror shall request a wage determination from the Contracting Officer.

(2) The due date for receipt of offers will not be extended as a result of an offeror’s request for a wage determination for a secondary site of the work.

FAR 52.252-5 AUTHORIZED DEVIATIONS in PROVISIONS NOV 2020

(a) The use in this solicitation of any Federal Acquisition Regulation (48 CFR Chapter 1) provision with an authorized deviation is indicated by the addition of "(DEVIATION)" after the date of the provision.

(b) The use in this solicitation of any Department of the Interior or Bureau of Reclamation Agency provision with an authorized deviation is indicated by the addition of "(DEVIATION)" after the name of the regulation.

(End of provision)

DIAR 1452.233-2 SERVICE OF PROTEST DEPARTMENT JUL 1996

OF THE INTERIOR (DEVIATION)

(a) Protests, as defined in section 31.101 of the Federal Acquisition Regulation, that are filed directly with an agency, and copies of any protests that are filed with the Government Accountability Office (GAO), shall be served on the Contracting Officer (addressed as follows) by obtaining written and dated acknowledgment of receipt from

Roxana Ahola, Contracting Officer

U.S. Bureau of Reclamation 2800 Cottage Way, Room E-1815

Sacramento, California 95825-1898

(b) The copy of any protest shall be received in the office designated above within one day of filing a protest with the GAO.

(c) A copy of the protest served on the Contracting Officer shall be simultaneously furnished by the protester to the Department of the Interior Assistant Solicitor for Procurement and Patents, 1849 C Street, NW, Room 6511, Washington, D.C. 20240

(End of Provision) http://www.arnet.gov/far/current/html/Subpart%2031_1.html#wp1089550

L-3

WBR 1452.215-81 PROPOSAL INSTRUCTIONS MAR 2021

BUREAU OF RECLAMATION

This procurement will be conducted in accordance with FAR Part 15.

In addition to the requirements of the Instructions to Offerors - Competitive Acquisitions provision of this solicitation (see FAR 52.215-1), each offeror shall submit a proposal in accordance with the instructions contained in this provision. To submit a proposal for this requirement, offerors are required to send an email to Charlesetta Seibure charlesetta_seibure@ios.doi.gov prior to the proposal due date.

(a) Use and Disclosure of Proposal Information. In accordance with the Use and Disclosure of Proposal Information -- Department of the Interior provision of this solicitation (see DIAR 1452.215-71), offerors shall mark trade-secret or confidential commercial or financial information contained in the proposal with the restrictive legends specified. The offeror shall also clearly and separately mark all proprietary information (as defined in FAR 3.104-3) contained in the proposal with the restrictive legend "Proprietary Information."

(b) Proposal Volumes. Offerors shall submit (3) separate Volumes as follows:

Volume Title

I Business Proposal (Representations, Certifications and Offer)

II Technical Proposal/Past Performance

III Pricing Proposal

(1) Separation of volumes. Each volume shall be sent in a separate email with the subject line having the following format:

Solicitation Title, Company Name, Volume I Solicitation Title, Company Name, Volume II Solicitation Title, Company Name, Volume III

(c) General Contents. Each separate proposal Volume shall:

(1) Be presented in a manner which allows it to “stand alone” without the need to reference other documents;

L-4

(2) Be a coherent document free of internal inconsistencies as well as inconsistencies with other volumes of the proposal;

(3) Conform to all solicitation provisions, clauses, or requirements;

(4) Address the submission requirements with specificity and detail where required;

(5) Be an orderly, specific, and complete document in every detail;

(6) Be logically presented, using clear and concise language so that it can be easily read and meaningfully evaluated by Reclamation personnel from a variety of different functional and technical disciplines;

(7) Have all pages in each volume consecutively numbered (including pages with tables and exhibits) and cross-referenced to other volumes where appropriate for each; and

(8) Indicate how the proposal conforms to the evaluation criteria identified in Section M.

(d) Format. Each volume shall contain the following items in addition to the other information required by this solicitation:

(1) Provide a Table of Contents which lists all sections specific to the proposal Volume;

(2) Cross-reference the work statement to the terms of the proposal and indicate how the proposal conforms to the evaluation factors contained in Part IV, Section M;

(3) Provide a list of any enclosures, including tables, drawings, charts, or other enclosures which summarize data or information;

(4) Provide a Cover page. The cover should indicate the following:

• Title of the proposal

• Volume Number (I, II or III)

• Proposal category (Business, Technical, Price Proposal)

• Request for Proposal (140R2026R0010) Number

• Name and address of offeror, Cage Code, UEI, and Business Size

• A statement that the proposal is valid for a period of 90 days from date of proposal submission.

(e) Volume I, Business Proposal. Volume I shall incorporate the other Volumes by reference but shall not physically include them. It shall consist of:

(1) A fully executed Solicitation, Offer, and Award form required by Part I, Section A of this solicitation. It shall be used as the cover sheet (or first page) of Volume I. All amendments signed by the offeror’s authorized signature authority.

(2) Fully executed and completed offeror representations, certifications, and acknowledgments required by Part IV, Section K of this solicitation;

(3) Additional information required by the solicitation to be furnished by the offeror which is not required to be obtained in another volume of the proposal;

(4) Make-or-buy program (if applicable);

(5) Requests for any waivers of any solicitation provisions or contract clauses; and

(6) A summary of any exemptions from, or deviations to, any other solicitation requirements.

