This document is a Request for Information (RFI) Amendment 0003 for FODO 253278, providing detailed responses to 36 technical and procedural questions about an ongoing construction project. The RFI covers multiple system and trade aspects, including personnel requirements, project scheduling, existing infrastructure reuse, and specific technical details across mechanical, electrical, plumbing, fire alarm, communications, and utility systems.

Key highlights include: The project involves renovating an unoccupied building with multiple incomplete systems; the contractor will be responsible for coordinating with utilities (specifically Cumberland Electric Membership Corporation), commissioning all systems, and determining reuse or replacement of existing infrastructure. Critical requirements include installing a new VRF HVAC system, complete fire alarm system, new electrical systems, and coordinating elevator installation with Thyssenkrup Elevators. The contractor must test and verify existing systems, complete partial installations, and ensure all systems meet current code compliance. The utility transformer is already installed, and the utility company will energize the permanent service after contractor equipment inspection and acceptance.

View the file

Other files

File Type Posted
B09_SF30_Amendment_0005_140P2025R0054_0005.pdf PDF
Sol_140P2025R0054_Amd_0005.pdf PDF
B09_SF30_Amendment_0004_140P2025R0054_0004.pdf PDF
B09_Amendment_0004_FODO_253278_RFI_06_Responses_0004.pdf PDF
Sol_140P2025R0054_Amd_0004.pdf PDF
B09_Amendment_0004_FODO_253278_RFI_05_Responses_0004.pdf PDF
B09_SF30_Amendment_0003_140P2025R0054_0003.pdf PDF
B09_FODO253278_2nd_Site_Visit_Attendance_11192025_0003.pdf PDF
B09_Amendment_0003_FODO_253278_RFI_03_Responses_0003.pdf PDF
Sol_140P2025R0054_Amd_0003.pdf PDF
B09_Amendment_0002_FODO_253278_RFI_01_Responses_0002.pdf PDF
B09_SF30_Amendment_0002_140P2025R0054_0002.pdf PDF
Sol_140P2025R0054_Amd_0002.pdf PDF
B09_Amendment_0002_FODO_253278_RFI_02_Responses_0002.pdf PDF
B09_SF30_Amendment_0001_140P2025R0054_0001.pdf PDF
Sol_140P2025R0054_Amd_0001.pdf PDF
B09_PreBid_Signin_Sheet_Oct282025_0001.pdf PDF
B09_PreBid_Agenda_Oct282025_0001.pdf PDF
B08_Attach_9-_Site_Condition_Survey_Report.pdf PDF
B08_Attach_5_-_Past_Performance_Q_FODO_253278.docx DOCX document
B08_Attach_8_-_General_References_FODO_253278.doc DOC document
B08_Attach_6_-_SF-24_Bid_Bond.pdf PDF
Sol_140P2025R0054.pdf PDF
B08_Attach_2-Drawings_FODO_253278_Final.pdf PDF
B08_Attach_1-Specifications_FODO_253278_Final.pdf PDF
B08_Attach_4_-_Project_Experience_Q_FODO_253278.docx DOCX document
B08_Attach_7_SubKPlan_FODO_253278.docx DOCX document
B08_Attach_3-WD_TN20250170.pdf PDF
Show all 28

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

FODO 253278

Amendment 0003

RFI #004

Item Question Response

1 Do the Superintendent, SSHO and QC Manager need to be 3 separate individuals?

The Superintendent can also act as the Safety Specialist. However, the Superintendent cannot act as the Quality Control Specialist. The Quality Control Specialist and Safety Specialist can be the same person.

2 Are there any phasing requirements? No, Contractor is resposible to develop project schedule.

3 If the building remains occupied, how many people will be in the building? Building is not occupied.

4 Are there any temporary heating/cooling requirements? Contractor is responsible to maintain

Can the period of performance be extended after award once the material/equipment lead times are confirmed due to current market conditions for the equipment for this project?

This can be considered.

Are soil boring reports available? If not, it will be assumed that excavation will be clear of rocks and obstructions.

See specification 01 11 00.

7 Please provide bidding quantities for deteriorated underlayment (roofing)/base course (paving).

Contractor to determine quantities based on the construction documents and the Site Condition Survey Report.

Please confirm the manufacturer of the existing roofing system and who carries the current warranty of the roofing system.

