Sol_140P8624R0017_Amd_0001.pdf
PDF 90 KB Posted
- Attached to
- PAINT THE POINT BONITA SUSPENSION BRIDGE
- Solicitation number
- 140P8624R0017
About this file
This document is an amendment to a solicitation (Solicitation Number: 140P8624R0017) for painting the Point Bonita Suspension Bridge at Golden Gate National Recreation Area in San Francisco, CA. The amendment updates the Terms and Conditions, provides a site visit sign-in sheet, and answers questions received from interested parties. Key updates include additional Key Personnel requirements in the evaluation criteria, specifications updates to reflect the Key Personnel changes, and clarification on the project duration, lead paint status, and painting requirements. The solicitation is a Service-Disabled Veteran-Owned Small Business (SDVOSB) set-aside, with a performance period of 305 days from the Notice to Proceed. The work involves full removal and sandblasting of the existing coating down to bare white metal. The National Park Service, Pacific West Region is the issuing agency.
View the file
Other files
Show all 21
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
(x)
140P8624R0017 x x
1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE
RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR
OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
x
PPG
San Francisco CA 94123 Building 201, Fort Mason
NPS, PWR - GOGA MABO
07/29/20240001
13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
FACILITY CODE CODE
10B. DATED (SEE ITEM 13)
10A. MODIFICATION OF CONTRACT/ORDER NO.
9B. DATED (SEE ITEM 11)
9A. AMENDMENT OF SOLICITATION NO.
CODE
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)
7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY
PAGE OF PAGES
4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)
1. CONTRACT ID CODE
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
07/10/2024
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority) appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
E. IMPORTANT: Contractor is not is required to sign this document and return __________________ copies to the issuing office.
ORDER NO. IN ITEM 10A.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
This amendment is being issued to update the Terms and conditions of the solicitation, provide sign-in sheet from site visit (ATTACHMENT 12), and answer questions received from interested parties.
A. Sections L and M of the solicitation have been updated to provide for additional Key
Personnel requirements that will be used in the evaluation process (ATTACHMENT 13).
B. Specifications (Attachment 1) have been updated to reflect moving the Key Personnel qualifications from the specifications to the evaluation factors.
C. The following questions have been received by interested parties:
Continued ...
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)
15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED
(Signature of person authorized to sign) (Signature of Contracting Officer)
Liset Gomez
STANDARD FORM 30 (REV. 11/2016)
Prescribed by GSA FAR (48 CFR) 53.243
Previous edition unusable
Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .
ITEM NO. SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
NAME OF OFFEROR OR CONTRACTOR
2 2
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF
(A) (B) (C) (D) (E) (F)
140P8624R0017/0001
Question 1: Is this Service Disable Veteran Owned
Small Business set aside?
Answer 1: Yes, this is SDVOSB.
Question 2: Is the site visit mandatory?
Answer 2: No, site visit is not mandatory but contractors are highly encouraged to attend.
Question 3: When does work start?
Answer 3: The work starts when Notice to Proceed is issued.
Question 4: How far down can the contractor drive to drop of materials?
Answer 4: Contractor may drive to Point Bonita tunnel. Materials can be carried from tunnel entrance to bridge using heavy equipment like a bobcat. Helicopter may also be used to drop off materials at the point Bonita Bridge.
Question 5: What is the project duration?
Answer 5: Project duration is 305 days from when
Notice to Proceed is issued per FAR Clause
52.211-10.
Question 6: Is there lead base paint on the bridge?
Answer 6: No lead base paint, this was built in
2012.
Questions 7: Is this full removal, sand blast?
Answer 7: Yes, it is full removal and sandblast down to bare white metal. Please refer to attached specifications.
Question 8: Can you provide the calculations for platform?
Question 8: Yes, is included as attachment 2. A full set of engineering drawings for the Point
Bonita Suspension Bridge. Contractor is responsible for calculations based upon the
Bridge engineering drawing.
All other terms and conditions remain the same.
NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)