(f) Volume II

a. Technical Proposal Contents. The technical proposal should clearly describe the capability of the offeror's organization to participate in this project and effectively

L-5 demonstrate a thorough understanding of the work statement contained in Part I, Section C of this solicitation. To assist in the uniform evaluation of proposals, the following format shall be utilized in preparing the technical proposal:

(a) Table of Contents. The Table of Contents shall list all sections of the technical proposal. Any future amendments, additions and/or revisions to the proposal shall be included in an updated Table of Contents;

(b) Index. The Index section shall cross reference the statement of work, specifications, or performance work statement to the terms of the proposal and indicate how the proposal conforms to the evaluation factors contained in Part IV, Section M;

(c) Enclosures. The Enclosures Section shall include a list of any tables, drawings, charts, and any other enclosures which summarize data or information;

(d) Executive Summary. The Executive Summary shall include a brief discussion of how the required work will be performed and important highlights of the proposal.

(e) There are two (2) technical (non-price) factors that will be evaluated in accordance with the criteria contained in Section M of this solicitation:

1. Technical Capability.

Subfactor 1A: Coordinated Construction Schedule and Narrative of Construction Sequence Subfactor 1B: Experience

2. Past Performance.

(f) Supplemental technical proposal instructions. The following are specific instructions for the preparation and content of the technical proposal to supplement the above information:

Factor 1 - Technical Plan for Construction: The Technical Plan for Construction shall include a coordinated construction schedule, a written narrative of the planned construction sequence for all required work under the bid schedule, identification and description of proposed subcontract scopes, and statements analyzing any major issues or assumptions. Both the schedule and the narrative of planned construction sequence shall be tied to the requirements contained in the specifications; (Commencement, Prosecution, and Completion of Work) in Section H.

Offerors shall submit a proposed schedule showing all major activities and the sequence of work required to complete the project within 365 450 calendar days from the Notice to Proceed (NTP).

For proposal and evaluation purposes, offerors shall assume an NTP date 90 days after the proposal due date of January 4, 2027. This assumed date is for evaluation only. The actual NTP will be issued to the awardee after contract award and shall be used for development of the finalized schedule.

Refer to Section H, for specific schedule restrictions.

L-6

Subfactor 1A - Coordinated Construction Schedule and Narrative of Construction Sequence:

The coordinated construction schedule shall include:

1) Content: A Gantt chart schedule that includes such detail to show the sequencing of the principal and critical components of work contained in the solicitation; in addition, any other activities or information needed to accurately portray the offeror’s proposed schedule shall be included. The schedule shall include critical submittals allowing for submittal preparation time and associated Government reviews/approvals.

2) Format: The schedule shall be in color and formatted to 11x17 sized paper and have columns that display the following information in the following order: activity name, planned duration, calendar ID, early start, late start, early finish, late finish and total float. The schedule shall meet the requirements of specification section 01 32 10 – Part 1.06.A, Schedules. The schedule shall be in format compatible with Primavera Professional Project Management. Include electronic copies of the. xer schedule date file and the .plf schedule layout file.

3) Schedule Organization Statement: To help facilitate a more efficient and consistent Government review, provide a brief statement that describes how the schedule was organized. Summaries the following information:

a) A listing of the site-specific calendar names and function of the calendars (i.e. 5 day with holiday, 7 day, etc.). List any assumptions used in developing the calendars.

b) Description of the work-breakdown-structure categories used to organize the schedule.

c) Any other pertinent information that will facilitate a more efficient review and provide a better understanding of the schedule’s organization.

The Narrative of Construction Sequence shall relate to items in the Coordinated Construction Schedule and description shall include:

Provide the following information for each principle and critical work component listed below.

i. Contractor(s) responsible for the component of work.

ii. Equipment types including capacities, sizes and production rates,

iii. Planned shifts, crew sizes, and production rates.

Within the narrative, this listing of assumptions shall correlate with the schedule by referencing activity identification (IDs) and activity description for key items of work.

Design and supplier information and ultimate acceptance of the offer shall not relieve the offeror from complying with the requirements of the specifications.

The Narrative of Construction Sequence shall not include voluminous amounts of generic product information that can be easily found on the internet.

Narrative of Construction Sequence shall not exceed 30 pages. Any pages in excess of 30 will be disregarded. One page is equivalent to one side of a double-sided printed piece of 8.5” by 11” paper. Font sizes must be no smaller than Times New Roman, size 10 type. Any material

L-7 submitted, including appendices and attachments, that exceeds the page limitations specified will not be considered during the evaluation process.

The following principal components of work shall have their own activity identification names and numbers:

1. Electrical inspection, design, demolition, and installation:

2. Remove two (2) existing fixed-cone valves and peripheral equipment.

3. Design two (2) valve supports for new fixed-cone valves. .

4. Furnish, install, and test two (2) fixed-cone valves with hoods and peripheral equipment.

5. Temporary pumping to supply water from Lake Cachuma to the Bradbury Dam Spillway during the Outlet Works Outage of the project.

Provide a narrative with work plans for each task identified below, including the means, methods, sequencing, and anticipated production rates. The work plans shall identify potential subcontractors and significant anticipated material suppliers. The proposed work plans shall also include the offeror’s technical approach for managing subcontractors and identifying the specific tasks that subcontractors will perform. The work plans shall correlate with the offeror’s proposed construction schedule and explain in detail the offeror’s, or subcontractor’s, approach to accomplish the following specific construction tasks:

Valve Replacement – Provide a concept leveled plan describing how the valves and the associated electrical power system will be removed and replaced. The plan shall include at a minimum:

a. Collecting and documenting as-found readings.

b. Means, methods, and sequence for disassembly, reassembly, design, and commissioning.

Temporary Bypass Pumping – Sketch and concept level plan outlining location of bypass flow system, including phasing as needed.