The roof membrane that is currently on the roof is a Johns Manville TPO membrane. The AE does not believe there is a warranty for the current roof system.

Please confirm whether asbestos or lead is present on this project, and if so, provide the relevant documentation.

NPS's understanding is that there is no asbestos or lead present on this project. However, we are not able to provide documentation.

10 Please provide the contact information for the building controls contractor. There is no building controls Contractor 11 Please provide the contact information for the building fire alarm company. Vector Security, 171 West Dunbar Cave Rd, Clarksville, TN 37040 12 Please provide the site visit attendee sign-in sheet. Please see attachments for Amendment 01 and 03 13 Please provide photos of the job site and existing conditions. Photos cannot be provided 14 Is this project tax exempt? No

In the Women's bathroom (002) sheet A7.1 of the drawings does not include the elevation detail for the entry door wall. Which, if any, wall tile will be going on this wall?

Tile W-3 shall be installed on that wall up to 5'-0" AFF (similar to details 3 & 5/A7.1).

In all of the bathrooms, the finish schedule calls for matching the tile base to the wall tile, is this correct even though each bathroom having two different types of wall tile?

The wall base tile shall be a 4x4 cove base tile that matches Tile W-3 for all the walls in each restroom/bathroom.

17 What should be used for the top of each wall tile to cap the tile? A bullnosed, finished edge.

Certain products and colors that are specified for this job have been discontinued and are no longer available, should we be getting as close to the requested color as possible, or is there an updated spec sheet?

Our recommendation is to replace the discontinued American Olean A81-Summer Rain with American Olean 0A36-Discovery and the discontinued American Olean 0045-Salt and Pepper with 4x4 Daltile ColorMatch Glazed Ceramic Tile CU33-Matte Carrara.

"The contract drawings and specifications list “Louvers, frames, and accessories” (Section 08 91 00), but several openings appear to include previously installed louvers, and at least one (A3.2) corresponds to a mechanical outside-air intake (“20 × 20 OA Intake” per M1.1). Please confirm:

A) Whether all exterior louvers under Section 08 91 00 are to be replaced in full or reused if existing units are serviceable.

The AE is not aware of any exterior louvers other than the one shown on A3.2, under the ramp. It was shown as 20"x20" on the construction documents, however, it was revised to 30"x20" in the submittal review and that is what was installed. The Site Conditions Survey Report states that this louver shall be replaced with a new aluminum louver. The louver shall be 30"x20" to match the opening. It shall have the appropriate trim flange to cover the gaps at the perimeter, and meet specification section 08 91 00 - Louvers.

B) If replacement is required, confirm model, performance criteria (AMCA 511, AAMA 2605 finish), and finish color (Benjamin Moore AC-29).

See specification section 08 91 00 - Louvers for requirements.

C) Confirm that the 20 × 20 fixed metal louver on A3.2 / A8.3 serves the mechanical OA intake, and that the architectural trade (Div 08) is responsible for furnishing and installing the louver assembly (frame, blades, finish, sealant), coordinated with Division 23 for ductwork termination, damper, and airflow testing."

As stated above, the louver is a fixed 30"x20" metal (aluminum) louver. The louver is specified in specification section 08 91 00 - Louvers. The General Contractor shall decide who furnishes and installs the louver.

20 "The Site Condition Survey indicates elevator installation is incomplete.

Elevator is stored in Thyssenkrup Elevators facility in Piperton, Tennessee. Contractor should coordinate elevator installation with Thyssenkrup. Jonathan Hord, Construction Superintendent M: 1-615-405-1629 jonathan.hord@tkelevator.com

Please confirm whether scope includes furnishing a new complete elevator system or completing work on existing equipment.

Elevator is stored in Thyssenkrup Elevators facility in Piperton, Tennessee. Contractor should coordinate elevator installation with Thyssenkrup. Jonathan Hord, Construction Superintendent M: 1-615-405-1629 jonathan.hord@tkelevator.com Additional AE Comments:

Per the original construction documents, the contractor must also coordinate elevator sprinkler and fire alarm requirements with the AE. The elevator is a machine-room-less hydraulic elevator.

Since the pump and hydraulic tank are located in the elevator pit, the pit is the machine room.

