B09-140P2025R0112-Amd_3_0003.pdf

PDF 9 MB Posted

Attached to
GLAC 318705 Replace Utility Systems - Construction Federal contract opportunity
Solicitation number
140P2025R0112
Issued by
Department of the Interior National Park Service National Office

About this file

This is a solicitation document for a National Park Service (NPS) utility system replacement project at Glacier National Park. The project, designated GLAC 318705, involves rehabilitating water and septic systems in three primary areas: St. Mary (Hudson Bay and Campground), St. Mary Winter Septic System, and Two Medicine. The total project is estimated at more than $10 million, with a 610-calendar day performance period after Notice to Proceed.

The solicitation is a total small business set-aside with a $45M small business size standard, using a firm fixed-price contract type (NAICS Code 237110). Key project components include groundwater well improvements, distribution system upgrades, treatment/control building construction, water storage tank rehabilitation, and septic system installations. Proposal submissions are due December 5, 2025, at 2:00 p.m. MST, with a pre-proposal virtual conference on November 6, 2025, and an on-site visit on November 12, 2025. The NPS will evaluate proposals using a Best Continuum Tradeoff Process, considering technical approach, management approach, schedule, project experience, and past performance.

View the file

Other files for this federal contract opportunity

Show all 21

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

(x)

140P2025R0112 x x

1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE

RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR

OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

x

PDS

Denver CO 80225-0287 P.O. Box 25287 1 Denver Federal Center, Building 50 DOI, NPS, DSC Contracting Services

PDS

Denver CO 80225-0287 P.O. Box 25287 1 Denver Federal Center, Building 50 NPS, DSC Contracting Services Div

11/06/20250003

13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

FACILITY CODE CODE

10B. DATED (SEE ITEM 13)

10A. MODIFICATION OF CONTRACT/ORDER NO.

9B. DATED (SEE ITEM 11)

9A. AMENDMENT OF SOLICITATION NO.

CODE

8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)

7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY

PAGE OF PAGES

4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)

1. CONTRACT ID CODE

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

10/01/2025

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority) appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

E. IMPORTANT: Contractor is not is required to sign this document and return __________________ copies to the issuing office.

ORDER NO. IN ITEM 10A.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

GLAC 318705 - Replace Utility Systems

The purpose of this amendment is to:

a) Provide the Pre-Proposal Virtual Conference Attendee List.

b) Provide the Pre-Proposal Virtual Conference Power Point Presentation.

c) Provide the Q&A's received to date.

d) Provide an updated Bid Schedule for use when providing proposals.

e) Provide the Limitations on Subcontracting Form to document percentage of subcontracting being proposed.

Continued ...

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)

15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED

(Signature of person authorized to sign) (Signature of Contracting Officer)

Vicki Freese-supler

STANDARD FORM 30 (REV. 11/2016)

Prescribed by GSA FAR (48 CFR) 53.243

Previous edition unusable

Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .

ITEM NO. SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

NAME OF OFFEROR OR CONTRACTOR

2 2

CONTINUATION SHEET

REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF

(A) (B) (C) (D) (E) (F)

140P2025R0112/0003

All other terms and conditions of the solicitation remain unchanged and in full force and effect.

NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)

Sponsored by GSA

FAR (48 CFR) 53.110

Solicitation #140P2025R0112 Pre-Proposal Virtual Conference

AttendeesName Email Company Address Phone

Ryan DeMars rdemars@ctlthompson.com CTL Thompson 153 Shepherd Trail, Unit G, Bozeman, MT 406-551-9125

Dick Campbell dick.campbell@tepa.com TEPA Companies 103 Ed Bayer Ct. #100, Warner Robins, GA 478-960-8540

Jake Simmons jacob.simmons@tepa.com TEPA Companies 2345 Grand Blvd., Suite 700, Kansas City, MO 816-550-1075

Chris Glotzbach chris.glotzbach@tepa.com TEPA COmpanies 2345 Grand Blvd., Suite 700, Kansas City, MO 816-708-1181