Subfactor 1B – Experience: It is considered important to the Government that the offeror, their subcontractors, and key project and site personnel are available, committed and have substantiated experience with construction of work similar in nature to the work requirements contained within this solicitation in order to adequately plan the specified work. Experience of Contractor and Subcontractor key personal to include at a minimum:

a. Superintendent,

b. Project Manager,

c. Safety Manager, L-8

d. Safety Professional,

e. Quality Control Professional,

f. Electrical Engineer.

1) Provide a description of the roles and responsibilities for all parties with a clear list of the work the prime contractor will self-perform versus work performed by subcontractors, sub-consultants, suppliers, and designers. In addition, explain the anticipated level of supervision the prime contractor will have over any work performed by a subcontractor.

2) Provide a visual organization chart that clearly depicts the proposed management team and identify the key personnel listed in Subfactor 1B.

a) Include a brief narrative that lists each person’s roles and responsibilities contained in the organization chart.

b) For each person on the organization chart include their proposed availability. For key management positions, indicate their proposed percent of time onsite for the duration of this project.

c) If the offeror’s proposed management team includes subcontractor personnel(s) performing major project management aspects of the project, explain how the proposed management team will result in the offeror retaining control of the overall management of the contract and that the proposed team will be cohesive and capable of effectively managing this work.

3) If the offeror intends to subcontract any of the key personnel listed above, the offeror shall include a Letter of Commitment. The Letter of Commitment shall be signed by both parties and shall demonstrate the commitment of both parties to this project.

4) Provide a list of alternate personnel sources to be utilized in the event proposed personnel are not available as planned. (Include full resume by name of all additional personnel listed).

Factor 2 - Past Performance: Offerors shall submit past performance information for at least one (1) and up to three (3) relevant projects performed within the past five (5) years. Projects submitted should be similar in size, scope, and complexity to the work required under this solicitation.

For each project submitted, the offeror shall provide the following information:

• Contract number, title, and customer (Federal, State, Tribal, local government, or commercial)

• Period of performance

• Brief description of the work performed

• Point of contact information (name, title, email, and phone number)

• A description of the offeror’s adherence to project schedules

• A description of the offeror’s performance regarding timely and complete submittals

• Any corrective actions taken during performance (if applicable)

Offerors shall also identify any performance issues encountered and describe actions taken to correct or mitigate those issues.

Use of Non-Offeror-Provided Past Performance Information The Government is not limited to the information provided by the offeror and may use any

L-9 available past performance information when evaluating past performance. This may include, but is not limited to:

• CPARS

• FAPIIS

• Other Government records

• Personal knowledge of the Contracting Officer or COR

• Information obtained from other Federal, State, Tribal, or local agencies

• Information from commercial clients or references

Offerors are advised that the Government reserves the right to verify all submitted information and to consider any reliable past performance information obtained from any source.

(g) Volume III, Price Proposal. Offerors are hereby notified that even though cost or pricing data are not initially requested in this solicitation, the Contracting Officer reserves the right to request such data if they are later found necessary pursuant to FAR 15.403-5(a)(1).

To assist in the uniform evaluation of proposals, the following format shall be utilized in preparing the pricing proposal:

(1) Table of contents. The Table of Contents shall list all sections of the pricing proposal. Any modifications or revisions to the proposal, up to the date of agreement on price, shall include an updated Table of Contents;

(2) Index. The index shall cross reference the work statement to the terms of the proposal and indicate how the proposal conforms to the evaluation factors contained in Part IV, Section M of this solicitation;

(3) Enclosures. A list shall be included with all enclosures, attachments, tables, drawings, charts, and any other material which summarizes data or information contained or referenced in the pricing proposal;

(4) The price proposal should be consistent with the technical approach(es) proposed in the technical proposal, Volume II;

(5) Pricing proposal breakdown. The offeror shall submit Section B of the contract Schedule (Schedule of Supplies and Services, found in Part I of this solicitation), including any attached Price Schedules noted in Section B, with its proposed total prices/costs for each contract line item number (CLIN), including any options, and proposed unit price(s), if required. In addition, a total proposed price consisting of the sum of all contract line items (excluding options) shall be submitted.

(6) No cost information shall be included in any of the other volumes;

(7) All price or cost amounts shall be expressed to the nearest whole dollar except for individual hourly labor rates (if required). All percentages shall be expressed to two decimal places.

M-1

SECTION M – EVALUATIONS FOR AWARD

WBR 1452.215-85 EVALUATION FACTORS FOR AWARD -- LOWEST PRICE

TECHNICALLY ACCEPTABLE SOURCE SELECTION PROCESS -- BUREAU OF

RECLAMATION (MAR 2021)

(a) Award will be made to the responsible offeror submitting the lowest evaluated price of proposals meeting or exceeding the acceptability standards for non-cost/price factors and any significant subfactors listed in this provision.

(b) Proposals shall be evaluated for acceptability, but not ranked, using the non-cost/price factors listed below. There shall be no trade-offs. The Contracting Officer has elected to included past performance as an evaluation factor. Past performance shall be evaluated in accordance with FAR 15.305; however there shall be no comparative assessment of offerors' past performance. If the Contracting Officer determines that a small business' past performance is not acceptable, the matter shall be referred to the Small Business Administration for a Certificate of Competency determination, in accordance with the procedures contained in FAR Subpart 19.6 and 15 U.S.C.

637(b)(7). If a proposal is determined by the Contracting Officer to be "technically unacceptable" as a result of evaluating all factors other than cost or price, the proposal may be rejected from further consideration.

Since technical proposals are being solicited to obtain information to be used in the evaluation, the Government reserves the right to use information outside of the proposal to evaluate the capability of offerors and the value of offers.

(c) Pursuant to FAR 15.305(a)(1), a cost or price analysis will be performed to determine price reasonableness and any instances of unbalanced pricing, using one or more of the techniques at

FAR 15.404 -1.

