MASTER_Q_A_0002.xlsx

XLSX spreadsheet 103 KB Posted

Attached to
Portable Toilet Services - ZION National Park
Solicitation number
140PP027Q0019
Issued by
Not on record

About this file

This file is a Questions and Answers document for Solicitation 140PP027Q0019, addressing contractor inquiries regarding portable toilet services at Zion National Park. The Q&A clarifies key contractual requirements including pricing methodology, unit specifications, emergency operations, and service logistics across five fiscal years (FY27-FY31) beginning January 1, 2027.

Critical clarifications include: (1) pricing of zero-unit months requires removal fees only when units were previously delivered; (2) septic cleaning requirements have been removed from scope; (3) emergency services and placements are priced per unit and incorporated into a funded "Not to Exceed" CLIN structure with a 24-hour response requirement; (4) ADA-accessible and handwashing station units are not required, with a minimum 60-gallon capacity specified; (5) contractors are responsible for locating approved off-site waste disposal facilities, with no park-provided dump station or water access; (6) a pre-bid site visit was held on November 12, 2026; (7) the applicable small business size standard is $9.0M under NAICS 562991; (8) subcontracting arrangements with qualified small businesses are permissible provided limitations on subcontracting are met per FAR 52.219-14; and (9) insurance requirements apply to the prime contractor with certificates of insurance due post-award. The monthly price schedule was revised to correct year labels, resolve service-count conflicts, and clarify emergency pricing structures. The incumbent contractor owns existing units under Contract 140P1222P0018, with new portable toilets permitted placement up to two days prior to January 1, 2027, ensuring continuous service at multiple park locations including East Entrance, Petting Zoo, Oak Creek, and Shooting Range.

View the file

Other files

File Type Posted
Sol_140PP027Q0019_Amd_0003.pdf PDF
Monthly_Pricing_Schedule_11_18_2026_0003.xlsx XLSX spreadsheet
Portable_Toilet_Map_(1)_0003.png PNG image
Statement_of_Work_11_18_2026_0003.docx DOCX document
MASTER_Q_A_11_18_2026_0003.xlsx XLSX spreadsheet
Sol_140PP027Q0019_Amd_0002.pdf PDF
A04_-_Revised_Statement_of_Work_0002.docx DOCX document
Attachment_4_-_Monthly_Price_Schedule_0002.xlsx XLSX spreadsheet
Sol_140PP027Q0019_Amd_0001.pdf PDF
Attachment_3_-_Q_A_Document.xlsx XLSX spreadsheet
Attachment_2_-_Applicable_Wage_Determinations.pdf PDF
Attachment_1_-_Statement_of_Work.pdf PDF
Attachment_5_-_Subcontracting_Worksheet.docx DOCX document
Sol_140PP027Q0019.pdf PDF
Attachment_4_-_Monthly_Price_Schedule.xlsx XLSX spreadsheet
Show all 15

