This is a Statement of Work (SOW) for portable toilet placement and service at Zion National Park, effective January 1, 2027 through December 31, 2031, comprising a one-year base period and four optional one-year periods.

The contractor must furnish all labor, materials, supplies, and parts to deliver, place, maintain, and service portable toilet units in designated high-visitor-use areas throughout the park. Key performance requirements include: maintaining units in clean, sanitary condition with interior surfaces sanitized at each service; equipping units with dual toilet paper dispensers and wall-mounted waterless hand soap dispensers, both adequately stocked; removing graffiti within 24 hours of notification; repairing or replacing damaged units within 24 hours; conducting routine pumping and servicing per standard commercial practices to ensure health and safety; submitting quarterly usage and servicing reports to the Contracting Officer and Contracting Officer's Representative; and adhering to all OSHA standards. Minimum portable toilet capacity is 60 gallons; ADA-accessible toilets and handwashing stations are not required. The contractor must provide a Safety Plan and Spill Plan for review by the Park Safety Officer after contract award. Emergency services provisions allow the NPS to request emergency unit placement (delivery within 24 hours) or emergency servicing (within 24 hours of written notice), to be billed against designated emergency Not-To-Exceed CLINs at rates established in the Price Sheet. The place of performance is Zion National Park, State Route 9, Springdale, Utah 84767. The Contracting Officer is Cole Johnson (Cole_Johnson@ios.doi.gov), and the Contracting Officer's Representative is Matthew MacKay, (435) 772-0207. Unit locations and quantities are specified in an attached Monthly Quote Schedule.xlsx.

View the file

Other files

File Type Posted
Sol_140PP027Q0019_Amd_0003.pdf PDF
Monthly_Pricing_Schedule_11_18_2026_0003.xlsx XLSX spreadsheet
Portable_Toilet_Map_(1)_0003.png PNG image
Statement_of_Work_11_18_2026_0003.docx DOCX document
MASTER_Q_A_11_18_2026_0003.xlsx XLSX spreadsheet
Sol_140PP027Q0019_Amd_0002.pdf PDF
Attachment_4_-_Monthly_Price_Schedule_0002.xlsx XLSX spreadsheet
MASTER_Q_A_0002.xlsx XLSX spreadsheet
Sol_140PP027Q0019_Amd_0001.pdf PDF
Attachment_3_-_Q_A_Document.xlsx XLSX spreadsheet
Attachment_2_-_Applicable_Wage_Determinations.pdf PDF
Attachment_1_-_Statement_of_Work.pdf PDF
Attachment_5_-_Subcontracting_Worksheet.docx DOCX document
Sol_140PP027Q0019.pdf PDF
Attachment_4_-_Monthly_Price_Schedule.xlsx XLSX spreadsheet
Show all 15

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATEMENT OF WORK

Portable Toilet Placement and Service

ZION NATIONAL PARK

November 5, 2026

1. INTRODUCTION:

The National Park Service has a need to place and service temporary toilet facilities in high visitor use areas to supplement existing restroom facilities. The contractor shall furnish all labor, materials, supplies, and parts to maintain portable toilets in a safe operating condition and in accordance with the specifications outlined in this Statement of Work (SOW).

2. BACKGROUND:

Zion National Park provides access to millions of visitors each year. Due to the ever-increasing number of visitors, it is necessary to supplement existing toilet facilities with portable toilets. This will ensure the health, safety, and enjoyment of the Parks visitors.

3. SPECIFIC TASKS OR REQUIREMENTS:

1) Furnish all labor, materials, and supplies to maintain portable toilets in a safe operating condition and in accordance with the following specifications. Skilled, trained personnel shall be used by the awardee of this contract and supervised by the contractor

2) Maintain the units in a clean, orderly, and sanitary manner.

3) Graffiti or other surface markings shall be removed within 24 hours of notification to the contractor or as soon as identified by the contractor itself.