Kris Anderson krisa@mrcmt.com Missouri River 2385 McClellan Creek Road, Helena, MT 406-594-2285

Tom Schulke tom@mrcmt.com Missouri River 2385 McClellan Creek Road, Helena, MT 406-439-6597

Nick Miller nickm@mrcmt.com Missouri River 2385 McClellan Creek Road, Helena, MT 406-594-2283

John Gilham john@ekandassociates.com Edward Kennedy & Associates 406-450-4175

Clark Davis clark.davis@ferguson.com Ferguson 112 E. Reserve Drive, Kalispell, MT 406-300-6055

R.E. Stout restout@sterlingconstructorsvo.com Sterling Constructors 303-720-2521 John Michael King jmking@sterlingconstructorsvo.com Sterling Constructors Todd Knapp tknapp@sterlingconstructorsvo.com Sterling Constructors Makayla King mking@sterlingconstructorsvo.com Sterling Constructors

Jeff Wilson jeff.wilson@tepa.com TEPA Companies 5575 Tech Center Drive, Suite 217, Colorado Springs 719-320-3845

Tommy Bartlett tommy.bartlett@tepa.com TEPA Companies 5575 Tech Center Drive, Suite 217, Colorado Springs

James Rank james.rank@tepa.com TEPA Companies 5575 Tech Center Drive, Suite 217, Colorado Springs

Mitch Hill mitch@sandryconstruction.com Sandy Construction 406-250-2544 Devin Bair devin@baircoconstruction.com Bairco Construction 307-548-6216 Charlie Cooley charlie@baircoconstruction.com Barico Construction 307-272-1564 Ron McCutcheon ron.mccutcheon@tepa.com TEPA Companies 816-708-1176 Chelsey Leonhardt chelsey@baircoconstruction.com Bairco Construction 307-548-6216

Virtual Pre-Proposal Conference

GLACIER NATIONAL PARK

REHABILITATE UTILITY SYSTEMS

PHASE 1 – ST. MARY & TWO MEDICINE

Solicitation: 140P2025R0112

NPS PMIS #: GLAC 318705

November 6, 2025

E X P E R I E N C E Y O U R A M E R I C A

Agenda WELCOME & INTRODUCTIONS : Marcello Arroio Bebianno Simoes, NPS-DSC Project Specialist

• Team Introductions

• Agenda

• Site Visit Constraints / FHWA work

PROJECT OVERVIEW : Kevin Johnson, DOWL Project Manager

• Project Overview: Summary of work at each location

PROJECT OVERVIEW : Krista Wassenaar, Glacier NP Engineer/PM

• Project Phasing / Seasonal Work Restrictions

PROPOSAL/SOLICITATION INFORMATION : Vicki Freese-Supler, DSC Contracting Officer

• Summary of Solicitation

• Timeline

• Project Site Tour Logistics

Project Team DSC PM – Josh Hooper DSC PS – Marcello Arroio Bebianno Simoes DSC CO – Vicki Freese-Supler GLAC Engineer – Krista Wassenaar GLAC Facilities – Jana Montiel AE Design Engineer – Kevin Johnson

1. St Mary Water System Improvements

A. Hudson Bay (Year-round housing / admin area)

B. St Mary Visitor Center and St Mary Campground (seasonal/summer system)

2. St Mary Winter Septic System Improvements

A. Winter use system; Existing WWTP only used in summer.

3. Two Medicine Water System Improvements

A. Seasonal/summer system

Project Overview

1. Hudson Bay Area A. Groundwater wells

a) New groundwater Well #2(drill and pump test); final pump TBD

b) Rehab of existing Well #1

I. Modify existing well with new pitless adapter equipment II. Existing chlorination building (over existing Well #1) III. Complete this work after Well #2 and new chlorine building are complete

B. New chlorination and pump control building

a) Chlorination and misc. process mechanical equipment

b) Emergency generator (propane)

c) New PLC/HMI controls

Project Overview – St Mary Water System Improvements

1. Hudson Bay Area (cont..)

A. Full water main replacement with HDPE in new location(s)

a) Installed below frost level

b) Some exceptions at south end (winterized/drained)

B. Existing system to remain live until new system is tested C. Then finish/connect new building services

a) Services connect inside buildings (crawl spaces or basements) D. Surface Restoration – Asphalt restoration limits as shown in details

1. St Mary Campground A. Full water system replacement B. Existing asbestos cement pipe; remove and dispose C. Replace with new HDPE in same location D. Existing waterlines shown in approximate locations E. New appurtenances (hydrants, camp site spigots, comfort station connections, drain provisions) F. Designed to drain; Install pipeline to design profile/grade.

