This document is a set of project specifications for painting the Point Bonita Suspension Bridge at Golden Gate National Recreation Area. The key details are:
The National Park Service has a requirement to apply a new protective coating system to the Point Bonita Bridge. The work includes surface preparation, abatement of corrosion and salt deposits, application of an epoxy-based corrosion protection system to the metal components, pressure washing and painting the wood components, and concrete repair and sealing. The contractor will be responsible for constructing a temperature, climate, and humidity-controlled containment and scaffolding system to access all areas of the bridge. The project has a period of performance of 305 days after the notice to proceed. The contractor must submit various plans for the work, including safety, quality control, and environmental compliance. Key products required include specified coatings, sealants, and concrete repair materials. The contractor must comply with SSPC, NACE, and OSHA standards for surface preparation, coating application, and worker safety.
View the file
Other files
Show all 21
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
United States Department of the Interior
NATIONAL PARK SERVICE
Golden Gate National Recreation Area Building 201, Fort Mason
San Francisco, CA 94123-0022
PROJECT SPECIFICATIONS
Paint Point Bonita Suspension Bridge
June 7, 2024
TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
01 11 00 .............................................................................................................. Summary of Work 01 27 00 ...................................................................................... Definition of Contract Line Items 01 31 00………… ............................................................... Project Management & Coordination 01 33 23… ......................................................................................................Submittal Procedures 01 36 00… ...................................................................................................... Safety Requirements 01 43 00… ..................................................................................................... Quality Requirements 01 60 00…………………………………………………………...……Material and Equipment 01 74 19… ............................................................ Construction Waste Management and Disposal 01 77 00… ....................................................................................................... Closeout Procedures
DIVISION 03 – 09 – TECHNICAL SPECIFICATIONS
03 91 13………………………………………...……….....Surface Applied Corrosion Inhibitor 03 93 00………………………...…………………...…………………..Concrete Rehabilitation 09 90 00………………………………………………………...……......Paintings and Coatings 09 90 10……………………………………………….…………........Coating of Exterior Metal 09 87 00…...…………………………………………………………. Coating Systems for Steel
SECTION 01 11 00 – SUMMARY OF WORK
PART 1 - GENERAL
1 .1 DESCRIPTION
A. The work of this contract consists of providing all the materials, labor and equipment to paint the Point Bonita Suspension bridge.
B. All work of the contractor shall be performed to safety guidelines promulgated by the
Environmental Protection Agency, Occupational Health and Safety Administration and Cal-OSHA.
C. The contractor will set up containment around the bridge to prevent contamination of soil, water and environment with construction debris.
D. Contractor will be responsible for complete removal of all debris pertaining to the project. Disposal of wastes by the contractor shall be done according to all County/State Regulations at a County/State permitted disposal site. Contractor shall keep projects neat, orderly, and in a safe condition always. Contractor shall store and use all equipment, tools, and materials in a manner that does not present a hazard.
1.2 PLACE OF PERFORMANCE
A. All work will be performed within Golden Gate National Recreation Area. Work will occur within Marin County in California.
B. The Point Bonita Bridge is located adjacent to the Point Bonita Lighthouse, Golden Gate National Recreation Area, Sausalito, California
C. Site Conditions – The Contractor is responsible for verifying quantities and existing site conditions. All interested parties must complete a mandatory site visit to familiarize themselves with local conditions that may affect the cost of contract performance.
Interested parties may coordinate the site visit through the COR or attend scheduled site walk.
D. General Conditions – The Contractor shall be responsible for containment, removal and disposal of any debris from the work areas. All debris from construction site must be self-contained and not have contact with landscape, soil, ocean, or any aquatic surfaces. All disturbed surfaces must be cleaned and restored to their original condition.
E. Post Award Meeting – A post award meeting to discuss and clarify procedures to be followed with the execution of the contract. Installation specs and coordination between contracted work and Park operations must be arranged by the contractor. Contact the COR to schedule an on-site meeting.
1.3 CONTRACTOR’S USE OF PREMISES
A. Construction Camp: Establishment of a camp within the park will not be permitted.
B. Contractor shall at all times conduct his operations to ensure the least inconvenience to the public, staff and occupants, no closures will be permitted without specific approval of Contracting Officer.
C. Confine storage of materials to areas approved by the Contracting Officer’s
Representative.
D. Preservation of Natural and Cultural Features: Confine all operations to work limits of the project. Prevent damage to natural surroundings. Restore damaged areas, repairing or replacing damaged trees and plants, at no additional expense to the Government.
E. Provide temporary barriers to protect existing trees and plants and root zones.
F. Do not remove, injure, or destroy trees or other plants without prior approval.
Consult with Contracting Officer and remove agreed-on roots and branches that interfere with construction.
G. Do not fasten ropes, cables, or guys to existing trees.
H. Hauling Restrictions:
a. Comply with all legal load restrictions in the hauling of materials. Load restrictions on park roads are identical to the state load restrictions with such additional regulations as may be imposed by the Park Superintendent. Information regarding rules and regulations for vehicular traffic on park roads may be obtained from the Office of the Park Superintendent. A special permit will not relieve Contractor of liability for damage that may result from moving of equipment.
1.4 SPECIFIC WORK / TASKS
A. Scaffold the bridge: construct a temperature controlled, climate-controlled, humidity controlled scaffolding system and moveable rig for coating system, paint application and concrete landing repair.
B. Pressure wash metal and wood components
C. Abate corrosion and salt deposit buildup from cables and metal bracing
D. Apply Tnemec “or equal” epoxy-based corrosion protection system (Section 099010), or approved equal, to cables, bracing, and all connection hardware. Perform coating thickness test.