(d) The following factors, significant subfactors (if listed), and acceptability standards for non-cost/price factors/subfactors shall be considered in evaluating proposals and making the source selection:

Factor 1 – Technical Capability Subfactor 1A: Coordinated Construction Schedule and Narrative of Construction Sequence Subfactor 1B: Experience

Factor 2: Past Performance

M-2

Factor 1 – Technical Capability

Subfactor 1A - Construction Schedule and Sequence and Narrative of Construction Sequence.

The Government will evaluate the proposed schedule to ensure they meet the period of performance and elements required for project completion, including the requirements identified in Section H. The construction sequence will be evaluated to ensure construction techniques are utilized to be successful.

Subfactor 1B - Experience . The Offeror must ensure all the requested proposal submission information is current, accurate, and complete. The Offeror’s Relevant Experience with Contract/Projects will be initially evaluated on an acceptable/unacceptable basis in regard to meeting the minimum quote submission requirements identified in this solicitation. The Government reserves the right to contact each experience provided as a reference verification check.

Factor 2 – Past Performance

The Government will evaluate the offeror’s past performance to determine the degree to which it demonstrates a reasonable expectation of successful performance. The evaluation will consider the following in sup:

• Relevance of past projects in scope, magnitude, and complexity

• Recency (typically within the past 5 years)

• Quality of performance, including:

• Timeliness

• Quality of workmanship

• Cost control (if applicable)

• Customer satisfaction

• Resolution of issues

Sources may include CPARS, PPIRS, references, and other verifiable information.

Rating of Proposals

Technical Ratings:

Rating Definition

Acceptable Proposal meets the requirements of the solicitation.

Unacceptable Proposal does not meet the requirements of the solicitation.

L-10

NOTICE TO OFFERORS:

System updates may lag policy updates. The System for Award Management (SAM) may continue to require entities to complete representations based on provisions that are not included in agency solicitations, including 52.223-22, Public Disclosure of Greenhouse Gas Emissions and Reduction Goals—Representation, and paragraph (t) of 52.212-3, Offeror Representations and Certifications—Commercial Products and Commercial Services.

Agencies will not consider or use these representations. Entities are not required to, nor are they able to, update their entity registration to remove these representations in SAM.

"General Decision Number: CA20260014 10/15/2026

State: California

Construction Types: Building, Heavy and Highway

Counties: California Counties of Santa Barbara

Building Construction Projects Dredging Projects-Includes Dredging Projects (does not include hopper dredge work) Heavy Construction Projects (excludes water well drilling) Highway Construction Projects

Modification Number Publication Date 3 01/30/2026 4 05/18/2026 5 07/14/2026 6 09/03/2026 7 10/15/2026