G. Asphalt restoration: Full width remove and replace; except where otherwise noted.

1. St Mary Visitor Center A. Water main replacement B. Surface Restoration

Project Overview – St Mary Water – Visitor Center

1. Sanitary sewer extensions

2. Level 2 treatment system

3. Dose tank and pumps

4. Pressure-dosed drain field

5. Abandonment of existing septic tanks & misc. facilities

Project Overview – St Mary Winter Septic System Improvements

1. Two Medicine Area A. Rehab one of two existing groundwater wells (Well #1)

a) Abandon third, existing well (Well #2)

b) Install new level transducers in two existing wells (Wells #1 and #3)

c) Install manual transfer switch on existing Well #3

B. Demo existing chlorination building and an existing, abandoned tank

a) Temporary chlorination system required

b) Temporary connections/controls for Well #3 operation

C. New chlorination and pump control building

a) Chlorination and misc. process mechanical equipment

b) Emergency generator (propane)

c) New PLC/HMI controls

Project Overview – Two Medicine Water System Improvements

1. Two Medicine Area (cont.)

D. Existing water storage tank rehabilitation/sealing E. Full water main replacement

a) Remove and dispose existing asbestos cement pipe

b) Install new system in same location/trench

c) Designed to drain (install to design grades)

d) Existing waterlines shown in approximate locations

e) New appurtenances (hydrants, camp site spigots, comfort station connections, drain provisions) F. Surface (Trench) Restoration – Asphalt restoration limits as shown in details

Existing chlorine building, abandoned tank and current tank Existing chlorine building, abandoned tank and current tank

Typical campground roadway and waterline location (Loop A) Typical campground roadway and waterline location (Loop A)

Typical campground road and waterline location (Loop B) Typical campground roadway and waterline location (Loop C start)

Camp store and comfort station near boat ramp (day use area) Boat ramp and parking area (day use area)

Work Restrictions - St. Mary Water System Improvements Work Window/Schedules A. Hudson Bay

a) No visitation-related restrictions. See Sec 01 10 00 Summary of Work for access coordination/limitations.

B. Visitor Center

a) No work can commence while the

Visitor Center is open to the public.

Work can proceed around the Visitor Center until May 11, 2026 and after October 10, 2026.

C. St Mary Campground

b) Work on GTSR cannot be done from July

1 to September 30. Contractor to maintain traffic during this time. Traffic hold restriction is set to 10 minutes.

c) Full Campground closure allowed from January 1 to June 19, 2026 to accommodate construction.

1. Work Window/Schedules A. Work on this project is not impacted by visitation and can proceed weather permitting.

B. The force main relocation shall be completed upon the NPS winterization/draining of the force main, between October 1st and April 30th.

C. Substantial completion by November 1, 2026, for use in winter.

Work Restrictions– St Mary Winter Septic System Improvements

Work Restrictions– Two Medicine Water System Improvements Work Window/Schedules 2026 Season

a) (Loops A, B, C) will be under a full closure to public access and available for construction.

b) The Day Use Area (concessionaire area, general store, and boat ramp) and Picnic Area, including the Ranger Station, must remain open to administration and public use (with water available) during normal visitation season, May 22 to September 8.

See temporary chlorination provisions

c) Either the Picnic loop or Loop A must remain available for picnic/day use during the visitation season – but water does not have to be available.

Solicitation No. 140P2025R0117 Summary of Solicitation and Award Information

Please refer to the Solicitation for complete details:

Pre-Proposal Virtual Conference – November 6, 2025 Pre-Proposal On Site Visit – November 12, 2025, 11:00 a.m.