E. Perform discontinuity holiday testing and repair any areas of pinholes, crazing or uneven finish surfaces.
F. Remove all surface mildew, algae, and dirt from wood components of bridge.
G. Light sand, prime and apply (2) coats of paint the wood components of the bridge.
H. Light sand and apply (2) coats of acrylic with grit to the non-slip surface on walkway of the bridge.
I. Conduct paint thickness test.
J. Chip away concrete at area of undermining in Northwest retaining wall. Chip concrete to sound substrate and remove concrete around corroding rebar minimum of 1”.
K. Scour corroded, exposed rebar at Northwest retaining wall with a metal brush, and sandblast rebar down to bare white metal.
L. Apply Sika Armatec 110 anti-corrosion coating system “or equal” to cleaned rebar.
M. Prepare chipped away concrete surface, build formwork and pour Sikacrete 211 SCC plus repair mortar “or equal”, per manufacturer’s instructions.
N. Clean east and west concrete bridge landings per manufacturer’s instructions prior to application of concrete corrosion protection system.
O. Apply (2) coats concrete corrosion protection system, Sika Ferrogard 908 or approved equal, to areas of repair and to East and West concrete landings and to concrete blocks anchoring suspension bridge.
P. Upon substantial completion, submit all reports, and photos documentation.
1.5 SPECIAL CONSTRUCTION REQUIREMENTS
A. The Contractor shall perform all work between the hours of 7:00 AM to 5:00 PM Monday thru Friday. Any variation of this work schedule must be requested in writing and approved in advance by the Contracting Officer.
B. Holiday Work Restrictions: No on-site work shall be performed on weekends or Federal holidays unless approved by the Contracting Officer.
C. The Contractor shall provide a stage 2 “Class 1A / 1C (B1, D1, E1, H2, J1)” containment or similar coating operations that will achieve the requirement of no VOC or particulate emissions, with no reuse of inner material.
D. Contractor shall provide dehumidification and heating as required to maintain each containment at a minimum of 50% RH and 70F with a substate temperature of 65-75F.
E. Surface temperature, wet bulb and dry bulb temperatures shall be monitored at all times with a certifiable device that can calculate dew point and relative humidity.
F. The contractor shall be responsible to maintain environmental conditions as required by the manufacturer for the coating system being applied, by suitable means including dehumidification if necessary.
G. Reference drawings:
a. Attachment 2: Existing Bridge Plans
b. Attachment 3: Photo Attachments
H. Staging area will be adjacent to the East bridge landing; coordinate exact location with
COR.
I. Submit to COR for approval on all materials, parts, shop drawings, products, and appurtenances to complete the tasks as specified in section 4.0 Specific Works/Tasks.
J. Submit painting plan to COR for review before work begins, K. Submit Scaffolding plans to COR for review before work beings.
L. Submit Concrete Repair and formwork plans for review before work begins.
M. Submit safety plan to COR for review before work begins.
N. Submit quality control plan including plan for retention of NACE certified coating agent to be always present on the jobsite during paint and coating system application.
O. Contractor to coordinate with the park and COR when beginning work.
P. Contractor may not use lighthouse/building toilets.
Q. Contractor may use electrical outlets.
R. Contractor may use site water service.
S. Contractor to provide progress reports daily. Photos to be compiled and sent weekly to the COR with captions describing work.
T. Completion Report: Upon project completion, a written completion report of all tasks performed, accompanied by photographs and any shop drawings produced, shall be provided to the COR. Cumulative photos to be saved on USB jump drive, organized by date, and given to Park staff after completion of project. Underexposed, overexposed, and blurry/out-of-focus photos will not be accepted.
U. All submittals as required by the contract shall be submitted and approved by the COR and Contracting Officer before the Notice to Proceed (NTP) is issued by the Contracting Officer (CO).
1.6 FIELD VERIFICATION
A. Field verify all existing dimensions affecting the work of this contract before ordering products. Contractor is responsible for all field verifications.
1.7 PERIOD OF PERFORMANCE
A. The period of performance shall be 305 days after Notice to Proceed (NTP).
B. Contractor shall submit written certification that the project is substantially complete, and final inspection is requested, the Contracting Officer’s Representative will inspect within seven (7) business days of receipt of request.
C. When the COR determines that the work is substantially complete, he will prepare a list of deficiencies to be corrected before final acceptance and a Letter of Substantial Completion will be issued by the CO.
D. Contractor shall coordinate manufacturer warranty inspection. Warranty documents shall be provided to the COR within 30 days of project completion.
1.8 GOVERNMENT-PROVIDED MATERIALS
A. There will be no Government-furnished property for the Contractor’s use.
B. All other materials shall be Contractor-furnished from outside the park.
C. SOILS INVESTIGATION REPORT: NOT USED.
PART 2 PRODUCTS: NOT USED
PART 3 EXECUTION
3.1 List of Contract Line Items
A. Scaffold the bridge: construct a temperature controlled, climate-controlled humidity controlled moveable rig for coating application. Scaffolding construction must access all areas of bridge.
B. Sandblast Metal Bridge Components to bare white metal: Abate corrosion and salt deposit buildup from cables and metal bracing and metal hardware. Remove all surface mildew, algae, and dirt from wood components of bridge.
C. Apply epoxy based coating system to metal bridge components. Apply corrosion protection system (Tnemec “or equal”) to cables, bracing, and connection hardware.
D. Pressure wash wood components of bridge. Rough Sand Wood Exterior and Paint. Apply acrylic primer and paint wood components of bridge. Apply textured surface to walkway.