ASBE0005-002 07/01/2024

Rates Fringes

ASBESTOS WORKERS/INSULATOR (INCLUDES THE

APPLICATION OF ALL INSULATING MATERIALS, PROTECTIVE

COVERINGS, COATINGS, AND FINISHES TO ALL TYPES OF

MECHANICAL SYSTEMS).................................$ 56.32 26.52

ASBE0005-002 09/01/2024

Rates Fringes

FIRE STOP TECHNICIAN (APPLICATION OF FIRESTOPPING

MATERIALS FOR WALL OPENINGS AND PENETRATIONS IN

WALLS, FLOORS, CEILINGS AND CURTAIN WALLS)..........$ 39.94 20.65

ASBE0005-004 07/04/2022

Rates Fringes

ASBESTOS REMOVAL WORKER/HAZARDOUS MATERIAL HANDLER

(INCLUDES PREPARATION, WETTING, STRIPPING,

REMOVAL, SCRAPPING, VACUUMING, BAGGING AND

DISPOSING OF ALL INSULATION MATERIALS FROM

MECHANICAL SYSTEMS, WHETHER THEY CONTAIN ASBESTOS

OR NOT).............................................$ 23.52 13.37

BOIL0092-003 01/01/2024

Rates Fringes

BOILERMAKER.........................................$ 51.98 42.11

BRCA0004-003 05/01/2026

Rates Fringes

BRICKLAYER; MARBLE SETTER...........................$ 50.32 21.23

10/22/26, 11:17 AM SAM.gov https://sam.gov/wage-determination/CA20260014/7 1/27

BRCA0018-008 06/01/2026

Rates Fringes

MARBLE FINISHER.....................................$ 46.97 17.17

TILE FINISHER.......................................$ 41.55 15.65

BRCA0018-010 09/01/2026

Rates Fringes

TERRAZZO FINISHER...................................$ 46.09 15.71

TERRAZZO WORKER/SETTER..............................$ 54.13 16.01

BRCA0018-011 06/01/2026

Rates Fringes

TILE LAYER..........................................$ 56.52 21.00

CARP0213-001 07/01/2025

Rates Fringes

CARPENTER: (1) CARPENTER, CABINET INSTALLER,

INSULATION INSTALLER, HARDWOOD FLOOR WORKER AND

ACOUSTICAL INSTALLER FOOTNOTE: WORK OF FORMING

IN THE CONSTRUCTION OF OPEN CUT SEWERS OR STORM

DRAINS, ON OPERATIONS IN WHICH HORIZONTAL LAGGING

IS USED IN CONJUNCTION WITH STEEL H-BEAMS DRIVEN OR

PLACED IN PRE- DRILLED HOLES, FOR THAT PORTION OF A

LAGGED TRENCH AGAINST WHICH CONCRETE IS POURED,

NAMELY, AS A SUBSTITUTE FOR BACK FORMS (WHICH WORK

IS PERFORMED BY PILEDRIVERS): $0.13 PER HOUR

ADDITIONAL..........................................$ 52.24 26.18

CARPENTER: (2) MILLWRIGHT FOOTNOTE: WORK OF

FORMING IN THE CONSTRUCTION OF OPEN CUT SEWERS OR

STORM DRAINS, ON OPERATIONS IN WHICH HORIZONTAL

LAGGING IS USED IN CONJUNCTION WITH STEEL H-BEAMS

DRIVEN OR PLACED IN PRE- DRILLED HOLES, FOR THAT

PORTION OF A LAGGED TRENCH AGAINST WHICH CONCRETE

IS POURED, NAMELY, AS A SUBSTITUTE FOR BACK FORMS

(WHICH WORK IS PERFORMED BY PILEDRIVERS): $0.13 PER

HOUR ADDITIONAL.....................................$ 52.24 26.68

CARPENTER: (3) PILEDRIVERMEN/DERRICK BARGEMAN,

BRIDGE OR DOCK CARPENTER, HEAVY FRAMER, ROCK

BARGEMAN OR SCOWMAN, ROCKSLINGER, SHINGLER

(COMMERCIAL) FOOTNOTE: WORK OF FORMING IN THE

CONSTRUCTION OF OPEN CUT SEWERS OR STORM DRAINS, ON

OPERATIONS IN WHICH HORIZONTAL LAGGING IS USED IN

CONJUNCTION WITH STEEL H-BEAMS DRIVEN OR PLACED IN

PRE- DRILLED HOLES, FOR THAT PORTION OF A LAGGED

TRENCH AGAINST WHICH CONCRETE IS POURED, NAMELY, AS

A SUBSTITUTE FOR BACK FORMS (WHICH WORK IS

PERFORMED BY PILEDRIVERS): $0.13 PER HOUR

ADDITIONAL. .......................................$ 52.37 26.18

CARPENTER: (4) PNEUMATIC NAILER, POWER STAPLER

FOOTNOTE: WORK OF FORMING IN THE CONSTRUCTION OF

OPEN CUT SEWERS OR STORM DRAINS, ON OPERATIONS IN

WHICH HORIZONTAL LAGGING IS USED IN CONJUNCTION

WITH STEEL H-BEAMS DRIVEN OR PLACED IN PRE- DRILLED

HOLES, FOR THAT PORTION OF A LAGGED TRENCH AGAINST

WHICH CONCRETE IS POURED, NAMELY, AS A SUBSTITUTE

FOR BACK FORMS (WHICH WORK IS PERFORMED BY

PILEDRIVERS): $0.13 PER HOUR ADDITIONAL.............$ 52.37 26.18

CARPENTER: (5) SAWFILER FOOTNOTE: WORK OF

FORMING IN THE CONSTRUCTION OF OPEN CUT SEWERS OR

STORM DRAINS, ON OPERATIONS IN WHICH HORIZONTAL

LAGGING IS USED IN CONJUNCTION WITH STEEL H-BEAMS

10/22/26, 11:17 AM SAM.gov https://sam.gov/wage-determination/CA20260014/7 2/27

DRIVEN OR PLACED IN PRE- DRILLED HOLES, FOR THAT

PORTION OF A LAGGED TRENCH AGAINST WHICH CONCRETE

IS POURED, NAMELY, AS A SUBSTITUTE FOR BACK FORMS

(WHICH WORK IS PERFORMED BY PILEDRIVERS): $0.13 PER

HOUR ADDITIONAL.....................................$ 52.34 26.18

CARPENTER: (6) SCAFFOLD BUILDER FOOTNOTE: WORK

OF FORMING IN THE CONSTRUCTION OF OPEN CUT SEWERS

OR STORM DRAINS, ON OPERATIONS IN WHICH HORIZONTAL

LAGGING IS USED IN CONJUNCTION WITH STEEL H-BEAMS

DRIVEN OR PLACED IN PRE- DRILLED HOLES, FOR THAT

PORTION OF A LAGGED TRENCH AGAINST WHICH CONCRETE

IS POURED, NAMELY, AS A SUBSTITUTE FOR BACK FORMS

(WHICH WORK IS PERFORMED BY PILEDRIVERS): $0.13 PER

HOUR ADDITIONAL.....................................$ 45.37 25.43

CARPENTER: (7) TABLE POWER SAW OPERATOR

FOOTNOTE: WORK OF FORMING IN THE CONSTRUCTION OF

OPEN CUT SEWERS OR STORM DRAINS, ON OPERATIONS IN

WHICH HORIZONTAL LAGGING IS USED IN CONJUNCTION

WITH STEEL H-BEAMS DRIVEN OR PLACED IN PRE- DRILLED

HOLES, FOR THAT PORTION OF A LAGGED TRENCH AGAINST

WHICH CONCRETE IS POURED, NAMELY, AS A SUBSTITUTE

FOR BACK FORMS (WHICH WORK IS PERFORMED BY

PILEDRIVERS): $0.13 PER HOUR ADDITIONAL.............$ 52.34 26.18

CARP0213-002 07/01/2025

Rates Fringes

DIVER: (1) WET AMOUNTS IN ""RATES' COLUMN ARE PER

DAY.................................................$ 901.92 26.18

DIVER: (2) STANDBY AMOUNTS IN ""RATES' COLUMN ARE

PER DAY.............................................$ 450.96 26.18

DIVER: (3) TENDER AMOUNTS IN ""RATES' COLUMN ARE

PER DAY.............................................$ 442.96 26.18

DIVER: (4) ASSISTANT TENDER AMOUNTS IN ""RATES'