4) Units shall be free of litter and routinely maintained.

5) Interior surfaces shall be wiped down and sanitized with a disinfectant cleaning product with every service.

6) Units shall be equipped with dual toilet paper dispensers which shall be adequately stocked with each service.

7) Units shall be equipped with wall-mounted waterless hand soap dispensers and shall be adequately stocked with each service.

8) Pumping and servicing of units will be scheduled to maintain the health and safety of the user, per standard commercial practices/frequency.

9) Damaged or deficient units shall be repaired or replaced within 24 hours.

10) Conduct regular inspections and maintenance to ensure units are in good working condition.

11) Contractor shall provide a record of servicing and quantity of use throughout the contract on a quarterly basis by submitting usage reports to the NPS Contracting Officer and Contracting Officer Representative.

12) Contractor shall provide for visitor safety and adhere to all OSHA Standards throughout the performance of the contract.

13) Contractor shall provide a Safety Plan for all operations and a Spill Plan to be reviewed by Park Safety Officer after award of the contract.

14) Report any conditions requiring work outside the scope of this contract to the Park COR.

15) Quantity of Portable Toilets needed, and locations may vary, according to Park’s needs. In the event additional quantities are required, the CO will exercise the Increased Quantities Clause and modify the contract to reflect the need for additional units.

4. PERFORMANCE REQUIREMENTS:

Contractor shall perform all work to include rental, delivery, routine pumping, cleaning, supplies, waste disposal, and removal of portable toilets to/from designated locations.

Septic pumping/cleaning is not a part of this contract.

All units shall be delivered and maintained in full operational condition.

The name of the portable toilet supplier/servicer shall be displayed on each unit.

Each unit has a minimum 60 gallon requirement, units delivered below this requirement will not be accepted.

ADA accessible toilets are not required.

Handwashing stations are not required.

5. EMERGENCY OPERATIONS (CLINS 0011, 0021, 0031, 0041, and 0051) During performance of this contract, the NPS may require the contractor to perform emergency services, which will include:

a. Emergency Placement. The NPS will provide the contractor with a request for emergency unit placement, which will include the specific location of the required unit, in writing.

The contractor shall deliver the unit(s) within 24 hours of receipt of the written notice for emergency placement.

Emergency Placement shall be billed against the Emergency NTE CLIN’s at the rate established in the Price Sheet incorporated into the award, depending on the current year of service (0011 for Base, 0021 for Option Year 1, etc).

Note: The associated routine maintenance costs of any Emergency Placement unit must be modified into the contract, via a Request for Equitable Adjustment. The contractor is not required to service emergency placement units until such modification or direction from the CO, is made part of the contract.

b. Emergency Services. The NPS will provide the contractor with a request for Emergency Service for any on-site units that require immediate servicing outside the scope of routine maintenance. This requirement can be initiated by either party (Government or Contractor) but must be approved by the Contracting Officer or Contracting Officer Representative, in writing, prior to executing such services.

Emergency Services shall take place within 24 hours of receipt of a written Notice to Proceed which may come from either the CO or the COR.

Emergency Services shall be billed against the Emergency NTE CLIN’s at the rate established in the Price Sheet incorporated into the award, depending on the current year of service (0011 for Base, 0021 for Option Year 1, etc).

6. GOVERNMENT FURNISHED PROPERTY (GFP):

No Government furnished property will be provided.

7. DELIVERABLE REQUIREMENTS:

Toilets shall be delivered to the locations noted within the Pricing Sheet at the quantities listed therein. Any quantities listed with “0” units may be required IAW Emergency Placement terms and conditions, as stated in Section 5 above.

8. SECURITY:

Access passes may be issued by the NPS, post-award to more easily access areas typically limited by park fees. Contractors do NOT have to pay any Park fees in the execution of this contract.

9. SAFETY:

Safety is an extremely important value of NPS and all efforts regarding NPS’ safety and Contractor safety is expected.