Offers Due: December 5, 2025, 2:00 p.m. MST Submission: Electronic to Vicki Freese-Supler and Kristin Tauber Section L: 52.216-1 – Type of Contract – Firm Fixed Price NAICS Code 237110 – Water and Sewer Line and Related Structures Construction Small Business Size Standard: $45M This is a Total Small Business Set Aside Period of Performance: 610 Calendar Days After Issuance of NTP Magnitude: More than $10M

Solicitation Clauses:

FAR 52.211-12 – Liquidated Damages-Construction - $1,632.00.

FAR 52.236-2 – Differing Site Conditions FAR 52.236-3 – Site Investigations and Conditions Affecting the Work FAR 52.236-9 – Protection of Existing Vegetation, Structures, Equipment, Utilities and Improvements FAR 52.236-21 – Specifications and Drawings for Construction

Basis for Award The Government will conduct a source selection using the Best Continuum Tradeoff Process defined at FAR Part 15.1. The Contracting Officer (CO) will obligate and award a contract to the Offeror who submits a proposal the Source Selection Authority (SSA) determines conforms to solicitation requirements; is fair and reasonable; and provides the best value to the government considering all evaluation factors combined as detailed below:

The Government may accept other than the lowest priced proposal when the perceived benefits of a higher priced proposal merit the price differential.

Additionally, pursuant to FAR 52.215(f), Contract Award, contained herein:

The Government may reject any or all proposals if such action is in the Government’s interest.

The Government may waive informalities and minor irregularities in proposals received.

The Government intends to evaluate proposals and award a contract without discussions with

Offerors (except clarifications as described in FAR 15.306(a)). Therefore, the Offeror’s initial proposal should contain the Offeror’s best terms from a cost or price and technical standpoint. The Government reserves the right to conduct discussions if the CO later determines them to be necessary.

Technical Evaluation Criteria:

Factor 1 – Technical Approach Approach to Critical Contract Requirements Logistics, Coordination, Process Risk Mitigation Natural, Cultural or Historic Resources Factor 2 – Management Approach Organizational Chart Capacity Owner and Regulatory Entity Coordination Safety/Quality Control

Technical Evaluation Criteria, Cont.:

Factor 3 – Schedule MS Project Gantt Chart Format Assume NTP date of April 1, 2026 Include specific activities require for this project and a clear critical path with major milestones and applicable predecessor activities. This shall include but not be limited to Division 1 submittals, commissioning activities, procurement lead time and seasonal shutdowns and float.

Factor 4 – Project Experience Relevant projects for up to five projects.

Teaming Experience Remote Work Utility Construction Experience

Factor 5 – Past Performance Factors 1-5 are listed in descending order of importance. Overall, proposed pricing is an evaluation factor. All evaluation factors other than price, when combined will be equal to price.

Technical Proposal Submission Requirements:

1. Documents to Provide With Proposal Submission

a. SF 1442

b. All amendments, acknowledged

c. Section B – Price Schedule

d. SF 24 Bid Bond (or other suitable guarantee)

e. Section K Representations and Certifications

f. General References

g. Subcontracting Percentage Worksheet

Schedule B - Contract Bid Items

Solicitation – Important Information

Direct all questions to the CO who requests that they be submitted in writing via email to both the CO, Vicki Freese-Supler, vicki_l_freese-supler@nps.gov and the CS, Kristin Tauber, Kristin_tauber@nps.gov.

Questions and answers will be issued by written amendment posted to the solicitation on SAM.gov. Offerors are required to fill out and sign the acknowledgment of amendments received (SF 1442 Section 19) and include this when submitting offer.

For all other interested vendors not able to attend the pre-proposal virtual conference or site showing, an amendment will be provided which will include this presentation and sign in sheet.