COLUMN ARE PER DAY..................................$ 418.96 26.18

CARP0213-004 07/01/2025

Rates Fringes

DRYWALL (DRYWALL INSTALLER/LATHER)..................$ 52.24 26.18

DRYWALL (STOCKER/SCRAPPER)..........................$ 21.45 11.27

CARP0721-001 07/01/2025

Rates Fringes

MODULAR FURNITURE INSTALLER.........................$ 25.00 13.06

ELEC0413-001 01/01/2026

Rates Fringes

ELECTRICIANS CABLE SPLICERS: $2.00 ADDITIONAL

PER HOUR. ALL WORK AT VANDENBERG AFB: $3.75

ADDITIONAL PER HOUR. FOOTNOTE: WORK FROM TRUSSES,

SWINGING SCAFFOLDS, OPEN LADDERS, SCAFFOLDS,

BOSUN'S CHAIRS, STACKS, OR THE MAINTENANCE OF

TOWERS OR OPEN PLATFORMS WHERE THE WORKER IS

SUBJECT TO A DIRECT FALL OR WHERE THE WORKER HAS TO

WORK FROM A LADDER OR OTHER SUPPORT FROM A PLATFORM

WITHIN 5 FT. OF ANY DIRECT FALL A DISTANCE OF 50

FT. FROM THE GROUND FLOOR OR SUPPORTING STRUCTURE:

DOUBLE THE REGULAR STRAIGHT-TIME RATE OF PAY.

SAFETY NETS, IF USED, WILL NOT INVALIDATE THIS......$ 54.61 25.16

ELEC0413-003 12/31/2024

10/22/26, 11:17 AM SAM.gov https://sam.gov/wage-determination/CA20260014/7 3/27

Rates Fringes

COMMUNICATIONS SYSTEM: INSTALLER COMMUNICATIONS

AND SYSTEMS WORK SCOPE OF WORK: INSTALLATION,

TESTING, SERVICE AND MAINTENANCE OF SYSTEMS

UTILIZING THE TRANSMISSION AND/OR TRANSFERENCE OF

VOICE, SOUND, VISION AND DIGITAL FOR COMMERCIAL,

EDUCATIONAL, SECURITY AND ENTERTAINMENT PURPOSES

FOR THE FOLLOWING: TV MONITORING AND SURVEILLANCE,

BACKGROUND-FOREGROUND MUSIC, INTERCOM AND TELEPHONE

INTERCONNECT, INVENTORY CONTROL SYSTEMS, MICROWAVE

TRANSMISSION, MULTI-MEDIA, MULTIPLEX, NURSE CALL

SYSTEMS, RADIO PAGE, SCHOOL INTERCOM AND SOUND,

BURGLAR ALARMS, FIRE ALARM (SEE LAST PARAGRAPH

BELOW) AND LOW VOLTAGE MASTER CLOCK SYSTEMS IN

COMMERCIAL BUILDINGS. COMMUNICATION SYSTEMS THAT

TRANSMIT OR RECEIVE INFORMATION AND/OR CONTROL

SYSTEMS THAT ARE INTRINSIC TO THE ABOVE LISTED

SYSTEMS; INCLUSION OR EXCLUSION OF TERMINATIONS AND

TESTINGS OF CONDUCTORS DETERMINED BY THEIR

FUNCTION; EXCLUDING ALL OTHER DATA SYSTEMS OR

MULTIPLE SYSTEMS WHICH INCLUDE CONTROL FUNCTION OR

POWER SUPPLY; EXCLUDING INSTALLATION OF RACEWAY

SYSTEMS, CONDUIT SYSTEMS, LINE VOLTAGE WORK, AND

ENERGY MANAGEMENT SYSTEMS. DOES NOT COVER WORK

PERFORMED AT CHINA LAKE NAVAL ORDNANCE TEST

STATION. FIRE ALARM WORK SHALL BE PERFORMED AT THE

CURRENT INSIDE WIREMAN TOTAL COST PACKAGE...........$ 48.13 17.49

ELEC1245-001 01/01/2025

Rates Fringes

LINE CONSTRUCTION: (1) LINEMAN; CABLE SPLICER

HOLIDAYS: NEW YEAR'S DAY, M.L. KING DAY, MEMORIAL

DAY, INDEPENDENCE DAY, LABOR DAY, VETERANS DAY,

THANKSGIVING DAY AND DAY AFTER THANKSGIVING,

CHRISTMAS DAY.......................................$ 70.16 24.71

LINE CONSTRUCTION: (2) EQUIPMENT SPECIALIST

(OPERATES CRAWLER TRACTORS, COMMERCIAL MOTOR

VEHICLES, BACKHOES, TRENCHERS, CRANES (50 TONS AND

BELOW), OVERHEAD & UNDERGROUND DISTRIBUTION LINE

EQUIPMENT) HOLIDAYS: NEW YEAR'S DAY, M.L. KING

DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY,

VETERANS DAY, THANKSGIVING DAY AND DAY AFTER

THANKSGIVING, CHRISTMAS DAY.........................$ 53.30 22.26

LINE CONSTRUCTION: (3) GROUNDMAN HOLIDAYS: NEW

YEAR'S DAY, M.L. KING DAY, MEMORIAL DAY,

INDEPENDENCE DAY, LABOR DAY, VETERANS DAY,

THANKSGIVING DAY AND DAY AFTER THANKSGIVING,

CHRISTMAS DAY.......................................$ 40.76 21.76

ELEV0018-001 01/01/2025

Rates Fringes

ELEVATOR MECHANIC FOOTNOTE: A. PAID VACATION:

