B08_Project_Experience_Questionnaire_0004.docx
DOCX document 46 KB Posted
- Attached to
- GLAC 318705 Replace Utility Systems - Construction Federal contract opportunity
- Solicitation number
- 140P2025R0112
About this file
The document is a Project Experience Questionnaire for Solicitation 140P2025R0112, related to a utility systems replacement construction project in Glacier National Park, Montana. The questionnaire requires detailed responses about previous project experience, focusing on work performed by contractors Sparky's Electrical Company (prime contractor) and ABC Plumbing & Heating, Co (subcontractor). The document requests comprehensive information about project scope, price changes, schedule modifications, problem resolution, successful methods, and additional project insights.
The solicitation, issued by the Department of the Interior National Park Service, involves replacing utility systems in three specific areas: St. Mary Water System Improvements, St. Mary Winter Septic System Improvements, and Two Medicine System Improvements. The project questionnaire is designed to evaluate contractors' past performance and capabilities through a structured series of seven questions that probe the technical, operational, and management aspects of previous similar work. Contractors must provide detailed explanations of their project experiences, demonstrating their competence and approach to complex utility infrastructure replacement projects.
View the file
Other files for this federal contract opportunity
Show all 21
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Project Experience Questionnaire Solicitation: 140P2025R0112
Submit responses to the questions below that address experience relative to the elements noted under the Project Experience evaluation subfactor in solicitation section L. Limit submittals to the quantity of projects and timeframes required in the solicitation. Expand the response sections shown below as needed to adequately address each question (this questionnaire may be expanded to multiple pages if needed).
| Offeror |
| Company Name |
REFERENCED PROJECT INFORMATION
| Project Title |
| Title |
| Project Location |
| City, State |
| Brief Project Description |
| Description |
| Project Owner |
| Company Name |
| POC: |
| First & Last Name |
| Phone: |
| (XXX) XXX-XXXX |
CONTRACTOR LIST
List Contractor(s) whose experience on the referenced project is being submitted for evaluation on this proposed project. If more than one contractor is listed (i.e. prime and subcontractors), provide information specific to that contractor.
| Contractor Name |
| Role on Referenced Project |
(Prime or Sub)
| Trade |
| Price |
(list for each contractor’s specific work) Performance Period (calendar days) (list for each contractor’s specific work)
| Original |
| Final |
| Original |
| Final |
| Sparky’s Electrical Company |
| Prime |
| Prime |
| $XXX,XXX |
| $X,XXX,XXX |
| XX |
| XX |
| ABC Plumbing & Heating, Co |
| Subcontractor |
| Plumbing & Mechanical |
| $X,XXX,XXX |
| $X,XXX,XXX |
| XXX |
| XXX |
Subcontractor
PROJECT EXPERIENCE QUESTIONS
1. Describe the project work performed by all contractors listed above.
Response
2. Identify which Project Experience elements listed in section L of the solicitation each contractor’s work addresses.
Response
3. Describe & provide reasons for any changes to the original price for the work described in question 2 above.
Response
4. Describe and provide reasons for any changes to the original schedule for the work described in question 2 above.
Response
5. Describe problems, associated with the work described in question 2 above, which were encountered and how they were resolved. Describe how the offeror’s proposal accounts for similar issues.
Response
6. Describe the means and methods, associated with the work described in question 2 above, which were successful. Would you implement the same means and methods on the proposed project? Why or why not?
Response
7. Provide any other additional project information you believe should be presented.
Response
File details come from the government source that posted it. Updated .