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sheet1

Questions & Answers Document
#Contractor QuestionReferenceGovernment ResponseReference
1Example: The specifications state that wiring is to be used inside of the conduit. What type of wiring is to be used?SOW 1.7.12, Drawings pg2Example: Wiring is to be copper AWG 12. SOW has been updated.SOW 1.7.12
2Rows with 0 units (East Entrance, Petting Zoo, Temple, Canyon Junction-2): should these be priced at $0 or as a per-service rate only? How will they be evaluated?Attachment 4 - Monthly Price ScheduleFor any locations with a zero (0) the contractor must take into consideration whether or not a unit was placed there in the prior months. A fee is expected for "removal" of the unit if one is not needed for that month, as indicated by a zero (0). A "first time" zero (0) where no unit was previously delivered would have no fee included. For example, the East Entrance in January 2027 has a zero (0) and no previous delivery - so the Per unit Rate would be $0. Likewise, Oak Creek has a One (1) all the way until October 2027, where it reads zero (0). The NPS expects a fee for removal of the unit to coincide with that zero (0) where a unit had been presently devliered and is (assumed) to still be in place. These will be evaluated based on the Price displayed in Cell F184 as the "Total Evaluated Price."CO RESPONSE and Revised Monthly Price Schedule
3What do "Temple*" and "*Septic Cleaning" in April and October mean? Is septic or vault pumping at the Temple of Sinawava in scope, and how does it relate to contract 140P1225P0007?Attachment 4 - Monthly Price ScheduleSeptic requirement has been removed, per the Park.CO RESPONSE
4Are Emergency Service (300 or 320 per year) and Emergency Placement (15 or 30 per year) included in the Total Evaluated Price at those quantities? What response time is required for an "emergency"?Attachment 4 - Monthly Price Schedule; Attachment 1 - SOWYes. Note the Pricing Sheet automatically incorporates the pricing added by the contractor in those highlighted "Emergency" sections to the total, overall, fee on the sheet. The CO will be utilizing the Total on that Sheet as the "Total Evaluated Price" as it pertains to quote evaluation.To make the Park's desire for this effort more contracturally feasible, the CO has added CLIN's 0011 to 0051 to the 1449 Schedule. The Emergency CLIN's on the 1449 Schedule will equal the total amounts quoted for both Emergency Services and Emergency Placement as listed on the Price Sheet. The Emergency CLINS (again CLINS 0011 to 0051) will be funded "NOT TO EXCEED" CLINS as T&M CLINS are currently not allowable under current DOI Policy. See revised Statement of Work, Section 5, entitled "Emergency Operations." See revised 1449 Schedule.CO RESPONSE, Revised SOW 11/5/2026 Section 5, revised 1449 CLIN Schedule and Revised Monthly Price schedule
5Are any units required to be ADA-accessible? Are hand-wash stations or hand sanitizer acceptable, or only waterless soap?Attachment 1 - SOWSee SOW Section 3, para 7.Revised SOW 11/5/2026 Section 3 Paragraph 7
6Size standard: the solicitation text states $7.5M while Block 10 states $9M. Please confirm the applicable size standard is $9.0M (NAICS 562991).Solicitation 140PP027Q0019, Block 10Thank you - this was a CO clerical error and has been corrected to $9M per the SBA Table of Size Standards.Revised 1449 Solicitation
7Which waste disposal / dump stations are permitted? Does the park provide an in-park dump station available to the contractor?Attachment 1 - SOWNo in-park dump station is available. It is the contractors responsiblilty to locate and confirm approved dump locations.Zion National Park Response
8Will a site visit be offered? Can the Government provide a map or coordinates for each unit location?Attachment 1 - SOW; Attachment 4A site visit has been requested by multiple interested parties. Therefore, the Park has established a site visit for 11/12/2026 at 1PM.CO RESPONSE, Revised 1449 Solicitation
9What unit type is currently in place, and who owns the existing units (incumbent or NPS)? Is there a transition period at the January 1 start?Attachment 1 - SOWAn incumbent (outside contractor) owns and services the existing portables (Contract 140P1222P0018 awarded to Wayne A. Levitz). There is space available at each location for the new portables to be placed during the transition. The new portables may be placed and locked at each location no more than 2 days prior to Jan 1 to ensure no lapse in service. New units will be unlocked and ready for service on Jan 1.
10Please confirm that each tab of the Monthly Price Schedule applies to the performance year in its tab name (FY27 through FY31), with the unit quantities and monthly service counts shown for that tab. Several monthly headers still show 2026. Could corrected year labels be provided so the delivery and servicing schedules align with the 2027-2031 performance periods?Attachment 4, FY27-FY31 Quote tabs, monthly headers; SOW section XI; solicitation base/option periods.The NPS has corrected the year errors stated in the pricing sheet.Revised Monthly Price Schedule
12Does the required portable-toilet mix include ADA-accessible units? If so, please identify the applicable locations, quantities and periods in the Monthly Price Schedule, and any required unit specifications.SOW section III and section XI; Attachment 4 location/quantity rows; solicitation technical factor 2, Product Data.The NPS has clarified that ADA Toilets are NOT a requirement. See SOW Section 4.Revised SOW 11/5/2026 Section 4
13Subcontracting arrangement and worksheet: We propose using a qualified local small-business subcontractor to provide the units and perform delivery, servicing, relocation, and removal, while [Contractor] retains contract administration and quality oversight. Please confirm whether this arrangement is permitted and explain the applicable calculation under Attachment 5, including how costs paid to a similarly situated subcontractor should be reported.Attahment 5 - Subcontracting WorksheetThis is permissible, in general but the government will not do your homework for you. See Clause FAR 52.219-14. The Worksheet includes a mathematical breakdown of how it's factored. Please use the sheet or come up with one of your own. So long as your submission with your quote proves your firm meets the necessary requirements of limitations on subcontracting, the arrangement is permissible.FAR Clause 52.219-14