E. Repair Concrete Landing. Clean and Seal exposed rebar on west approach slab (at retaining wall with and approved protective coating. Repair area of undermining at Northwest retaining wall. Repair Clean and seal Northwest retaining wall and concrete block bridge anchors.
F. Mobilization/Demobilization
a. This item includes mobilizing and demobilizing all required equipment, labor, materials to the site.
G. Progress payments will be based on percentage of the work item that is completed, or as outlined in the approved Schedule of Values
END OF SECTION
SECTION 01 27 00 – DEFINITION OF CONTRACT LINE ITEMS
1.1 SUMMARY
A. Section explains in general, what is and is not included in a contract line item, and limits or cut-off points where one item ends and another begins.
B. If no contract line item exists for a portion of work, include costs in a related item.
PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION
3.1 LIST OF CONTRACT LINE ITEMS (CLIN)
A. Contract Line-Item Number 1: Scaffold the bridge: construct a temperature controlled, climate-controlled humidity controlled moveable rig for coating application. Scaffolding must be able to access all areas of bridge and cover surface area contained within 26,000 cubic feet with stabilized and consistent temperature, humidity control and climate protection (refer to SECTION 09 00 10) Contractor is responsible for verifying all quantities and dimensions, see attachment #2 construction documents for the Pt Bonita Suspension Bridge.
B. Contract Line-Item Number 2: Sandblast Metal Bridge Components to bare white metal: Abate corrosion and salt deposit buildup from cables and metal bracing and metal hardware. Remove all surface mildew, algae, and dirt from wood components of bridge estimated total surface area contained within approximately 17,100 cubic feet. Contractor is responsible for verifying all quantities and dimensions, see attachment #2 construction documents for the Pt Bonita Suspension Bridge. (Refer to SECTION 09 00 10 and SECTION 09 87 00)
C. Contract Line Item Number 3: Apply epoxy based coating system to metal bridge components.
Apply corrosion protection system (Tnemec “or equal”) to cables, bracing, and connection hardware and all metal surfaces of bridge surface area contained within approximately 11,500 cf.
Contractor is responsible for verifying all quantities and dimensions, see attachment #2 construction documents for the Pt Bonita Suspension Bridge. (Refer to SECTION 09 00 10, SECTION 09 87 00)
D. Contract Line-Item Number 4: Pressure wash wood components of bridge. Rough Sand Wood
Exterior and Paint. Apply acrylic primer and paint wood components of bridge and Apply textured surface to walkway, surface area within approximately 7600 cubic feet. Contractor is responsible for verifying all quantities and dimensions, see attachment #2 construction documents for the Pt Bonita Suspension (Refer to SECTION 03 91 13, SECTION 03 93 00)
E. Contract Line-Item Number 5: Repair Concrete Landing. Clean and Seal exposed rebar on west approach slab (at retaining wall with and approved protective coating. Repair area of undermining at Northwest retaining wall. Repair, Clean and seal Northwest retaining wall and concrete block bridge anchors. Area of repair is contained within approximately 1,000 cubic feet on Northwest landing of bridge. Contractor is responsible for verifying all quantities and dimensions, see attachment #2 construction documents for the Pt Bonita Suspension Bridge. (refer to
SECTION 09 90 00)
F. Contract Line-Item Number 6: Mobilization/Demobilization: This item includes mobilizing and demobilizing all required equipment, labor, materials to the site.
END OF SECTION 01 27 00
SECTION 01 31 00 - PROJECT MEETINGS
PART 1 GENERAL
1 .1 PRE-CONSTRUCTION CONFERENCE
A. Before start of construction, Contracting Officer will arrange a Microsoft Teams meeting or phone conference meeting with Contractor. The meeting agenda will include the following as a minimum:
a. Correspondence procedures
b. Designation of responsible personnel
c. Labor standards provisions
d. Payroll reports
e. Changes
f. Payments to Contractor
g. Subcontractors
h. National Park Service regulations
i. Accident prevention program (including name of responsible supervisor)
j. Accident reporting
k. Documents required under the contract
l. Park rules and regulations
m. Recycling Program
n. Saturday, Sunday, holiday and night work
o. Safety program (compliance with the "Accident Prevention" clause of the
General Provisions)
p. Cultural Survey and Natural Resource Compliance requirements for off-site, non- commercial borrow pits (compliance with "Cultural Resources Survey" clause of the General Provisions.
q. Tentative construction schedule
r. Submittal of shop drawings, project data, samples, and approved equals
s. Project closeout requirements
t. Relationship of Division 1 to other divisions
1 .2 PROGRESS MEETINGS
A. The Contracting Officer will schedule weekly meetings with the Contractor and subcontractors.
B. The meeting agenda will include the following as a minimum:
1. Approval of minutes of previous meetings
2. Review of work progress
3. Field observations, problems, and decisions
4. Identification of problems which impede planned progress
5. Review of submittals schedule and status of submittals
6. Review of off-site fabrication and delivery schedules
7. Status of project record drawings (monthly)
8. Status of operation and maintenance data manuals (monthly)
9. Maintenance of progress schedule
10. Corrective measures to regain projected schedules
11. Planned progress during succeeding work period
12. Coordination of projected progress
13. Maintenance of quality and work standards
14. Inform of proposed changes on progress schedule and coordination
15. Other business relating to work
PART 2 PRODUCTS: NOT USED.
