This is a Scope of Work (SOW) document for the National Park Service detailing boardwalk rehabilitation and replacement at Fort Frederica National Monument.
The project requires the contractor to demolish the existing wood boardwalk and construct a new boardwalk with improved life-safety features compliant with current International Building Code requirements. The work includes four primary construction components: (1) Elevated boardwalk footings and post anchorage using reinforced precast concrete footings with 4,000 psi minimum strength and cast-in-place J-bolt anchors; (2) Ground contact boardwalk construction using nominal 4x4 preservative-treated posts spaced at 8 feet on center, embedded in concrete with double 2x6 beams and 2x8 joists at 16 inches on center; (3) Elevated boardwalk construction with double 2x8 beams, minimum 6x6 posts spaced at 4 feet on center (interior) and 8 feet on center (perimeter), connected with Type 316 stainless steel through-bolts; and (4) Decking and guardrails consisting of 5/4 x 6 preservative-treated lumber decking and a two-rail guardrail system 42 inches high. All lumber in ground contact or embedded in concrete must be preservative-treated for ground contact, with corrosion-resistant fasteners throughout.
The contractor must provide material submittals for Government review prior to installation, a site-specific safety plan addressing site control and worker/visitor safety, Activity Hazard Analyses for demolition and structural work, and a one-year workmanship warranty. Resource protection requirements include limiting ground disturbance to the existing boardwalk footprint and approved Area of Potential Effect extending 10 feet beyond the perimeter, restricting new borings to 12 inches diameter with NPS archeological monitoring, and restoring all disturbed areas to pre-construction condition. The contract uses a lump-sum pricing structure with nine contract line items covering demolition, concrete placement, structural framing, decking, guardrails, general conditions, profit, and overhead, plus an option for installing two waysides interpretive panels at the elevated section.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
FORT FREDERICA NATIONAL MONUMENT
BOARDWALK REHABILITATION AND REPLACEMENT
Scope of Work (SOW)
National Park Service (NPS)
1. Project Background and Justification
Fort Frederica National Monument proposes replacement of the existing wood boardwalk to address deterioration, improve visitor safety, and maintain an accessible route over the dry moat at the historic townsite boundary.
Replacement provides the NPS an opportunity to improve life-safety features and construction practices consistent with current International Building Code requirements, including loading capacity and guardrail height, while maintaining the boardwalk's existing function and alignment.
2. Scope
The Contractor shall provide all labor, materials, equipment, and transportation necessary to demolish and remove the existing wood boardwalk and construct a new wood boardwalk in its place, including concrete supports, structural framing, decking, and guardrails. Work includes maintaining a continuous accessible route, protecting adjacent resources, and restoring disturbed areas.
3. Tasks
3.1 Demolition
1. Contractor shall demolish and remove the existing boardwalk in its entirety, including decking, framing, posts, guardrails, concrete encasements, and associated components.
2. Demolition shall be controlled to prevent damage to the dry moat and surrounding landscape.
3. Existing post voids shall remain available for reuse where practicable to limit new ground disturbance.
4. Contractor shall maintain site control and visitor and worker safety throughout demolition.
3.2 Elevated Boardwalk Footings and Post Anchorage
1. Elevated boardwalk vertical supports shall bear on reinforced precast concrete footings. Footings shall be manufactured off site using minimum 4,000 psi concrete and reinforced with welded wire mesh (WWM).
2. Precast footings shall include threaded J-bolt anchors cast into the concrete during the precasting process.
J-bolts shall be positioned and wet set to receive the specified pre-manufactured post bases.
3. Post bases shall be compatible with the cast-in-place J-bolt anchors and sized for the specified vertical support.
4. Post bases and anchors shall be centered and aligned on the footing to provide proper load transfer.
3.3 Ground Contact Boardwalk Construction
1. Ground-contact boardwalk segments shall use nominal 4x4 preservative-treated posts spaced at no more than 8 feet on center and fully embedded in concrete to provide lateral support and prevent movement.
2. Existing post voids shall be reused where practicable. Voids may be widened as necessary, not to exceed 12 inches in diameter, to allow concrete embedment.
3. Each post line shall support two (2) nominal 2x6 beams spanning the 8-foot boardwalk width. Beams shall remain in ground contact and shall be attached to each post with two (2) through-bolts.
4. Joists shall be nominal 2x8 lumber, bear a minimum of 1-1/2 inches on the 2x6 beams, and be spaced at no more than 16 inches on center. Joists shall be laid out from both sides with the odd space located at the center of the boardwalk.
5. Provide joist blocking at beam bearing locations.
3.4 Elevated Boardwalk Construction
1. Supporting beams shall consist of double nominal 2x8 preservative-treated members.
2. Interior bearing posts shall be spaced at no more than 4 feet on center. Perimeter posts shall be spaced at no more than 8 feet on center. Posts supporting beams shall be minimum nominal 6x6 preservative-treated lumber.
3. Posts shall be notched 7-1/4 inches high by 3 inches deep to provide full bearing for double 2x8 beams.
4. Beam-to-post connections shall use not less than two (2) 1/2-inch diameter Type 316 stainless steel through-bolts with Type 316 stainless steel washers and nuts at each connection.
5. Provide blocking joist blocking at all bearing beam locations. .
3.5 Decking
1. Decking shall be nominal 5/4 x 6 preservative-treated lumber installed perpendicular to the joists with a 3- 1/2-inch overhang at each side of the boardwalk.
2. Deck boards shall be fastened with two (2) 3-inch coated deck screws at each joist and installed to provide a smooth, continuous accessible walking surface.