The fire sprinkler must be installed above the height of the tank; a heat detector is required to be installed within 24 inches of the sprinkler; and the luminaires in the pit must provide a minimum illumination level of 19 footcandles measured at the floor of the pit. The elevator controller will be located in the door jamb of the elevator. Coordinate the location of fire alarm control relays with the location of the controller. A minimum illumination level of 19 footcandles is also required at the location of the controller.

22 Provide manufacturer basis-of-design and warranty requirements."

See specification 14 24 00. Elevator is stored in Thyssenkrup Elevators facility in Piperton, Tennessee. Contractor should coordinate elevator installation and warranty with Thyssenkrup.

Jonathan Hord, Construction Superintendent M: 1-615-405-1629 jonathan.hord@tkelevator.com

"Confirm whether the existing sprinkler system is to be replaced or completed/repaired from prior work.

Completed, repaired and provide warranty.

Clarify connection to existing fire main and confirm testing and AHJ witnessing requirements.

a. Confirm whether existing sprinkler piping observed on site is to be reused or replaced in full.

The contractor needs to provide a complete fire protection system tested and accepted by the authority having jurisdiction.

b. Clarify whether a new fire service connection, backflow preventer, or riser is required.

Much of the system is already installed but not tested. Adjustments need to be made to allow for the installation of other trades. Contractor is responsible for a complete and accepted sprinkler system.

c. Confirm whether hydrostatic and acceptance testing will be required for any reused piping. Confirmed

d. Identify who provides coordination with the AHJ for system inspection and certification." Contractor

"Plumbing Systems (Division 22), Reference: Site Condition Survey Report (Attachment 9); Spec Sections 22 05 00, 22 08 00; Drawings P1.1–P1.3. The Site Condition Survey notes incomplete domestic water and sanitary rough-ins, missing fixtures, and no active service connection or water heating equipment. Portions of the plumbing piping appear installed but untested, with no verification of integrity or certification for reuse. Please confirm and clarify the following:

Plumbing Systems (Division 22) - See responses below.

a. Whether existing domestic water and sanitary piping may be reused, or if full replacement is required.

What is installed can be used to provide a complete system.

b. Whether pressure and leak testing will be required prior to reuse of any existing piping. Testing is required.

c. If any existing under-slab sanitary or vent piping is to remain in place.

Contractor can use underslab system if connected to site sanitary distribution and passes pressure testing. Contractor should scope sub slab drainage. Turn video over to COR for review.

d. Clarify fixture replacement extent—all new versus completion of partially installed fixtures. Contractor can use rough ins if contractors fixtures work with the existing installation.

e. Identify whether new domestic water heaters are required and confirm energy source. Water heater shall meet current code and contract documents.

f. Confirm whether water meter(s) and backflow preventer(s) are to be contractor- or Government-furnished."

If installed devices are tested and accepted by COR, they can be reused.

"HVAC Systems (Division 23), Reference: Mechanical Drawings MD1.1–MD1.2 (Mechanical Demolition), M1.1–M1.4 (Ductwork Plans), Site Condition Survey Report (Attachment 9), Spec Sections 23 05 93, 23 08 00 The demolition drawings show partial removal of ventilation fans, swamp coolers, and associated flexible tubing, but do not identify system limits or the extent of new versus existing mechanical infrastructure to be reused. The Site Condition Survey indicates mechanical equipment, ductwork, and controls are incomplete and not operational. Please confirm and clarify the following:

HVAC Systems (Division 23) - See responses below.

a. Existing Equipment & Reuse: Confirm whether any existing HVAC components (VRF/ERV units, ductwork, refrigerant piping, condensate drains, etc.) are intended for reuse, or if all systems shall be replaced new. If reuse is intended, identify which equipment, piping, and ductwork are to remain and which must be removed per MD1.1/MD1.2. Confirm whether refrigerant piping and drains previously installed can be re-used after pressure/leak testing, or if new linesets are required.

The installed hvac uses R-410a. A new A2L refrigerant system shall be installed which is the fan coil units, air handling units, branch selector boxes, refrigerant piping, outdoor units are to be new. Ductwork and ERV shall be adjusted to meet proper placement of equipment and to suit work as described in field report. the drainage piping shall be replaced with a material per plans and specs.

b. Controls / BAS: Confirm whether an existing DDC/BAS or control backbone exists on site or if a new system shall be furnished. Provide manufacturer and communication protocol (BACnet, LonWorks, proprietary, etc.) for controls integration. Identify who provides the controls commissioning and point-to-point verification (mechanical contractor or Government’s CxA).