PART 3 MEASUREMENT AND PAYMENT
3 .1 PROJECT MEETINGS
A. Payment will be included in the bid item to which this work relates.
SECTION 01 33 23 - SUBMITTALS
1.1 DESCRIPTION
A. The work of this section consists of submittal requirements before and during construction.
1.2 RELATED REQUIREMENTS
A. Project closeout - Section 01770.
1.3 SUBMITTAL AND APPROVAL PROCEDURES
A. All submittals shall be transmitted using National Park Service form CM-16. A copy of the form is included at the end of this section.) No action will be taken on a submittal item unless accompanied by the transmittal form.
B. Forward submittals to Contracting Officer’s Representative at least 5 days before need for approval. Unless a different number is specified, submit one reproducible original and two copies of each shop drawing, three copies of manufacturer’s catalog sheets (cut sheets), three specimens of each sample, and three copies of all other submittals requested.
1. Surface Preparation Plan: for work related operations on bridge.
2. Manufacturers’ Catalog Sheets: Submit only pertinent pages: mark each copy of standard printed data to identify specific products proposed for use.
3. Manufacturer’s Application Instructions: When contract documents require compliance with manufacturer’s printed instructions, provide one complete set of instructions for Contracting Officer and keep another complete set of instructions at the project site until substantial completion.
4. Submit manufacturer’s warranty information.
5. Submit completed daily job reports provided by NPS detailing work accomplished each day, trades present, and the weather.
6. Painting and Coating formulas and vendor information for each color used will also be given to NPS for future reference.
C. Contracting Officer reserves the right to require submittals in addition to those called for in individual sections.
D. Approved Equals:
1. For each item proposed as an “or equal,” submit supporting data demonstrating the product meeting the salient characteristics including:
a. Drawings and samples as appropriate.
b. Comparison of the characteristics of the proposed item with that specified.
c. Changes required in other elements of the work because of the substitution.
d. Name, address, and telephone number of vendor.
e. Manufacturer’s literature regarding application of paints and coatings.
2. A request for approval constitutes a representation that Contractor:
a. Has investigated the proposed item and determined that it is equal or superior in all respects to that specified.
b. Will provide the same warranties for the proposed item as for the item specified.
c. Has determined that the proposed item is compatible with interfacing items.
d. Will coordinate the installation of an approved item and make all changes required in other elements of the work because of the substitution.
e. Waives all claims for additional expenses that may be incurred as a result of the substitution.
3. Construction Materials: The Contractor is encouraged to submit for approval products made out of recycled or environmentally responsible material. Every effort will be made by the National Park Service to approve these materials.
E. Coordinate all submittals and review them for legibility, accuracy, completeness, and compliance with contract requirements. Forward submittals that are related to or affect one another as a package to facilitate coordinated review. Each transmittal shall contain only data specific to that individual submittal.
F. Submittal Identification:
1. Identification shall include the park name-package number, project title, contract number, and transmittal number.
2. All sets of shop drawings, manufacturer’s catalog sheets, samples, and other documents submitted to the Contracting Officer must have the identification information stamped on the submittal.
3. Identification information shall be applied to the bottom right margin on each page. Identification information on samples shall be applied to the most readily visible area on the sample or on tags attached to sample.
G. Submittal Numbering:
1. Number each submittal consecutively.
2. For re-submittals use the original submittal number, plus a letter suffix beginning with A.
3. Additional re-submittals of the same item shall contain the original number with the next consecutive letter.
H. Contracting Officer's Representative’s Review:
1. Submittals will be returned disapproved without technical review if identification information is missing, not filled in, or if placed on the back of the submittal; an incorrect number or format of submittals is provided; the transmittal form is incorrectly filled out;
submittals are not coordinated; or submittals do not show evidence of Contractor’s approval.
2. Any work done or orders for materials or services placed before approval shall be at the Contractor’s own risk.
3. After reviewing submittal. the Contracting Officer’s Representative will return one copy of form CM-16 and one copy of applicable (marked up) submittal sheets to the Contractor. Shop drawing review notations will be returned on the reproducible original shop drawing. All other submitted items will be retained.
The Contractor is responsible for producing additional copies for his/her own use.
4. The returned submittal will be marked in one of three ways as defined below:
a. APPROVED: Acceptable with no corrections.
b. APPROVED WITH NOTATIONS: Minor corrections or clarifications required. All comments are clear and no further review is required. The Contractor shall address all review comments when proceeding with the work.
c. DISAPPROVED - RESUBMIT: Rejected as not in accordance with the contract or as requiring major corrections or clarifications.
The Contracting Officer’s Representative will identify the reasons for disapproval. The Contractor shall revise and resubmit with changes clearly identified.
SECTION 01 36 00 - ACCIDENT PREVENTION
A. The work of this section consists of establishing an effective accident prevention program and providing a safe environment for all personnel and visitors.
1 .2 SUBMITTALS
A. Accident Prevention Program: Before on-site work begins, submit for approval an accident prevention program. The Park Safety Officer will review the proposed program for compliance with OSHA and project requirements. If the program requires any revisions or corrections, the Contractor shall resubmit the program within 10 days. No progress payments will be made until the program is approved. The program shall include:
1. Name of responsible supervisor to carry out the program.
2. Weekly and monthly safety meetings.
3. First aid procedures.
4. Outline of each phase of the work, the hazards associated with each major phase, and the methods proposed to ensure property protection and safety of the public, National Park Service personnel, and Contractor's employees. Identify the work included under each phase by reference to specification section or division numbers.
5. Training, both initial and continuing.
6. Planning for possible emergency situations, such as floods, fires, cave-ins, slides, explosions, power outages, and wind storms. Such planning shall take into consideration the nature of construction, site conditions, and degree of exposure of persons and property.