EMPLOYER CONTRIBUTES 8% OF REGULAR HOURLY RATE AS

VACATION PAY CREDIT FOR EMPLOYEES WITH MORE THAN 5

YEARS OF SERVICE, AND 6% FOR 6 MONTHS TO 5 YEARS OF

SERVICE. B. PAID HOLIDAYS: NEW YEAR'S DAY,

MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY,

VETERANS' DAY, THANKSGIVING DAY, FRIDAY AFTER

THANKSGIVING, AND CHRISTMAS DAY.....................$ 69.43 38.44

ENGI0012-004 08/01/2025

Rates Fringes

10/22/26, 11:17 AM SAM.gov https://sam.gov/wage-determination/CA20260014/7 4/27

OPERATOR, POWER EQUIPMENT: (1) LEVERMAN (DREDGING)..$ 67.90 40.95

OPERATOR, POWER EQUIPMENT: (2) DREDGE DOZER

(DREDGING)..........................................$ 61.93 40.95

OPERATOR, POWER EQUIPMENT: (3) DECKMATE (DREDGING)..$ 61.82 40.95

OPERATOR, POWER EQUIPMENT: (4) WINCH OPERATOR

(STERN WINCH ON DREDGE) (DREDGING)..................$ 61.27 40.95

OPERATOR, POWER EQUIPMENT: (5) FIREMAN-OILER,

DECKHAND, BARGEMAN, LEVEEHAND (DREDGING)............$ 60.73 40.95

OPERATOR, POWER EQUIPMENT: (6) BARGE MATE

(DREDGING)..........................................$ 61.34 40.95

ENGI0012-024 07/01/2025

Rates Fringes

OPERATOR: POWER EQUIPMENT, ALL OTHER WORK: GROUP

1- BARGEMAN; BRAKEMAN; COMPRESSOR OPERATOR; DITCH

WITCH, WITH SEAT OR SIMILAR TYPE EQUIPMENT;

ELEVATOR OPERATOR-INSIDE; ENGINEER OILER; FORKLIFT

OPERATOR (INCLUDES LOED, LULL OR SIMILAR TYPES

UNDER 5 TONS; GENERATOR OPERATOR; GENERATOR, PUMP

OR COMPRESSOR PLANT OPERATOR; PUMP OPERATOR;

SIGNALMAN; SWITCHMAN PREMIUM PAY: $10.00 PER HOUR

SHALL BE PAID ON ALL POWER EQUIPMENT OPERATOR WORK

ON THE FOLLOWNG MILITARY BASES: CHINA LAKE NAVAL

RESERVE, VANDENBERG AFB, POINT ARGUELLO, SEELY

NAVAL BASE, FORT IRWIN, NEBO ANNEX MARINE BASE,

MARINE CORP LOGISTICS BASE YERMO, EDWARDS AFB, 29

PALMS MARINE BASE AND CAMP PENDLETON WORKERS

REQUIRED TO SUIT UP AND WORK IN A HAZARDOUS

MATERIAL ENVIRONMENT: $2.00 PER HOUR ADDITIONAL.

COMBINATION MIXER AND COMPRESSOR OPERATOR ON GUNITE

WORK SHALL BE CLASSIFIED AS A CONCRETE MOBILE MIXER

OPERATOR............................................$ 63.40 33.20

OPERATOR: POWER EQUIPMENT, ALL OTHER WORK: GROUP

2- ASPHALT-RUBBER PLANT OPERATOR (NURSE TANK

OPERATOR);COIL TUBING RIG OPERATOR, CONCRETE MIXER

OPERATOR-SKIP TYPE; CONVEYOR OPERATOR; FIREMAN;

FORKLIFT OPERATOR (INCLUDES LOED, LULL OR SIMILAR

TYPES OVER 5 TONS; HYDROSTATIC PUMP OPERATOR; OILER

CRUSHER (ASPHALT OR CONCRETE PLANT); PETROMAT

LAYDOWN MACHINE; PJU SIDE DUM JACK; SCREENING AND

CONVEYOR MACHINE OPERATOR (OR SIMILAR TYPES);

SKIPLOADER (WHEEL TYPE UP TO 3/4 YD. WITHOUT

ATTACHMENT); TAR POT FIREMAN; TEMPORARY HEATING

PLANT OPERATOR; TRENCHING MACHINE OILER PREMIUM

PAY: $10.00 PER HOUR SHALL BE PAID ON ALL POWER

EQUIPMENT OPERATOR WORK ON THE FOLLOWNG MILITARY

BASES: CHINA LAKE NAVAL RESERVE, VANDENBERG AFB,

POINT ARGUELLO, SEELY NAVAL BASE, FORT IRWIN, NEBO

ANNEX MARINE BASE, MARINE CORP LOGISTICS BASE

YERMO, EDWARDS AFB, 29 PALMS MARINE BASE AND CAMP

PENDLETON WORKERS REQUIRED TO SUIT UP AND WORK

IN A HAZARDOUS MATERIAL ENVIRONMENT: $2.00 PER HOUR

ADDITIONAL. COMBINATION MIXER AND COMPRESSOR

OPERATOR ON GUNITE WORK SHALL BE CLASSIFIED AS A

CONCRETE MOBILE MIXER OPERATOR......................$ 64.18 33.20

OPERATOR: POWER EQUIPMENT, ALL OTHER WORK: GROUP

3- ASPHALT-RUBBER BLEND OPERATOR; BOBCAT OR SIMILAR

TYPE (SKID STEER); EQUIPMENT GREASER (RACK); FORD

FERGUSON (WITH DRAGTYPE ATTACHMENTS); HELICOPTER

RADIOMAN (GROUND); STATIONARY PIPE WRAPPING AND

CLEANING MACHINE OPERATOR PREMIUM PAY: $10.00 PER

HOUR SHALL BE PAID ON ALL POWER EQUIPMENT OPERATOR

WORK ON THE FOLLOWNG MILITARY BASES: CHINA LAKE

NAVAL RESERVE, VANDENBERG AFB, POINT ARGUELLO,

10/22/26, 11:17 AM SAM.gov https://sam.gov/wage-determination/CA20260014/7 5/27

SEELY NAVAL BASE, FORT IRWIN, NEBO ANNEX MARINE

BASE, MARINE CORP LOGISTICS BASE YERMO, EDWARDS

AFB, 29 PALMS MARINE BASE AND CAMP PENDLETON

WORKERS REQUIRED TO SUIT UP AND WORK IN A HAZARDOUS

MATERIAL ENVIRONMENT: $2.00 PER HOUR ADDITIONAL.