The VRF system is to be controlled by the to be installed manufacturer control system.

c. Commissioning & Functional Testing: Identify which mechanical systems will require full commissioning versus verification only. Confirm the Government’s CxA will perform functional testing and provide commissioning documentation; contractor participation limited to start-up and assistance.

Cx shall be per plans and specs.

d. Warranty & Existing Installations: Clarify whether warranties for previously installed HVAC components (if any) are still valid or have expired. If expired, confirm whether equipment must be replaced to establish new warranties under this contract.

The installed equipment shall be removed.

e. Coordination & Documentation: The demolition drawings (MD1.1–MD1.2) do not clearly define limits of removal or existing equipment to remain. Confirm if new drawings or field direction will be provided prior to construction to verify demolition boundaries and protect any systems to remain.

Contractor is to complete what is required by the contract documents supplemented by this solicitation.

f. Confirm whether the mechanical contractor is responsible for furnishing all new control devices, network controllers, and programming, or if a separate controls subcontractor (Government-retained or provided under Division 25/28) will provide the system integration.

The VRF system is to be controlled by the to be installed manufacturer control system.

g. Testing and Balancing: Confirm whether Testing, Adjusting, and Balancing (TAB) of HVAC systems shall include any previously installed ductwork or equipment, or only newly installed systems under this contract. If existing components are to be reused, confirm whether pre- TAB verification or baseline testing is required prior to final TAB and commissioning."

Testing and balancing is for the complete system. Only existing ductwork and erv shall be reused. Contractor is responsible to test in accordance with contract documents.

"Electrical Systems (Division 26), Reference: Site Condition Survey Report (Attachment 9); Spec Sections 26 05 00, 26 08 00; Drawings E1.1–E4.1 The Site Condition Survey indicates panelboards, conduit, and feeders are installed but incomplete, unenergized, and untested.

Fixtures and devices are partially installed with missing terminations, labeling, and grounding.

The drawings do not define which existing electrical infrastructure is to remain, be re-pulled, or replaced. Please confirm and clarify the following:

"Electrical Systems (Division 26) - See responses below.

a. Whether existing conduit, feeders, and branch wiring may be reused or must be replaced in full.

As stated in the Site Condition Survey Report, the AE team's assessment of project conditions was based solely on visual observation during the site visit. The Project Team did not perform an exhaustive on-site inspection to check the quality or quantity of every aspect of the construction Work. Existing conduit, feeders, and branch wiring may be reused, however, Contractor must test conductors for resistance, shield-continuity and insulation resistance, as well as torque verification at terminations. Where wiring is defective, this will be considered an unforeseen condition. The contractor is responsible for describing the condition in detail and providing proposed alternatives to address it. The Contracting Officer (CO) will review the information and determine whether a contract modification is required.

b. If reuse is allowed, confirm required testing procedures (continuity, insulation resistance, and torque verification) prior to energization.

See response to question 27 above.

c. Confirm that this contractor is responsible for completing all terminations, labeling, and grounding to meet current code compliance prior to energization.

This Contractor is responsible for completing all wiring terminations, labeling, grounding and bonding, and testing to meet current code compliance prior to energization.

d. Clarify inclusion of generator and transfer switch testing in this contract. Testing of the generator and transfer switch must be performed under this Contract.

e. Confirm whether lighting fixtures and branch devices are to be replaced, reconnected, or completed from previously installed rough-in work.

Replace wiring devices with new. Retain existing track lights and complete the installation.

f. Provide direction for arc-flash and coordination study updates — confirm whether the electrical contractor shall perform and pay for a new or updated power system study (including short-circuit, coordination, and arc-flash labeling), or if this will be provided by the Government’s commissioning team."

The Electrical Contractor shall perform and pay for a new or updated power system study (including short-circuit, coordination, and arc-flash labeling). This will not be provided by the Government’s commissioning team.

"Communications Systems (Division 27) "Communications Systems (Division 27) - See responses below.

a. Confirm if new low-voltage cabling (Cat6, coax, fiber) is required.

New cabling is required. Refer to Specification Section 27 15 13 "Communications Copper Horizonatal Cabling" and sheet E6.4 of the Contract Documents.

b. Identify whether telecom racks and patch panels are contractor-furnished.