B. Certificates: Provide certificates from a mechanic that all mechanical equipment has been inspected and meets OSHA requirements.
C. Submit a copy of test reports, as required by OSHA.
D. Submit a report of safety meetings and of inspections.
E. Upon request, submit proof of employees' qualifications to perform assigned duties in a safe manner.
1 .3 QUALITY ASSURANCE
A. Clauses entitled "Accident Prevention" and "Permits and Responsibilities" of the contract.
In case of conflicts between Federal, state, and local safety and health requirements, the most stringent shall apply. Equipment or tools not meeting OSHA requirements will not be allowed on the project sites. Failure to comply with the requirements of this section and related sections may result in suspension of work.
B. Qualifications of Employees:
1. Ensure that employees are physically qualified to perform their assigned duties in a safe manner.
2. Do not allow employees to work whose ability or alertness is impaired because of drugs, fatigue, illness, intoxication, or other conditions that may expose themselves or others to injury.
3. Operators of vehicles, mobile equipment, hoisting equipment, and hazardous plant equipment shall be able to understand signs, signals, and operating instructions, and be capable of operating such equipment. Provide operating instructions for all equipment. Newly hired operators shall be individually tested by an experienced operator or supervisor to determine if they are capable of safely operating equipment.
1 .4 ACCIDENT REPORTING
A. Reportable Accidents: A reportable accident is defined as death, occupational disease, traumatic injury to employees or the public, property damage by accident in excess of $100, and fires. Notify Contracting Officer immediately in the event of a reportable accident. Within 7 days of a reportable accident, fill out and forward to Contracting Officer an Accident/Property Damage Report (Form CM-22). Form may be obtained from the Contracting Officer.
B. All Other Accidents: The Contractor shall report all other accidents to the Contracting
Officer as soon as possible and assist the Contracting Officer and other officials as required in the investigation of the accident.
PART 2 PRODUCTS
2 .1 FIRST AID FACILITIES
A. Provide adequate facilities for the number of employees and the type of construction at the site.
2 .2 PERSONNEL PROTECTIVE EQUIPMENT
A. Meet requirements of NIOSH and MSHA.
PART 3 EXECUTION
3 .1 EMERGENCY INSTRUCTIONS
A. Post telephone numbers and reporting instructions for ambulance, physician, hospital, fire department, and police in conspicuous locations at the work site.
3 .2 EGRESS
A. Provide and maintain adequate egress at all times in accordance with the Life Safety Code (NFPA 101). No corridor, aisle, stairway, door, or exit shall be obstructed or used in a manner that interferes with egress.
3 .3 PROTECTIVE EQUIPMENT
A. Inspect personal protective equipment daily and maintain in a serviceable condition.
Clean, sanitize, and repair, as appropriate, personal items before issuing them to another individual.
B. Inspect and maintain other protective equipment and devices before use and on a periodic basis to ensure safe operation.
3 .4 SAFETY MEETINGS
A. As a minimum, conduct weekly "toolbox" safety meetings. These meetings shall be conducted by a foreman and attended by all construction personnel at the worksite.
B. Conduct monthly safety meetings for all levels. Notify the Contracting Officer of meeting dates and times. These meetings shall be used to review the effectiveness of the Contractor's safety effort, to resolve current health and safety problems, to provide a forum for planning safe construction activities, and for updating the accident prevention program. The Contracting Officer will attend the meeting and enter the results of the meetings into the daily log.
3 .5 HARD HATS AND PROTECTIVE EQUIPMENT AREAS
A. A hard hat area will be designated by the Contracting Officer. The hard hat area shall be posted by the Contractor in a manner satisfactory to the Contracting Officer.
B. If wearing a hardhat is required, it is the Contractor's responsibility to require all those working on or visiting the site to wear hard hats and other necessary protective equipment at all times during the visit. As a minimum, provide six hard hats for use by visitors. Change liners before reissuing hats.
3 .6 TRAINING
A. First Aid: Provide adequate training to ensure prompt and efficient first aid.
B. Hazardous Material: Train and instruct each employee exposed to hazardous material in safe and approved methods of handling and storage. Hazardous materials are defined as explosive, flammable, poisonous, corrosive, oxidizing, irritating, or otherwise harmful substances that could cause death or injury.
PART 4 MEASUREMENT AND PAYMENT
4 .1 ACCIDENT PREVENTION
SECTION 01 43 00 - CONTRACTOR QUALITY CONTROL
A. The work of this section consists of preparing and executing a quality control program during performance of this painting contract.
1 .2 SUBMITTALS
A. Quality Control Plan: At the time of the preconstruction conference, submit for approval a written Contractor Quality Control (CQC) plan. If the plan requires any revisions or corrections, the Contractor shall resubmit the plan within 10 days. The Government reserves the right to require changes in the plan during the contract period as necessary to obtain the quality specified. No change in the approved plan may be made without written concurrence by the Contracting Officer. The plan shall include:
1. A list of personnel responsible for quality control and assigned duties.
i nclude each person's qualifications.
2. A copy of a letter of direction to the Contractor's quality control supervisor outlining assigned duties.
3. Names and descriptions of laboratories to perform sampling and testing, and samples of proposed report forms.
4. Methods of monitoring and controlling environmental pollution and contamination as required by regulations and laws.
5. Methods of performing, documenting, and enforcing quality control of all work.
B. Daily Submittals: Submit Daily Quality Control Report showing all inspections and tests on the first workday following the date covered by the report. Reference Attachment:
Contractors Q.C. Daily Report.
