B09_Amendment_0003_FODO_253278_RFI_03_Responses_0003.pdf

PDF 85 KB Posted

Attached to
FODO 253278 - Fort Donelson VC Rehabilitation
Solicitation number
140P2025R0054
Issued by

About this file

This document is a Request for Information (RFI) Amendment #003 for FODO 253278, providing detailed responses to 43 contractor questions about a federal construction project. Key details include requirements for project execution such as: contractors must issue contract-specific QA/QC and Safety Plans, the project is not tax exempt, and shop drawings are required. Critical scope items involve replacing mechanical systems (all refrigerant systems using R-410a refrigerant), removing and reinstalling roof systems with new tapered insulation, demolishing and reinstalling concrete equipment pads, and potential generator replacements based on Cummins service representative assessments. The project involves comprehensive system replacements across electrical, mechanical, and architectural domains, with specific guidance on what existing systems can remain and what must be replaced or reinstalled. A second site visit is scheduled for November 19, 2025, and contractors are advised to carefully review the Site Condition Survey Report for comprehensive project details.

View the file

Other files

File Type Posted
B09_SF30_Amendment_0005_140P2025R0054_0005.pdf PDF
Sol_140P2025R0054_Amd_0005.pdf PDF
B09_SF30_Amendment_0004_140P2025R0054_0004.pdf PDF
B09_Amendment_0004_FODO_253278_RFI_06_Responses_0004.pdf PDF
Sol_140P2025R0054_Amd_0004.pdf PDF
B09_Amendment_0004_FODO_253278_RFI_05_Responses_0004.pdf PDF
B09_SF30_Amendment_0003_140P2025R0054_0003.pdf PDF
B09_FODO253278_2nd_Site_Visit_Attendance_11192025_0003.pdf PDF
B09_Amendment_0003_FODO_253278_RFI_04_Responses_0003.pdf PDF
Sol_140P2025R0054_Amd_0003.pdf PDF
B09_Amendment_0002_FODO_253278_RFI_01_Responses_0002.pdf PDF
B09_SF30_Amendment_0002_140P2025R0054_0002.pdf PDF
Sol_140P2025R0054_Amd_0002.pdf PDF
B09_Amendment_0002_FODO_253278_RFI_02_Responses_0002.pdf PDF
B09_SF30_Amendment_0001_140P2025R0054_0001.pdf PDF
Sol_140P2025R0054_Amd_0001.pdf PDF
B09_PreBid_Signin_Sheet_Oct282025_0001.pdf PDF
B09_PreBid_Agenda_Oct282025_0001.pdf PDF
B08_Attach_9-_Site_Condition_Survey_Report.pdf PDF
B08_Attach_5_-_Past_Performance_Q_FODO_253278.docx DOCX document
B08_Attach_8_-_General_References_FODO_253278.doc DOC document
B08_Attach_6_-_SF-24_Bid_Bond.pdf PDF
Sol_140P2025R0054.pdf PDF
B08_Attach_2-Drawings_FODO_253278_Final.pdf PDF
B08_Attach_1-Specifications_FODO_253278_Final.pdf PDF
B08_Attach_4_-_Project_Experience_Q_FODO_253278.docx DOCX document
B08_Attach_7_SubKPlan_FODO_253278.docx DOCX document
B08_Attach_3-WD_TN20250170.pdf PDF
Show all 28

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

FODO 253278

Amendment 0003

RFI #003

Item Question Response

1 In executing this project, can one superintendent fulfill the supervision, safety, and QAQC roles?

The Superintendent can also act as the Safety Specialist. However, the Superintendent cannot act as the Quality Control Specialist. The Quality Control Specialist and Safety Specialist can be the same person.

2 Are contractors required to issue a contract specific QA/QC Plan? Yes 3 Are contractors required to issue a contract specific Safety Plan? Yes 4 Is this project tax exempt? No 5 Are shop drawings required? Yes. Please review each specification section for shop drawings requirements.

6 Is temporary power going to be required for outages? Temporary power is provided by NPS.

Can all previous RFI’s from both previous projects be provided? All Rfi’s that were asked, and all answer’s that were provided as a result.

No, these will not be provided.