The deadline for questions related to this solicitation is: November 28, 2025 The proposal submission date is December 5, 2025 at 2:00 p.m. MST.

mailto:vicki_l_freese-supler@nps.gov mailto:vicki_l_freese-supler@nps.gov mailto:vicki_l_freese-supler@nps.gov mailto:Kristin_tauber@nps.gov

Thank You For Your Interest in This Project

E X P E R I E N C E Y O U R A M E R I C A

National Park Service U.S. Department of the Interior

Pre-Proposal Virtual Conference

AttendeesMary Mohland mary.mohland@centralph.com Central PH 406-579-9615 Jesse Waldenberg jesse.waldenberg@centralph.com Central PH 406-579-9615 Kolby Green kolby.green@centralph.com Central PH 406-579-9615 Jeff Zarycki jeffrey@karvllc.com KARV Directional Drilling 406-598-3182 Stephanie McElhinneysteph@allterrainexcavationmt.com All Terrain Excavation 509-952-3116 Ashley Hardy ashley@mckenzieconst.com McKenzie Construction 703-505-8346 Brian Willette brian@mckenzieconst.com McKenzie Construction 703-505-8346 Brien Ables brien@mckenzieconst.com McKenzie Construction 703-505-8346 Kelsey Skinner kskinner@ams-industrial.com AMS Industrial 650-743-3739 Sam Meyers samw@lhcmt.com LHC Mt

GLAC 318705 - Replace Utility Systems

Construction Package 1 - St. Mary Water, St. Mary Winter Septic and Two Medicine Questions and Answers

A B C D E F

Can you provide the limits of subcontracting sheet as part of the solicitation for the proposal? Please see attached document. 11/6/2025 3

PPQ(s) are requested; however, with the shutdown may be limited in terms of responses due to the furlough and government shutdown. Please see response to Q7 below. 11/6/2025 3

Definition of contract line items as CLIN 01- 05 as an option for asphalt restoration in the St. Mary's (Schedule 1). That option is not on the Bid Schedule - Can you confirm if it will be added.

Yes, they are being added. Please see revised Bid Schedule attached. 11/6/2025 3

Definitiion of contract line items has CLIN 03- 06 as an option for asphalt restoration in Two Medicine (Schedule 3). That option is not on the Bid Schedule. Can you confirm if it will be added.

Yes, they are being added. Please see revised Bid Schedule attached. 11/6/2025 3

SF 1442 Block 13a says "original and 1 copy";

however, Section L, RFP, Page 65 and 68 "submit (1) electronic copy" for each volume.

Please confirm that only one electronic copy is required of each volume.

Confirmed, only one (1) electronic copy is required. 11/6/2025 3

Construction Package 1 - St. Mary Water, St. Mary Winter Septic and Two Medicine Questions and Answers

A B C D E F

Section L, Factor 2 - Management Plan requires "submission of resumes for key personnel (superintendent, quality control, safety, and project manager). For key subcontractors, submit a signed letter of commitment from the subcontractor…."

Given that Offerors are limited to 10 pages for this factor and resumes and letters of commitment have the potential to require nearly 10 pages alone, can the NPS confirm that key personnel resumes and key subcontractor letters of commitment are exluded from the 10-page limit.

Confirmed, these are excluded from the 10-page limit. 11/6/2025 3

Section L, Factor 5, Past Performance states "submit Past Performance information for the same projects submitted under Project Experience (Factor 4) using the attached Past Performance Questionnaire". Will the NPS accept previously completed Past Performance Questionnaires in lieu of requesting our references to complete a new Past Performance Questionnaire? If so, can you please confirm that Offerors should include previously completed Past Performance Questionnaires in our proposal response with Factor 5 - Past Performance. This is acceptable. 11/6/2025 3

Construction Package 1 - St. Mary Water, St. Mary Winter Septic and Two Medicine Questions and Answers

A B C D E F

Section L, Factor 5 Past Performance states "CPARS evaluation reports will be obtained by NPS in addition to the Past Performance Questionnaire for use in evaluating an Offeror's Past Performance record." If CPARS evaluation has been completed, our references will not typically complete a Past Performance Questionnaire. Can the NPS confirm that Offerors are not required to request completion of a Past Performance Questionnaire if a project has an existing CPARS evaluation?