C. Tests: Submit triplicate copies of complete test results not later than three calendar days after the test was performed. Submit failing test results and proposed remedial actions within four hours of noted deficiency. Reference Attachment: Test Report Information Sheet
D. Off Site Inspection Reports: Submit prior to shipment.
E. Progress Payments: If the CQC plan and Daily Quality Control Reports are not submitted in a timely manner, the Contracting Officer may retain an appropriate amount of the applicable progress payment.
1 .3 QUALITY ASSURANCE
A. General: Except for tests or other items of work specified to be performed by the
Government, the quality of all work shall be the responsibility of the Contractor. Inspect and test all work often enough to ensure that the quality of materials, workmanship, construction, finish, and functional performance is in compliance with applicable specifications and drawings.
B. Quality Control Staff: The Contractor's job supervisory staff may be used for quality control, supplemented as necessary by additional technicians. The Contractor's designated Quality Control Supervisor shall be employed full time at the project site whenever contract work is in progress.
PART 2 - PRODUCTS (NOT USED)
PART 3 - EXECUTION
3 .1 OFF-SITE CONTROL
A. Items that are fabricated or assembled off-site shall be inspected for quality control at the place of fabrication.
3 .2 ON-SITE CONTROL
A. Notify the Contracting Officer at least 24 hours in advance of the initial and follow-up phases.
B. Preparatory: Perform before beginning each feature of work.
1. Review control submittal requirements with personnel directly responsible for the quality control work.
2. Ensure that provisions have been made for field control testing.
3. Examine the work area to ensure that all preliminary work has been completed.
4. Verify all field dimensions and advise the Contracting Officer of discrepancies.
5. Ensure that necessary equipment and materials are at the project site and that they comply with approved shop drawings and submittals.
C. Initial: As soon as work begins, inspect and test a representative portion of a particular feature of work for quality of workmanship. Review control testing procedures to ensure compliance with contract requirements.
D. Follow-Up: Inspect and test as work progresses to ensure compliance with contract requirements until completion of work.
3 .3 DOCUMENTATION
A. Maintain Daily Quality Control Reports (sample attached) of quality control activities and tests. Daily Quality Control Reports may not be substituted for other written reports required under the General Provisions, such as Disputes, Differing Site Conditions, or Changes.
3 .4 ENFORCEMENT
A. The Contractor shall stop work on any item or feature pending satisfactory correction of any deficiency noted by the quality control staff or the Contracting Officer. Construction shall not proceed on any feature of work containing uncorrected work.
PART 4 - MEASUREMENT AND PAYMENT
4 .1 CONTRACTOR QUALITY CONTROL
SECTION 01 60 00 - MATERIAL AND EQUIPMENT
A. The work of this section consists of the general procedures for handling, storing, and protecting material and equipment.
1 .2 TRANSPORTATION AND HANDLING
A. Arrange deliveries of materials in accordance with construction schedules; coordinate to avoid conflict with work and conditions at the site. Deliver materials in undamaged condition, in manufacturer's original containers or packaging, with identifying labels intact and legible. Contractor is encouraged to obtain materials in biodegradable or recyclable/reusable packaging which uses the minimum amount of packaging possible.
1 .3 STORAGE AND PROTECTION
A. Store materials in accordance with manufacturer's instructions, with seals and labels accessible for inspection.
B. Interior Storage: Maintain temperature and humidity within the ranges required by manufacturer's instructions.
C. Exterior Storage:
1. Store products subject to damage by the elements in weathertight enclosures.
2. Store fabricated products above the ground, on blocking or skids; prevent soiling or staining. Cover products subject to damage or deterioration with impervious sheet coverings; provide adequate ventilation to avoid condensation.
PART 2 MEASUREMENT AND PAYMENT
2 .1 MATERIAL AND EQUIPMENT
SECTION 01 77 00 - PROJECT CLOSEOUT
PART 1 GENERAL
A. The work of this section consists of final cleanup, closeout submittals, and final inspection procedures.
PART 2 - PRODUCTS
2 .1 CLEANING MATERIALS
A. As recommended by the manufacturer of the surface to be cleaned.
3 .1 CLEANING
A. Before scheduling the final inspection, remove all tools, equipment, surplus materials, and rubbish. Restore or refinish surfaces that are damaged due to work of this contract to original condition. Remove grease, dirt, stains, foreign materials, and labels from finished surfaces. Thoroughly clean building interiors. Pick up all construction debris from the site. At time of final inspection, project shall be thoroughly clean and ready for use.
3 .2 CLOSEOUT SUBMITTALS
A. Submit before final inspection request.
1. Guarantees and Bonds: As specified in individual sections.
2. Spare Parts and Materials: As specified in individual sections.
3. All product submittals are provided and accepted.
3 .3 SUBSTANTIAL COMPLETION AND FINAL INSPECTION
A. When project, or designated portion of project, is substantially complete, request in writing a final inspection. Upon receipt of written request that project is substantially complete, the Contracting Officer will proceed with inspection within 10 days of receipt of request or will advise the Contractor of items that prevent the project from being designated as substantially complete.
B. If, following final inspection, the work is determined to be substantially complete, Contracting Officer will prepare a list of deficiencies to be corrected before final acceptance and issue a Letter of Substantial Completion. Contractor shall complete the work described on the list of deficiencies within 30 calendar days, as weather permits.
If the Contractor fails to complete the work within this time frame, the Contracting Officer may either replace or correct the work with an appropriate reduction in the contract price or charge for re-inspection costs in accordance with the Inspection of Construction clause of the contract. If, following final inspection, the work is not determined to be substantially completed, Contracting Officer will notify Contractor in writing. After completing work, Contractor shall request a new final inspection. All re-inspection costs may be charged against the Contractor in accordance with the Inspection of Construction clause of the contract.
