Attachment_6_Revised_Performacne_Work_Statement_0002.pdf

PDF 183 KB Posted

Attached to
Replace Lighthouse Well Pump, Point Reyes N. S. Federal contract opportunity
Solicitation number
140P8325Q0014
Issued by
Department of the Interior National Park Service Pacific West Region

About this file

This document is a Revised Performance Work Statement (PWS) for Request for Quote (RFQ) no. 140P8425Q0014, issued by the National Park Service (NPS) for replacing a well pump at the Lighthouse Well in Point Reyes National Seashore. The primary tasks include removing the existing pump from a 422-foot deep well at specific coordinates, installing a new Goulds 5G S20 (or equivalent) 2 horsepower pump, installing 2-inch Schedule 80 PVC drop pipe, and completing electrical wiring and controls. Additional requirements include sterilizing the well with chlorine after installation, submitting specification sheets for COR approval, and providing manufacturer warranties.

The project has an anticipated performance period from 10/06/2025 to 12/18/2025. The contractor is responsible for conforming to Marin County Environmental Health Services Department regulations, properly disposing of waste materials, and minimizing environmental impact by limiting construction activity to a small work area. The contractor must coordinate staging areas with the Contracting Officer's Representative (COR) and adhere to local, state, and federal regulations throughout the project.

View the file

Other files for this federal contract opportunity

Other files attached to Replace Lighthouse Well Pump, Point Reyes N. S., newest first.
File Type Posted
Sol_140P8325Q0014_Amd_0002.pdf PDF
Attachment_7_Q_and_A_0002.pdf PDF
Sol_140P8325Q0014_Amd_0001.pdf PDF
Attachment__1_Terms_Provisions_Clauses.pdf PDF
Attachment_3_Performacne_Work_Statement.pdf PDF
Sol_140P8325Q0014.pdf PDF
Attachment_4_Forms_and_Provisions_to_Return_with_Quote.docx DOCX document
Attachment_5_Optional_Past_Performance_Questionnaire.docx DOCX document
Attachment_2_DOL_Service_Wage_Rates_2015-5725.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Solicitation (RFQ) no. 140P8425Q0014, Attachment 6 – REVISED Performance Work Statement (9/9/25)

Replace Pump at Lighthouse Well, Point Reyes National Seashore (PORE)

General Information:

The Contractor shall furnish all materials, equipment, and personnel necessary to manage and accomplish the work.

This is a Performance Work Statement, meaning the NPS has provided a list of key tasks below, but that list may not cover all that’s required for the contractor to do a full well pump replacement. NPS is relying on Contractor’s expertise and experience to prepare a firm-fixed priced quote for complete replacement of the well pump.

Point Reyes National Seashore site map is available here:

https://www.nps.gov/pore/planyourvisit/directions.htm

A. Description of Primary Tasks/Work:

1. Remove and dispose of the existing pump located in the Lighthouse well in Point

Reyes National Seashore at coordinates 38.04685 degrees North, 122.98837 degrees

West. The well is about 422 feet deep, and the existing pump is suspended at 315 feet.

2. Furnish and install a new well pump, Goulds 5G S20 or equivalent, but must be 2 horsepower, 230 volts, single phase.

3. Furnish and install a 2-inch dimeter drop pipe, Schedule 80 PVC or better.

4. Furnish and install electrical wiring and controls needed to operate the pump.

5. After installation the well is to be sterilized with chlorine and sealed.

6. Submit specification sheets for products and materials to be installed to the

Contracting Officer’s Representative (COR) for COR’s review and approval prior to contractor installing them.

7. Furnish the well pump manufacturer’s warranty to the COR along with any other materials’ warranties.

B. Contractor will also be responsible for the following:

1. The Contractor is responsible for completing work that conforms to the County of

Marin Environmental Health Services Department regulations.

2. Removing all waste materials, adhering to Local, State, and Federal regulations.

C. Environmental protection:

To minimize environmental impact, construction activity shall be limited to a small allowable work area in order to protect as much as possible the natural environment around where the pump is located. Coordinate staging areas for equipment and work zones with COR prior to start of work.

Solicitation (RFQ) no. 140P8425Q0014, Attachment 6 – REVISED Performance Work Statement (9/9/25)

Replace Pump at Lighthouse Well, Point Reyes National Seashore (PORE)

D. Period of Performance:

Government’s anticipated period of performance is from 10/06/2025 – 12/18/2025.