This document is a Request for Information (RFI) with 12 technical clarification requests for a seawall and landscaping project, likely for a federal or municipal construction project. The RFIs cover various technical details including bid date postponement (extended to January 15, 2026), landscaping and irrigation work breakdown across multiple Contract Line-Item Numbers (CLINs), concrete strength specifications, seawall repair details, utility force main installation, and environmental considerations like oyster clump relocation. Key technical clarifications include confirmation that concrete strengths vary by sheet, instructions for handling a short coquina wall during utility installation, guidance on demolishing existing seawall sections, and maintaining existing environmental documentation for oyster relocation. The project appears to involve complex marine construction with multiple site-specific engineering and environmental challenges that required detailed clarification from the project team.
View the file
Other files
Show all 27
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
RFI #001 – Request for Structural Plan Information
Response: RFI #001 was answered in Amendment #02.
RFI #002 – Bid Date Postponement
Due to the Bid date of 01/08/2026 falling immediately after the upcoming Holiday (Christmas/New Years) breaks where most companies will not be working, can we expect the Bid Due Date to be pushed back to allow more time for bidders to submit their bid?
Response: The Bid Due Date will be extended to January 15, 2026.
RFI #003 – Clarification for Landscaping & Irrigation Work on Base Bid vs Alternatives
Can you provide more clarification on which Contract Line-Item Number (“CLIN”) the Landscaping & irrigation work will fall under. Will it fall under the CLIN 1-4 scope demarcation per sheet G102 CLIN PLAN, or will it all fall under Base Bid, or all under Options?
Response: Refer to the CLIN Plan, sheet G102. Here is an additional explanation.
CLIN 1 includes:
• All landscaping and irrigation shown behind the Center Wall, behind the South Wall, around the sidewalk from the visitor parking lot to the entrance plaza, area around and under the new timber stairs, behind the North Wall, around the sidewalk along the north lawn.
CLIN 2 includes:
• Grass in northeast corner of entrance plaza.
CLIN 3, Option A includes:
• Landscaping along the existing sidewalk on the south side of the fort from the existing stairs into the plaza to the sidewalk connection to A1A, and landscaping along the new pedestrian path from the plaza to the proposed connection point to A1A (south and southwest of the fort).
CLIN 4, Option B includes:
• Landscaping along the proposed pedestrian path from the new timber stair structure to the location where the path splits to connect to A1A (north and northwest side of the fort).
RFI #004 – Clarification for Bid Amount Entry on Bid Form
Can you provide the following clarification on Page 2 of 75 of the Solicitation Document under the Offer section – What Dollar Value do we enter at the “AMOUNTS” block below item #17? Will that be TOTAL BASE PRICE (Contract Line-Item Number 1 through 2), or TOTAL PROPOSED PRICE – BASE PLUS ALL OPTIONS (CLIN 1 through 4), or other?
Response: For Block 17 of page 2 the following can be written - “See Section B – Bid Schedule”
For the Bid Schedule fill out as stated.
RFI #005 – Permitting Requirements and Jurisdictions for New Building
For the new fee station building, can you provide more clarification on which permits are required, by which entity(s) and/or jurisdiction(s), and who will be responsible for pulling them (GC or Owner)?
Response: No permits are required for the new fee station building.
RFI #006 – Design Clarification on Center Seawall Repair
Sheet(s) / Sub Sheet(s): 98/120 - SM103 Center Seawall Repair Plan
Detail A has a 4’ dimension and a 3’-6” Max. dimension that contradicts.
Please advise.
Response: There are varying stone dimensions at the landside and waterside. At the waterside edge, the maximum stone length is 3’-6”. At the landside edge, stones are more regular at approximately 4’-0”.
RFI #007 – Design Clarification on Concrete Strength details
Sheet(s) / Sub Sheet(s): 94/120 - SM001 Structural Notes (1 of 2)
31/119 - C501 Site Details
Plan sheet 94 of 120 (SM001) concrete item 10 states Cast-in-Place Concrete is 5500 PSI.
Plan Sheet 31 of 119 (C501) details 3 and 6 indicate concrete is 3500 PSI.
Please advise.
Response: The notes on SM001 related to concrete strength only apply to elements in the marine (SM) sheets. The notes on C501 are valid for details on that sheet.
RFI #008 – Design Clarification on Steel Sheet Pile Cofferdam Locations
Sheet(s) / Sub Sheet(s): 88/120 - DM101 Demolition Plan
97/120 - SM102 Enlarged Seawall Plans
Plan sheet 88 of 120 (DM101) shows the steel sheet pile cofferdam at the south wall only and not at the south transition wall. We will need to extend the cofferdam to be able to form and pour the concrete wall per detail 2 on SM102.
Please advise.
Response: The cofferdams have been permitted as shown. The intent of the south transition wall construction is to use watertight forms as has been employed successfully on similar bulkhead/seawall projects including outfall extensions.
RFI #009 – Design Clarification on Environmental Control Plan
Sheet(s) / Sub Sheet(s): 82/120 – GM102 Environmental Control Plan
Plan sheet 82 of 120 (GM102) shows 970 SF of existing scattered oyster clumps behind south wall to be relocated to the recipient site. Upon visiting the site last Tuesday, 12/16/25, we observed that these oysters appear to be dead or destroyed.
Please advise.
Response: The quantity of oyster clumps was documented at the time of the project biological assessment and submitted to permit agencies. Assume the same quantity of oysters to be relocated and will be confirmed with the project team during preconstruction.
RFI #010 – Design Clarification on Coquina/Shell Concrete
Sheet(s) / Sub Sheet(s): 94/120 – SM001 Structural Notes (1 of 2)
112/120 – SM502 Center Seawall Repair Details
Please confirm that plan sheet 94 of 120 (SM001) concrete note 10C Coquina Concrete 1000 PSI is the same as the Shelled Concrete shown on plan sheet 122 of 120 (SM502) Section 1 “Replace Edge Stone with Shell Concrete.”
Response: Confirmed.
RFI #011 – Design Clarification on new Utility Force Main Installation
Sheet(s) / Sub Sheet(s): 27/119 – C302 Utility Plan 2 of 2
Can the short coquina wall at the north end of the South Wall be demolished to allow for the installation of the new Force Main line?
Response: The existing wall is to remain intact during demolition of the existing force main and installation of the proposed force main. The proposed force main shall be pipe jacked or bored under the wall. The existing depth of the wall is unknown and will require coordination during construction to impact the wall as little as possible.
RFI #012 – Design Clarification on Existing Seawall Demolition
Sheet(s) / Sub Sheet(s): 89/120 – DM301 Demolition Sections
107/120 – SM302 Typical Seawall Sections (2 of 3)
On plan sheet 89 of 120 (DM301) at Detail 4, it does not state to “Demolish Existing Wall” like it does on Details 1 and 3. However, this wall needs to be demolished in order to install the new wall design as shown on plan sheet 107 of 120 (SM302).
Response: Correct, the south wall is to be demolished under this scope of work.