3 .4 FINAL ACCEPTANCE OF THE WORK
A. After all deficiencies have been corrected, a Letter of Final Acceptance will be issued.
PART 4 - MEASUREMENT AND PAYMENT
4 .1 PROJECT CLOSEOUT
SECTION 03 91 13 - SURFACE APPLIED CORROSION INHIBITOR (SACI)
PART 1 – GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and
Supplementary Conditions and Division 01 Specification Sections, apply to this Section.
1.2 SUMMARY
A. Provide a SACI on concrete and other acceptable substrates in order to reduce the effects of corrosion.
1. Work includes substrate preparation including crack and joint treatment.
1.3 PERFORMANCE REQUIREMENTS
A. The SACI is intended to mitigate active corrosion, and/or delay the onset of corrosion
1. System shall perform as a corrosion inhibitor.
2. Manufacturer shall provide all SACI materials that are physically and chemically compatible when installed in accordance with manufacturer’s current application requirements.
1.4 SUBMITTALS
A. Submittals: Comply with project requirements for submittals as specified in Division 01.
B. Product Data:
1. Materials list of items proposed to be provided under this Section.
2. Manufacturer's specifications and other data needed to prove compliance with the specified requirements.
C. Site mockup: For confirmation of performance, construction sequencing and standard of acceptance. Complete prior to commencing with the project.
D. Pre-Construction Field Adhesion Testing: Written results of field tests, including summary of joint preparation, surface preparation, products used and installation techniques.
1.5 QUALITY ASSURANCE
A. Installer Qualifications:
1. Installer shall have experience in installing materials of types specified and shall have successfully completed at least three projects of similar scope and complexity.
2. Installer shall designate a single individual as project foreman who shall be on site at all times during installation.
B. Applicable Regulations: Comply with local code and requirements of authorities having jurisdiction. Do not exceed VOC regulations as established by the State in which they are being installed; including total VOC content, in grams per liter, for all system components (i.e. primers, adhesives, coatings, and similar items.)
1.6 PRE-INSTALLATION CONFERENCE
A. Prior to scheduled commencement of the SACI installation and associated work, conduct a meeting at the project site with the installer, COR, manufacturer’s representative and any other persons directly involved with the performance of the Work. The Installer shall record conference discussions and include decisions and agreements reached (or disagreements), and furnish copies of recorded discussions to each attending party. The main purpose of this meeting is to review foreseeable methods and procedures related to the Work.
1.7 DELIVERY, STORAGE AND HANDLING
A. SACI materials must be delivered in original, unopened containers with the manufacturer's name, labels, product identification, and batch numbers. Damaged material must be removed from the site immediately.
B. Store SACI materials off the ground and protect from rain, freezing or excessive heat until ready for use.
C. Condition the specified product as recommended by the manufacturer.
1.8 PROJECT CONDITIONS
A. Environmental Conditions: Do not apply material if it is raining or snowing or if such conditions appear to be imminent. Minimum application temperature is 45 degrees F (5 degrees C) and rising.
B. Protection: Precautions should be taken to avoid damage to any surfaces near the work zone due to mixing and handling of the specified material.
1.9 WARRANTY
A. Warranty: Provide manufacturer’s standard warranty for each type of product.
Warranty shall include manufacturer’s statement that materials in contact with another have been tested and verified to be compatible. Include written testing documentation and test reports if requested by COR.
PART 2 - PRODUCTS
2.1 MANUFACTURER
A. Basis-of-Design Manufacturer: Sika Corporation, 201 Polito Avenue, Lyndhurst NJ
07071. Toll Free 800-933-SIKA (7452), www.sikausa.com. (“or equal”)
B. SACI: Sika FerroGard 908 (“or equal”) penetrating corrosion inhibitor for hardened http://www.sikausa.com/ concrete with the following properties:
C. Dual-Functional, SACI: Sika FerroGard 908 (“or equal”) Dual-functional, SACI and penetrating sealer for reinforced concrete with the following properties:
1. Sealer Type: Alkylalkoxy silane.
2. Active ingredient content: 99%
3. Color: Clear
4. VOC: 327 g/l
5. Flashpoint: 104 degrees F (40 degrees C)
6. Chloride penetration (NCHRP 244) applied @ 125 sf/gallon: Series II –
Absorbed chloride 88%, Series IV – Absorbed chloride 99%
7. Application temperature (ambient and substrate): 40°-95°F (5°to 35°C).
8. Pot life: Indefinite.
9. Corrosion reduction (ASTM G 109 modifed) with 2.5 years of data, application applied before cracking and before corrosion vs a control: 92% corrosion reduction.
10. Corrosion reduction (ASTM G 109 modifed) with 2.5 years of data, application applied after cracking and before corrosion vs a control: 95% corrosion reduction.
11. Corrosion reduction (ASTM G 109 modifed) with 2.5 years of data, application applied after cracking and after corrosion vs a control: 85% corrosion reduction.
12. Reduction in water absorption vs control: greater than 75% reduction.
D. Concrete Repair and Patching Materials: As recommended by manufacturer of SACI (Surface applied corrosion inhibitor), surface applied corrosion inhibitor.