No - Past Performance Questionnaires must be provided.

When the NPS pulls CPARS evaluation information, the evaluations are randomly selected. 11/6/2025 3

Specification Section, 01 40 00, Page 3, Paragraph 1.5.B Contractors Quality Control Staff states the following: "1. Contractor's Quality Control Supervisor may also perform other duties."

All key personnel positions must be separate individuals serving in those functions. No dual hatting will be allowed. 11/6/2025 3

Contractor's Quality Control Supervisor shall be assigned no other duties. Can the NPS please clarify whether the Contractor's Quality Control Supervisor may also serve as the Job Site Safety Manager (also referred to as SSHO in the specifications?

All key personnel positions must be separate individuals serving in those functions. No dual hatting will be allowed. 11/6/2025 3

Construction Package 1 - St. Mary Water, St. Mary Winter Septic and Two Medicine Questions and Answers

A B C D E F

Are Offerors required to complete and include Section H (Page 17), SPECIAL REQUIREMENT 4: KEY PERSONNEL in our proposal response in addition to identifying and providing resumes for key personnel with Factor 2 - Management Plan?

No - this will be completed by the NPS after award. 11/6/2025 3

Questions Response Date Amendment

Contract Number:

Prime Contractor:

Current Total Contract Price:

Type of Set Aside:

Period of Performance MM/DD/YYYY - MM/DD/YY Type of Service (Required Participation):

$0 $0

Total Amount Paid To: [Insert SSS company name] $0 Total Amount Paid To: [Insert SSS company name] $0 Total Amount Paid To: [Insert SSS company name] $0 Total Amount Paid To: [Insert SSS company name] $0

Total Amount Paid To: [Insert SSS company name] $0

$0 Total Amount Paid To: [Insert NSS company name] $0 Total Amount Paid To: [Insert NSS company name] $0 Total Amount Paid To: [Insert NSS company name] $0 Total Amount Paid To: [Insert SSS company name] $0

Total Amount Paid To: [Insert SSS company name] $0

#DIV/0!

#DIV/0!

1) Amount Invoiced by the Prime Contractor:

[Insert type of set-aside: Small Business, HUBZone, SDVOSB, WOSB, 8(a), etc.]

Amounts shown below shall include amounts from all previous invoices and the current invoice. Exclude the cost of materials.

* Similarly Situated Subcontractor (SSS): is a small business subcontractor that is a participant of the same Small Business Administration (SBA) program that qualified the prime contractor as an eligible offeror and awardee of the contract as defined in 13 CFR 125.6 (i.e. Small Business, HUBZone Business, Service Disabled Veteran Owned Small Business (SDOVB), etc.)

2) Portion of Amount Invoiced for All Similarly Situated Subcontractors (SSS)*

3) Portion of Amount Invoiced for Non-Similarly Situated Subcontractors (NSS)

4) Prime & SSS Participation %

** Limitation on Subcontracting Percentage = (Total amount invoiced by the Prime Contractor - Portion of total amount invoiced for Non-Similarly Situated Subcontractors (NSS)/ Total amount invoiced by the Prime Contractor)

Participartion Calculation as of the Current Invoice

5) % subcontracted to NSS

[Insert the amount of the original contract + all excuted contract modifications]

If the NSS % noted in line 5 above is not in compliance with the % required by contract clause 52.219-3, 14, 27,29,30 then the prime contractor shall provide a written corrective action plan below:

Corrective Action Plan

Report on Limitations on Subcontracting [Template Version 7/25/19]

1) Services (except construction). 50% maximum may be subcontracted to non-similary situated Subcontractors

2) General construction. 85% maximum may be subcontracted to non-similary situated Subcontractors

3) Construction by special trade contractors. 75% maximum may be subcontracted to non-similary situated Subcontractors

This report is required for small business, 8(a) or other socio-economic set-aside service contracts (including construction) priced at or above $150,000.