COMBINATION MIXER AND COMPRESSOR OPERATOR ON GUNITE

WORK SHALL BE CLASSIFIED AS A CONCRETE MOBILE MIXER

OPERATOR............................................$ 64.67 33.20

OPERATOR: POWER EQUIPMENT, ALL OTHER WORK: GROUP

4- ASPHALT PLANT FIREMAN; BACKHOE OPERATOR

(MINI-MAX OR SIMILAR TYPE); BORING MACHINE

OPERATOR; BOXMAN OR MIXERMAN (ASPHALT OR CONCRETE);

CHIP SPREADING MACHINE OPERATOR; CONCRETE CLEANING

DECONTAMINATION MACHINE OPERATOR; CONCRETE PUMP

OPERATOR (SMALL PORTABLE);DIRECT PUSH OPERATOR

(GEOPROBE OR SIMILAR TYPES) DRILLING MACHINE

OPERATOR, SMALL AUGER TYPES (TEXOMA SUPER

ECONOMATIC OR SIMILAR TYPES - HUGHES 100 OR 200 OR

SIMILAR TYPES - DRILLING DEPTH OF 30' MAXIMUM);

EQUIPMENT GREASER (GREASE TRUCK); GUARD RAIL POST

DRIVER OPERATOR; HIGHLINE CABLEWAY SIGNALMAN;

HYDRA-HAMMER-AERO STOMPER; MICRO TUNNELING (ABOVE

GROUND TUNNEL); POWER CONCRETE CURING MACHINE

OPERATOR; POWER CONCRETE SAW OPERATOR; POWER-DRIVEN

JUMBO FORM SETTER OPERATOR; POWER SWEEPER OPERATOR;

ROCK WHEEL SAW/TRENCHER; ROLLER OPERATOR

(COMPACTING); SCREED OPERATOR (ASPHALT OR

CONCRETE); TRENCHING MACHINE OPERATOR (UP TO 6

FT.); VACUUM OR MUCH TRUCK PREMIUM PAY: $10.00

PER HOUR SHALL BE PAID ON ALL POWER EQUIPMENT

OPERATOR WORK ON THE FOLLOWNG MILITARY BASES: CHINA

LAKE NAVAL RESERVE, VANDENBERG AFB, POINT ARGUELLO,

SEELY NAVAL BASE, FORT IRWIN, NEBO ANNEX MARINE

BASE, MARINE CORP LOGISTICS BASE YERMO, EDWARDS

AFB, 29 PALMS MARINE BASE AND CAMP PENDLETON

WORKERS REQUIRED TO SUIT UP AND WORK IN A HAZARDOUS

MATERIAL ENVIRONMENT: $2.00 PER HOUR ADDITIONAL.

COMBINATION MIXER AND COMPRESSOR OPERATOR ON GUNITE

WORK SHALL BE CLASSIFIED AS A CONCRETE MOBILE MIXER

OPERATOR............................................$ 65.96 33.20

OPERATOR: POWER EQUIPMENT, ALL OTHER WORK: GROUP

6- ARTICULATING MATERIAL HAULER; ASPHALT PLANT

ENGINEER; BATCH PLANT OPERATOR; BIT SHARPENER;

CONCRETE JOINT MACHINE OPERATOR (CANAL AND SIMILAR

TYPE); CONCRETE PLANER OPERATOR; DANDY DIGGER; DECK

ENGINE OPERATOR; DERRICKMAN (OILFIELD TYPE);

DRILLING MACHINE OPERATOR, BUCKET OR AUGER TYPES

(CALWELD 100 BUCKET OR SIMILAR TYPES - WATSON 1000

AUGER OR SIMILAR TYPES - TEXOMA 330, 500 OR 600

AUGER OR SIMILAR TYPES - DRILLING DEPTH OF 45'

MAXIMUM); DRILLING MACHINE OPERATOR; HYDROGRAPHIC

SEEDER MACHINE OPERATOR (STRAW, PULP OR SEED),

JACKSON TRACK MAINTAINER, OR SIMILAR TYPE;

KALAMAZOO SWITCH TAMPER, OR SIMILAR TYPE; MACHINE

TOOL OPERATOR; MAGINNIS INTERNAL FULL SLAB

VIBRATOR, MECHANICAL BERM, CURB OR GUTTER(CONCRETE

OR ASPHALT); MECHANICAL FINISHER OPERATOR

(CONCRETE, CLARY-JOHNSON-BIDWELL OR SIMILAR); MICRO

TUNNEL SYSTEM (BELOW GROUND); PAVEMENT BREAKER

OPERATOR (TRUCK MOUNTED); ROAD OIL MIXING MACHINE

OPERATOR; ROLLER OPERATOR (ASPHALT OR FINISH),

RUBBER-TIRED EARTH MOVING EQUIPMENT (SINGLE ENGINE,

UP TO AND INCLUDING 25 YDS. STRUCK); SELF-PROPELLED

TAR PIPELINING MACHINE OPERATOR; SKIPLOADER

OPERATOR (CRAWLER AND WHEEL TYPE, OVER 3/4 YD. AND

10/22/26, 11:17 AM SAM.gov…

This is the start of the file's text. The full file is on GovTribe.