Contractor is required to meet or exceed all OSHA regulations. Failure to comply with OSHA regulations may result in removal from the jobsite and subsequent disqualification from performing deliveries at any NPS’ site.

NPS’ sites are designated as NON-SMOKING.

Contractor is required to notify the NPS’ Tactical Security Operations Supervisor and the Safety and Health Department of all incidents (as described below), including minor incidents, occurring in the course of performing any NPS’ deliveries whether on NPS’ premises or any other location. Contractor will use Contractor’s own safety reporting protocol.

Contractor must complete an incident investigation in accordance with the Contractor written policy to identify the cause(s) and any action needed to prevent recurrence. Initial findings shall be provided to the park within 24 hours of incident with final report provided within ten (10) calendar days. Joint incident investigations with Contractors’ Safety Representative may be required when deemed necessary by NPS’ Safety & Health Office.

Hazards identified by the contractor that are within the control of NPS shall be reported to the NPS’ Safety & Health Office and the PM immediately. These hazards will be investigated, and corrective measures taken, when appropriate.

NPS’ Safety and Health Department requires notification immediately (no later than 3 hours) following any incident resulting in the following:

· Any incident requiring the call and dispatching of emergency services

· Death

· Hospitalization (contractor employee, subcontractor, public, etc.)

· Damage to any vehicle which renders it inoperable

· Amputation of any body part

· Electrical Contact

· Fire or Arc Blast

· Injury resulting in an unconscious employee

· Safety system failures (slings breaking, support structures collapse, etc.)

· Near miss that could have reasonably resulted in any of the above.

Contractor shall also be responsible for ensuring that contract personnel adhere to any and all health and safety protocols that may be in place.

10. PERIOD AND PLACE OF PERFORMANCE:

1) This contract is for a base period of January 1, 2027 through December 31, 2027 and four option years with period of performance from January 1 through December 31 of each year. Total Period of Performance is January1, 2027 through December 31, 2031.

2) Place of performance is as follows:Zion National Park
State Route 9
Springdale, Utah 84767

UNIT LOCATIONS & QUANTITIES

See attached Monthly Quote Schedule.xlsx for locations and quantities.

ADD COUNTIES HERE

11. REPORTS:

See Section V (Specific Tasks and Requirements) and Section VI (Performance Requirements) above.

12. NPS SPECIFIC SOW REQUIREMENTS:

The Contracting Officer is the duly appointed government representative, subject to their individual warranting levels, authorized to execute and administer this contract. Certain duties are delegable. Delegated duties will be identified in writing to the contractor prior to start of the contract. The primary delegation made will be to a “COR” or Contracting Officer’s Representative. Other authorities will be communicated prior to start of performance.

13. ADDITIONAL REQUIREMENTS:

CONTRACT ADMINISTRATION DATA

The Contracting Officer's Representative (COR) for this project is:

Matthew MacKay, National Park Service, Zion National Park Highway 9 Springdale, Utah 84767-1099 Telephone: (435) 772-0207.

The Contracting Officer for this project is:

Cole Johnson, CONOPS Central, National Park Service, DOI Cole_Johnson@ios.doi.gov

SPECIAL CONTRACT REQUIREMENTS Technical Direction

1) The COR will provide technical direction on contract performance. Technical direction includes:

(a). Guidance to the Contractor which assists in accomplishing the Scope of Work.
(b). Comments on an approval of reports or other deliverables.

2) Technical guidance from the COR will remain within the contract Scope of Work. The COR does not have the authority to issue technical direction which (1) institutes additional work outside the scope of the contract; (2) constitutes a change as defined in the "Changes" clause; (3) causes an increase or decrease in the estimated costs of the contract; (4) alters the period of performance; or (5) changes any of the other express terms or conditions of the contract.

3) Technical direction will be issued in writing by the COR or confirmed by them, in writing, five calendar days after verbal issuance.