3.6 Guardrail
1. Contractor shall install a two-rail guardrail along the full length of the boardwalk. Guardrail height shall be 42 inches above the finished walking surface.
2. Guardrail posts shall be nominal 4x4 at ground-contact segments and nominal 6x6 at elevated segments.
3. The upper rail shall be nominal 2x4 lumber installed flush with the top of the posts. The lower rail shall be nominal 2x4 lumber installed 14-1/2 inches below the upper rail.
4. Top caps shall be nominal 2x6 lumber. Top caps connecting 6x6 posts shall be nominal 2x lumber ripped to
8 inches wide.
5. Guardrail components shall be securely fastened to provide a rigid assembly.
6. Contractor shall mount 2 waysides at the elevated section of boardwalk. Location to be determined on site.
See Appendix B for mounting details.
4.0 Requirements
1. Lumber on or in contact with soil, or embedded in concrete, shall be preservative-treated and rated for ground contact. All other lumber shall be preservative treated for exterior use.
2. Through-bolts, washers, and nuts shall be Type 316 stainless steel. Other fasteners, connectors, and hardware shall be corrosion-resistant and compatible with preservative-treated lumber.
3. All cuts, notches, and field modifications to treated lumber shall be field-treated with a compatible preservative.
4. Contractor shall verify dimensions, layout, and field conditions before construction. Bid Sketches in Appendix A communicate the Government's minimum design intent and are not construction drawings.
5. Work shall follow best practices for construction in a historic site and shall minimize unnecessary ground disturbance.
6. Contractor shall maintain site control and visitor and worker safety throughout the Work.
5.0 Deliverables
1. Material submittals for lumber, concrete, fasteners, connectors, post bases, anchors, and other major components shall be provided for Government review prior to installation.
2. Contractor shall provide a site-specific safety plan addressing site control, visitor safety, worker safety, demolition, excavation, concrete placement, structural framing, material handling, and use of wheeled or mechanized equipment.
3. Activity Hazard Analyses (AHAs) shall be provided for demolition, excavation and concrete placement, structural framing, and use of wheeled or mechanized equipment.
4. Contractor shall provide a one (1) year workmanship warranty beginning at final Government acceptance.
6.0 Resource Protection
6.1 Cultural Resources
1. The boardwalk is a non-historic structure located within a culturally significant maintained landscape. Its alignment conveys the location of the original entry bridge into the townsite and shall be preserved.
2. Construction access, staging, and material storage shall be confined to previously disturbed areas and areas immediately adjacent to the boardwalk to the maximum extent practicable.
3. Ground disturbance shall remain within the existing boardwalk footprint and the approved Area of Potential Effect, extending 10 feet outside the existing boardwalk perimeter.
4. New borings shall be limited to those required for structural support and shall not exceed 12 inches in diameter. Up to 20 additional 12-inch diameter borings may be required.
5. NPS will provide archeological monitoring. Contractor shall notify the COR at least 72 hours before performing new borings.
6. If cultural materials, archeological resources, or human remains are encountered, Contractor shall stop work in the immediate area and notify the Contracting Officer. Work shall resume only when directed.
7. All wheeled equipment operated within the historic townsite during performance of the Work shall be equipped with turf tires.
6.2 Natural Resources
1. Disturbed turf or ground surfaces shall be restored to pre-construction condition, including grading to existing contours, seeding, and stabilization until vegetation is established.
2. Contractor shall not disturb, harass, or otherwise interfere with wildlife and shall avoid impacts to wildlife habitat.
3. Contractor shall stage, contain, and remove all demolition and construction debris from the site. All debris shall become the property of the Contractor and shall be disposed of outside of the Park boundary in accordance with Local, State, and Federal regulations.
APPENDIX A - BID SKETCHES
The following sketches are provided to communicate the Government's minimum design intent. They are not construction drawings. Contractor shall verify all dimensions and field conditions prior to construction.
Appendix A-1 - Ground Contact Walkway Detail
Appendix A-2 - Ground Contact Section
Appendix A-3 - Elevated Boardwalk Section
APPENDIX B
31°13'25.02"N 81°23'24.22"W rsdaniels Polygon rsdaniels Line
1 1 Each
2 1 Each
3 1 Each
4 1 Each
5 1 Each 6 2 Each 7 1 Each 8 1 Each 9 1 Each
10 1 Each
10 1 Each
TOTAL PRICE FOR ALL OPTIONS BASE PRICE (Contract Line Item Number 9)-----------
TOTAL BASE PRICE (Contract Line Item Number 1 through 7-----------------------------
Option 1: N/A
Total Price
Demolition of Existing Boardwalk
Concrete Footing Placement
Decking
Structural Framing
Guardrail
General Conditions Profit Overhead
Install Waysides
Contract Price Schedule National Park Service (NPS)
Solicitation : TBD Park: FOFR
PMIS Number: 327467 Developed Area:
Project Title: FOFR Moat Boardwalk Notice: Offerors are required to submit, a minimum, an offer that conforms to the solicitation documents with pricing for Base line items and all option line items. Failure to do so may render the proposal unacceptable. On lump-sum line items, provide the total price only. For all unit-priced line items, provide the unit price and the extended total price. If no specific line item exists for a portion of the work, include the costs in a related item. In case of error in calculation of extended prices, the unit price governs. In case of error in summation, the total of the corrected amounts govern. Round totals and extended prices to whole dollars.
Contract Line Item Number
(CLIN)
Unit of Measure
Contract Line Item (CLI) Title Quantity Unit Price