This is a Questions and Answers document for GOGA 319407 Amendment 1, addressing bidder inquiries regarding proposal submission requirements and solicitation clarifications.

The document clarifies four key submission requirements: bidders must use the updated contract price schedule titled "GOGA319407_ContractPriceSchedule_20260816" uploaded with Amendment 1, which contains three options rather than the four options listed in the original RFP Section B; electronic funds transfer information must be submitted with the initial offer as instructed in Section 52.232-38, not withheld until contract award; resumes are required for four key personnel positions—Site Superintendent, Safety Manager, Traffic Control Manager, and Quality Control Manager—reconciling the conflicting requirements stated in Sections L and M; and bids are due September 14, 2026 at 2:00 PM Mountain Daylight Time (MDT), with the SF 1442 form defaulting to "local" time. The document additionally indicates that a virtual pre-bid site visit is planned with date and time details to be provided in Amendment 2.

View the file

Other files

Show all 20

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

GOGA 319407 – Amendment 1 Questions and Answers

Should we use the Section B price schedule in the RFP or the Price Schedule Excel form?

The one in the RFP has 4 options. The Excel one has only 3 options.

Utilize the updated contract price schedule titled “GOGA319407_ContractPriceSchedule_20260816” that is uploaded with Amendment 1 for your proposal submission.

Although Section 52.232-38 says to submit electronic funds transfer information with the o er, should we hold o on that and only submit if we are awarded the contract? That's what we've been advised to do on at least one previous bid.

Please submit as instructed in the solicitation.

Section L says to provide resumes for the Site Superintendent, Safety Manager, and Quality Control Manager. But Section M says to provide them for the Site Superintendent, Tra ic Control Manager, and Quality Control Manager. Which is correct?

Site Superintendent, Safety Manager, Tra ic Control Manager, and Quality Control Manager are the key personnel that resumes are required for this solicitation.

When will the virtual pre-bid/site visit be? We'll need to know the date and time before we can RSVP our attendee(s).

A virtual pre-bid site visit is planned with a date and time still to be determined.

Amendment 2 will be sent out with that information.

Please confirm whether bids are due on 9/14/26 at 2 pm Pacific Daylight Time or Mountain Daylight Time. The SF1442 just says "local" time. The sam.gov page says Mountain time.

Mountain Daylight Time (MDT). The SF 1442 says local time by default and can't be changed.

File details come from the government source that posted it. Updated .