Contractor must furnish telecom/IT/AV equipment racks and patch panels. Refer to Specification Section 27 11 16 and sheet E6.4 of the Contract Documents.

c. Provide Government IT contact for service coordination." CO to provide Government IT point of contact "Electronic Safety and Security (Division 28 – Section 28 31 11) "Electronic Safety and Security (Division 28 – Section 28 31 11) - See responses below.

a. Confirm whether existing fire alarm panel, devices, and cabling are to be reused or replaced.

Fire alarm devices and fire alarm cabling that have been installed must be removed and replaced wit h new. Shop drawing product data for a FireLite Model MS-9600UDLS(E) fire alarm control panel was approved on October 14, 2022, however, the fire alarm control panel has not yet been installed. It is not known whether the fire alarm control panel had been procured and if so, where it is being stored and what condition it is in.

b. Provide manufacturer/model of any retained components.

As stated above, Shop drawing product data for a FireLite Model MS-9600UDLS(E) fire alarm control panel was approved on October 14, 2022, however, the fire alarm control panel has not yet been installed. It is not known whether the fire alarm control panel had been procured and if so, where it is being stored and what condition it is in.

c. Clarify if central station monitoring is required.

Yes. Central station monitoring is required by 2018 IBC, Section 901.6 which states, "Where required, fire protection systems shall be monitored by an approved supervising station in accordance with NFPA 72." Central monitoring is also required by the Contract Documents.

Refer to Specification Section 28 31 11, Articles 2.2.B.3, 2.2.E.3, and 2.2.F.2 and the fire alarm matrix on sheet E6.5, system outputs N, O, and P, all of which require alarm, supervisory, and trouble signals to be transmitted to a remote alarm receiving (supervising) station.

d. Confirm inclusion or exclusion of security/CCTV/access control. Security, CCTV, and Access Control are not included.

e. Confirm whether the electrical contractor shall furnish and install the complete addressable fire alarm system (panel, devices, wiring, programming, and acceptance testing), or if a specialty fire alarm vendor under Government contract will provide and commission the system."

The General Contractor shall furnish and install the complete addressable fire alarm system including but not limited to the fire alarm control panel, fire alarm initiating devices, notification appliances, and wiring, programming, and acceptance testing. It is not the intent of the Government to subcontract directly with a specialty fire alarm vendor to provide and commission the system. It is the General Contractor's responsibility to subcontract with a qualified Contractor to provide the system. Spec Section 28 31 11, Article 1.3.C.2 requires fire alarm shop drawings to be prepared by a NICET-certified Level IV fire-alarm technician or a Licensed Fire Protection Engineer. Article 1.8.A requires the fire alarm system to be installed under the supervision of persons meeting one or more of the following minimum qualifications as approved by the Authority Having Jurisdiction: 1. State or municipal certified/licensed fire alarm contractor;

2. Trained, certified, and qualified by fire alarm system manufacturer; 3. Certified by NICET as a fire-alarm Level III technician.

"Site Utilities (Division 33), Reference: Site Condition Survey Report (Attachment 9); Spec Sections 33 05 00, 33 10 00, 33 30 00; Civil Drawings C1.1–C4.1. The Site Condition Survey indicates no new underground utilities have been installed and that existing tie-in locations for water, sewer, and electrical services have not been verified. Subsurface conditions and backfill requirements are not defined in the drawings. Please confirm and clarify the following:

a. Whether the full Geotechnical Report (Appendix V) will be issued prior to excavation. See specification 01 11 00.

b. If not, provide allowable trench slopes, bedding materials, and backfill compaction requirements for installation of new utilities.

See specification 01 11 00.

c. Confirm whether the contractor is responsible for locating and exposing existing mains prior to connection and verifying tie-in elevations in the field.

Yes

d. Confirm whether existing utilities must remain active during construction and if temporary bypass piping or service connections are required."

Contractor is responsible to locate all utilities and service connections.

"Confirm that the Government retains and pays the Commissioning Authority (CxA) and that the contractor participates in startup, pre-functional testing, and documentation only.

Contractor is responsible for Commissioning all systems. See commissioning requirements in each specification section.