[Insert prime contractor's company name] [Insert contract #]

[Put an X in the applicable box below per clause 52.219-3, 14, 27,29,30]

ATTACHMENT 7

PARK: Glacier National Park

PARK - PMIS: GLAC 318705

PROJECT TITLE: Replace Utility Systems: Package 1 - St. Mary Water, St. Mary Winter Septic, Two Medicine Water

CONTRACT

LINE ITEM NO

BID ITEM CONTRACT LINE ITEM

TITLE QUANTITY

UNIT OF

MEASURE UNIT PRICE = TOTAL PRICE

CLIN 1-01 Mobilization/Demobilization 1.0 LS = -$ CLIN 1-02 Distribution System Improvements 1.0 LS = -$ CLIN 1-03 Groundwater Well 1.0 LS = -$ CLIN 1-04 Treatment/Control Building 1.0 LS = -$ CLIN 2-01 Mobilization/Demobilization 1.0 LS = -$ CLIN 2-02 Winter Septic System 1.0 LS = -$ CLIN 3-01 Mobilization/Demobilization 1.0 LS = -$ CLIN 3-02 Distribution System Improvements 1.0 LS = -$ CLIN 3-03 Groundwater Well 1.0 LS = -$ CLIN 3-04 Treatment/Control Building 1.0 LS = -$ CLIN 3-05 Water Storage Tank Rehabilitation 1.0 LS = -$

TOTAL BASE BID (Contract Line Items 01 through 04) ------------------------------------------------------------------------------- =

CLIN 1-05 OPTION 1A - Asphalt Paving 1.0 LS = CLIN-3-06 OPTION 3A - Asphalt Paving 1.0 LS =

TOTAL OPTIONS (Items 05) ------------------------------------------------------------------------------------------------ =

TOTAL PROPOSED PRICE (ITEMS 01 THROUGH 05) ----------------------------------------------------------------------------- = -$

Notice: Refer to FAR Clause 52.217-5, Evaluation of Options, as prescribed in FAR 17. Submit pricing for base price and all options. Failure to do so may render the proposal unacceptable. On lump sum items, provide total price only; on unit price items, provide the unit price and the extended amount. If no item exists for a portion of the work, include the costs in a related item. In case of error in extension prices, unit governs. In case of errors in summations, the total of the corrected amounts govern. Limit amounts to whole dollars. The Government reserves the right to award any or no options at or after the time of award. At the option of the Government, the period for exercise of options at the proposed prices shall extend 180 calendar days from the Notice to Proceed. Pricing will be evaluated based on best value to the Government. Options may be exercised in any combination, order, or grouping deemed in the judgement of the Contracting Officer to offer the best advantage (value) in goods and services for the dollar. Award will be made to one offeror in accordance with the Evaluation Factors for Award, Section M

In addition to the offer that conforms to the solicitation documents, offerors are encouraged to submit alternate proposals that will result in cost savings to the Government. Such proposals shall clearly identity why the acceptance of the alternate proposal would be advantageous to the Government, see FAR Clause 52.215-1, Instructions to Offerors - Competitive Acquisition- Alternate II and DSC-36 Clause (Instructions for Submission of Offers and Other Information) in Section L of the Solicitation.

GLAC 318705 - Pre-Proposal Virtual Conference List.pdf
Sheet1
GLAC 318705 - Replace Utility Systems, Phase 1 - Pre-bid_V3.pdf
�Virtual�Pre-Proposal Conference ��Glacier National park�Rehabilitate utility systems�phase 1 – St. Mary & two medicine ��Solicitation: 140P2025R0112�NPS PMIS #: GLAC 318705�November 6, 2025
Agenda
Slide Number 3
Slide Number 4
Slide Number 5
Slide Number 6
Slide Number 7
Slide Number 8
Slide Number 9
Slide Number 10
Slide Number 11
Slide Number 12
Slide Number 13
Slide Number 14
Slide Number 15
Slide Number 16
Slide Number 17
Slide Number 18
Slide Number 19
Slide Number 20
Slide Number 21
Slide Number 22
Slide Number 23
Slide Number 24
Slide Number 25
Slide Number 26
Slide Number 27
Slide Number 28
Slide Number 29
Slide Number 30
Thank You For Your Interest in This Project