15Additional services: Please clarify how emergency services, additional placements, and septic cleaning should be priced, whether the listed quantities are estimates, and how these items will be included in the evaluated total.Attachment 4 & Attachment 1 - Statement of WorkThis answer is similar to Q4 above, the NPS has drastically updated the SOW to better define emergency work under SOW Section 5, Emergency Opertations. Septic is no longer included as of Amendment 02. The listed quantities ARE estimates, however, the prices included by the contractor in the emergency sections on the price sheet will be used for evaluation purposes of the Total Evaluated Price. The Park originally desired such CLIN's to be "options" but given the potential quantities, the CO determined such CLIN's should not be options (as the government would have to write an SF30 modification every time the Park needs an emergency toilet or service delivered). Instead, the CO will write the Emergency CLINS as funded Lump Sum "Not to Exceed" (NTE) CLINS. This method removes the need for arduous option mods and is also the CO's way of "working with" the limitations the DOI has placed on using T&M CLINS, which are currently (Generally Speaking) not allowable under this administration.CO RESPONSE, Revised SOW 11/5/2026 Section 5, Revised Monthly Price Schedule and 1449 CLIN Schedule
17Question deadline: Please confirm the exact time and time zone for the November 11 close-of-business deadline.Solicitation - Question Submission InstructionsThe Questions Deadline has been updated to 11/18/2026 by COB. COB means Close of Business and the CO is not issuing a particular time. Submit remaining questions by the end of the day, please. They will be compiled and answered, the next business day.1449 Solicitation and CO RESPONSE.
28Is there a park dump station or designated disposal facility the contractor may use for waste pumped from the units, or must all waste be hauled off-site? Will the park provide water or a staging area for contractor equipment?SOW III.1, III.8, VII; Solicitation pg 5, 8All waste will be hauled off-site. Water will not be provided.Zion National Park Response
29The SOW does not specify the portable toilet type. Should all units be standard portable toilets, or are any ADA-accessible units, flushing units or handwashing stations required? If ADA units are needed, how many and at which locations?SOW III.6, III.7; Solicitation pg 12; Attachment 4The SOW has been updated. ADA are not required. Handwashing stations are not required. A minimum of 60 gallons has been added to the SOW along with a requirement to have the name of the company somewhere on the unit.Revised Statement of Work 11/5/2026.
31Will NPS issue a corrected monthly schedule confirming all quantities, dates, locations, and service counts? Shooting Range shows once weekly but only twice monthly, and several option tabs retain old calendar years.Attachment 4 (all tabs); SOW XI.1; Solicitation pg 11See revised Price Sheet/Schedule. The Park had notes originally included explaining why there were some 1 per week but 5 services or 3 per week with 15 services total, etc. However, the CO has done a complete revamp of the per week to match the per month, line for line. This was done for simplicity and clarity. Park notes removed.Revised Monthly Price Schedule
32Which controls when weekly and monthly service counts conflict?Attachment 4 (Notes 1 & 8); Solicitation pg 11See Q31 answer above. The conflicts have been resovled per the CO's descretion.CO RESPONSE
35How are emergency services and placements ordered and paid under the annual fixed-price structure? Are rates per toilet or per dispatch, and what response times apply?Attachment 4 (Emergency lines); SOW III.3, III.9, III.15; Solicitation pg 3, 5, 11, 12The prices on the Price Sheet for Emergency work are priced "per unit." The CO has added Section 5 Emergency Operations to the SOW to clarify what each of these means and has included response times therein. If the government suddenly needs a unit at Oak Creek in December 2027, for example, the Government would notify the contractor of the need and the expectation is to have that unit delivered within 24 hours of receipt of the notification. The contractor can then bill CLIN 0011 at the unit price proposed in Cell C173, as CLIN 0011 will be a funded NTE CLIN, set up to swiftly pay for such scenarios without having to issue an option or mod. Similar mechanics apply for Emergency Services.Revised Monthly Price Schedule, Revised SOW 11/5/2026, and CO RESPONSE
37May the contractor use a park disposal facility or water source? Please identify truck-access restrictions and permitted servicing hours.SOW III.1, III.8, III.12, VII, X, XI.2; Solicitation pg 8, 15NO park disposal facility. The park is open 24 hours a day. Portable toilet locations are accessable at all times.Zion National Park Response
38How does this scope differ from 140P1222P0018?SOW I–III, XI; Attachment 4; Contract 140P1222P0018The two are generally the same. This new scope clarifies the potential emergency need.Zion National Park Response
43Under DOI 1452.228-70, please confirm: (a) whether the insurance requirement is firm as written; (b) the minimum coverage amounts that apply to the prime contractor; (c) when the certificate of insurance must be demonstrated (with the quote, at award, or before performance begins); and (d) whether the performing subcontractor's coverage can satisfy the requirement, in whole or in part.Solicitation clause 1452.228-70Insurance applies to the Prime Contractor - the government wont have a formal relationship with a Subcontractor which makes it difficult to hold them to insurance requirements. The COI can be provided to the CO post-award and is not an evaluation factor. It is the CO's opinion that Subcontractor coverage does not satisfy the requirement, per the clauses inclusion within the solicitation itself (which applies to the Prime). Insurance is a mandatory requirement for a contract like this where the public can be quite abusive to these units, historically. Reliance on the sub (or supplier) for insurance creates significant risk to the NPS. The CO is open, however, to further consideration. If utilizing subcontractor insurance is "commercial practice" under portable toilet servicing, please provide the government with additional details prior to the final Questions Due Date, using the Q&A form provided in the solicitation.CO RESPONSE & Clause 1452.228-70
44
45
46
47
48
49
50