E. Elastomeric Sealants: As recommended by manufacturer of SACI. For exterior joints in vertical surfaces such as, but not limited to control and/or expansion joints in cast-in-place concrete or unit masonry, joints between architectural pre-cast concrete units, joints between dissimilar materials or perimeter joints at frames of doors, windows, storefronts, louvers and similar openings apply a low-modulus, single-component or multi-component non-sag sealant in compliance with ASTM C920, Type S or M, Grade NS, Class 25, Class 35, Class +50/-50, Class +100/-50. Acceptable products:
1. Sikaflex 1a “or equal”, a premium-grade, high-performance, moisture-cured, 1-component, polyurethane-based, non-sag elastomeric sealant.
2. Sikaflex 2c “or equal” , a 2-component, premium-grade, polyurethane-based chemical cure, elastomeric sealant.
3. Sikaflex 15 “or equal” lm a low-modulus, high-performance, 1-component, polyurethane-based, non-sag elastomeric sealant.
3.1 EXAMINATION
A. Verify that surfaces and conditions are ready to accept the Work of this section. Verify surfaces are clean, dry, sound and free of voids, deformations, protrusions and contaminants that may inhibit application or performance of the elastomeric coatings
Notify COR in writing of any discrepancies. Commencement of the Work in an area shall mean Installer’s acceptance of the substrate.
3.2 PREPARATION
A. Verify that the surfaces are clean and open texture.
B. Substrates must be clean, sound, dry, and absorbent free of surface contaminants or other contaminants deleterious to the penetration of the SACI. Remove dust, laitance, and grease, oils, curing compounds, form release agents existing coatings and all foreign particles by mechanical means. Substrate shall be in accordance with ICRI Guideline No. 03732 for sealers and fall within CSP1 to CSP3.
3.3 APPLICATION OF CONCRETE REPAIR AND PATCHING MATERIALS
A. Fill all visible hairline cracks and surface defects with appropriate Sika repair mortar
“or qual”, leveling mortar or surface filler prior to applying coating primer. Bugholes or irregularities of substrate shall be leveled with specified leveling mortar or surface fillers as appropriate.
3.4 CRACK TREATMENT FOR CONCRETE
A. For non-structural cracks, 12 mils or less apply the SACI in accordance with the
Product Data Sheet.
B. For non-structural cracks greater than 12 mils rout and seal the crack to a 1/4 inch by 1/4 inch profile and properly seal with a flexible, specified elastomeric joint sealant.
C. For structural static cracks, inject with a suitable epoxy.
3.5 APPLICATION OF SACI
A. The SACI is delivered ready to be used. No mixing is required and do not dilute on site.
B. Coverage is entirely dependent on the porosity of the substrate. Normally the consumption is achieved with 2 coats. Extremely porous substrates may only require 1 coat, very dense substrates may require 3 coats. To ensure proper penetration, a field mock up is required.
C. Placement Procedure: The SACI shall be applied liberally and allowed to soak into the substrate. This shall be accomplished by the use of brushes, rollers, low pressure gun or airless spray equipment.
D. On vertical surfaces, apply the product from the top down in successive passes until the targeted consumption for the first coat is achieved.
F. Successive passes are done when the concrete surface still has a matt appearance from the product, but is no longer wet (e.g. when placing the bare hand on the surface and removing it, no wetness on the hand is observed). The concrete surface is assumed to be saturated with the SACI when it remains “wet” in appearance for at least 5 seconds.
G. The following coat can then be applied when the concrete is completely dry.
H. On horizontal surfaces, saturate the substrate by continuous spray (airless or low pressure gun) or flooding technique and allow to have “wet” look for at least 5 seconds.
I. On soffit areas, apply the material with a continuous spray and saturate the substrate until surface keeps its “wet” look for at least 5 seconds.
J. Adhere to all limitations and cautions for the SACI product as stated in the manufacturers printed literature.
K. Do not apply the SACI in case of imminent rain (within the next few hours), strong wind exceeding 30 mph or in strong direct sun light.
3.6 APPLICATION OF SEALANTS
A. Provide the approved sealant system where shown on the Drawings, and in strict accord with the manufacturer's recommendations as approved by the COR.
B. Install sealants immediately after joint preparation. Mix and apply multi-component sealants in accord with manufacturer's printed instructions.
C. Install sealants to fill joints completely from the back, without voids or entrapped air, using proven techniques, proper nozzles and sufficient force that result in sealants directly contacting and fully wetting joint surfaces.
D. Install sealants to uniform cross-sectional shapes with depths relative to joint widths that allow optimum sealant movement capability as recommended by sealant manufacturer.
E. Tool sealants in manner that forces sealant against back of joint, ensures firm, full contact at joint interfaces and leaves a finish that is smooth, uniform and free of ridges, wrinkles, sags, air pockets and embedded impurities.
F. Remove sealant from adjacent surfaces in accord with sealant and substrate manufacturer recommendations as work progresses.
G. Protect joint sealants from contact with contaminating substances and from damages.
Cut out, remove and replace contaminated or damaged sealants, immediately, so that they are without contamination or damage at time of substantial completion.
3.7 FIELD QUALITY CONTROL
A. Notify COR when sections of work are complete to allow review prior to covering completed Work.
B. Cooperate with Owner’s inspection agency as applicable, who will observe substrate and coating installation and provide written documentation of observations.
3.8 CLEANING
A. Remove uncured materials from tools or other surfaces with an approved solvent.
B. Leave finished work and work area in a neat, clean condition without evidence of spillovers onto adjacent areas.
3.9 PROTECTION
A. Cap and protect exposed back-up walls against moisture and wet weather conditions during and after application of membrane. Protect Work against wet weather conditions for a minimum of 24 hours.
SECTION 039300 - CONCRETE
REHABILITATION
1.1 SUMMARY
A. This specification describes the patching or overlay of…
This is the start of the file's text. The full file is on GovTribe.