32 If the contractor must retain a CxA, specify qualifications and scope.

Contractor is responsible for Commissioning all systems. See commissioning requirements in each specification section.

Confirm that all functional testing for HVAC, electrical, and life-safety systems will be led by the Government’s CxA, with the contractor and its subcontractors providing startup data, attendance, and corrective actions only."

Contractor is responsible for Commissioning all systems. See commissioning requirements in each specification section.

"Coordination of Existing Systems Across Trades, Reference: Site Condition Survey Report (Attachment 9); Division 21–28 coordination; Drawings M1.1–M1.4, E1.1–E4.1. The Site Condition Survey identifies partially installed systems across mechanical, electrical, fire alarm, and communications trades. Several existing raceways, supports, and hangers appear installed but incomplete or unverified for reuse. The contract documents do not indicate whether these installations have been inspected, tested, or approved by the Government. Please confirm and clarify the following:

Coordination of Existing Systems Across Trades - See responses below.

a. Whether existing raceways, cable trays, supports, and hangers may be reused if visually inspected and accepted by the CxA or Contracting Officer.

Yes. Existing raceways, cable trays, supports, and hangers may be reused if visually inspected and accepted by the CxA or Contracting Officer.

b. If reuse is not permitted, confirm whether complete replacement of all existing supports and raceways is required.

See response to question 34.a. above.

c. Confirm whether the contractor is responsible for field verification, labeling, and removal of abandoned raceways prior to new work installation.

Yes, the contractor is responsible for field verification, labeling, and removal of abandoned raceways prior to new work installation.

d. Identify whether reuse acceptance criteria (structural condition, capacity, corrosion, alignment) will be provided or determined in the field by the Government’s CxA.

AE response: Reuse acceptance criteria (structural condition, capacity, corrosion, alignment) will be determined in the field by the Government.

e. Clarify whether any as-built documentation for existing raceways or hangers will be issued to assist in verifying reuse feasibility."

There are no As-builts available.

"Permanent Power Service / Utility Coordination, Reference: Site Condition Survey (Attachment 9); Drawings E1.1–E1.3; Spec Section 26 05 00 “Common Work Results for Electrical.” The Site Condition Survey indicates that the building currently has no active electrical service. Existing service equipment appears incomplete, and the drawings do not clearly indicate the status or location of the existing utility transformer or meter connection. Please confirm:

Permanent Power Service / Utility Coordination - See responses below.

a. Whether an existing utility transformer and service lateral remain in place and are available for reuse.

Transformer is installed. Contractor is responsible to coordinate with utility company.

b. If the existing transformer or service has been removed or de-energized, confirm whether the contractor is responsible for furnishing and coordinating a new utility transformer, metering, and service connection with the local utility provider.

Transformer is installed. Contractor is responsible to coordinate with utility company.

c. Confirm that the serving utility is Cumberland Electric Membership Corporation (CEMC), and clarify who is responsible for all coordination, applications, and associated costs (including any utility fees, permits, transformer set charges, or service connection costs) required to establish permanent power service.

Refer to sheet E6.2 of the Contract Documents which provides contact information for Cumberland Electric Membership Coproration. Contractor is responsible for all coordination, applications, and associated costs (including any utility fees, permits, transformer set charges, or service connection costs) required to establish permanent power service.

d. Confirm whether the Government or utility will provide and energize the permanent service after inspection and acceptance of contractor-installed gear.

The utility company will provide and energize the permanent service after inspection and acceptance of contractor-installed electrical equipment.

e. Please confirm that the following is the correct point of contact for utility coordination:

Cumberland Electric Membership Corporation (CEMC) – Stephen Fitzhugh, Dover District Engineer; 931-232-5153 ext. 660; sfitzhugh@cemc.org"

Refer to sheet E6.2 of the Contract Documents which provides contact information for Stephen Fithugh, with Cumberland Electric Membership Coproration (CEMC). The phone number provided on sheet E6.2 is 615-384-5566 (Extension 6602) is still Stephen's phone number, and the email address is still correct. Stephen has confirmed that he still has the Work Order open, that the transformer is in place and has been inspected, and that CEMC still has some wires to pull.

Confirm whether any interface or cross-communication between the BAS (Division 23) and Fire Alarm (Division 28) systems is required under this contract, and identify which trade is responsible for programming and testing that integration.

Any cross-connections will be identified in the contract documents.