Can all submittals from the two previous projects be provided? All submittals that were submitted, all rejected submittals with comments on rejection, all accepted submittals with comments, and all accepted submittals without comments.

No, these will not be provided.

9 Can all transmittals of information between the previous contractors and the client be provided? No, these will not be provided.

Can the schedule of values along with most recent accepted work completed from each previous contractors’ applications for payment be provided to show what was originally accepted and what hasn’t?

No, these will not be provided.

Can all shop drawings created by the previous subcontractors, manufacturers, and design firm be provided from the previous projects?

No, these will not be provided.

Can all redlined drawings created by the previous contractors, design firm, and or the client be provided?

No, these will not be provided.

Can the previous construction project schedules from the original contractor be provided in it’s most progressed version accepted by the client be provided?

No, these will not be provided.

The fire protection system seems to be about 90% complete. Is the fire protection scope only to finish the small remainder of the fire protection system that has not been completed along with minor deficiencies from the original installation?

Refer to the A/E assessment for fire protection additional comments.

It is our understanding that the existing fire protection system was tested and approved as installed?

a. Is this true No

b. If so, will the existing system need to be retested? Refer to the A/E assessment for fire protection additional comments.

c. Will the awarding contractor be responsible for warranting the entire fire protection system?

Yes

16 Will any ductwork outside of the main mechanical room need to be removed and reinstalled?

Ductwork noted for replacement in the report is to be replaced. All other ductwork is existing to remain.

The site survey conditions document states that all mechanical equipment and units are to be replaced. Can you confirm this scope is correct?

All refrigerant systems using R-410a refrigerant, including all fan coil units, all condensing units, and all refrigerant piping shall be replaced.

Concrete pads were poured in the mechanical room to support HVAC units and other equipment.

The scope states that these units are installed in the wrong place. Should the concrete pads be demoed or new pads poured in correct locations and leave poured pads as installed?

Demolish 7 inch housekeeping pads and install per design.

It was made known at the site visit that the client is in possession of the elevator to be installed.

The site survey conditions document states that the contractor should provide and install a new elevator.

a. Will the contractor provide a new elevator or install the one the client already has?

No, Elevator is stored in Thyssenkrup Elevators facility in Piperton, Tennessee. Contractor should coordinate elevator installation with Thyssenkrup. Jonathan Hord, Construction Superintendent M: 1-615-405-1629 jonathan.hord@tkelevator.com

b. Will the client be responsible for providing any missing parts or assemblies for the elevator if the client is providing the elevator?

No, Elevator is stored in Thyssenkrup Elevators facility in Piperton, Tennessee. Contractor should coordinate elevator installation with Thyssenkrup. Jonathan Hord, Construction Superintendent M: 1-615-405-1629 jonathan.hord@tkelevator.com c, If the client is providing the elevator then can the contractor assume that we do not have to warranty this item as we have no way of knowing if the manufacturer will warranty this elevator?

Contractor should coordinate all warranty requirements with Thyssenkrup.

The site survey conditions document and some of the mentions at the site visit suggest that all the TPO roofing is to be removed and replaced but only some of the tapered insulation is to be replaced and it is in varying degrees depending on which roof it is. For any contractor to warranty these roofs and to be able to replace these roofs without seeing what amount of insulation is to be removed, the contractors will have to assume removing all insulation and roofing system and replacing it in its entirety for all roofs. Can the scope for this item be adjusted for this?

Remove roof membrane, any cover board and insulation. Install new tapered insulation, cover board and tapered insulation. Roof slope shall be 1/8”/foot.

For any of the pipes that need to be replaced in different locations. Will the old pipe need to be removed or can it be capped and abandoned in place as long as it does not conflict with new systems?

The old (existing) pipes shall be removed where being replaced. Most of the existing pipes are being removed due to conflicts.

Please Confirm if we are required to provide new generators and ATS’s, or if the existing generator and ATS’s systems should be utilized as part of the project?

The Contractor shall contact the local Cummins Service Representative to coordinate an assessment of all existing Cummins units, including evaluation of their operational condition and verification of warranty status. Any unit determined to be out of warranty shall be replaced with new equipment. A written assessment report shall be submitted to the Contracting Officer (CO) for review and approval.

Please confirm new lighting fixtures are required or were they stored offsite, as no existing lighting fixtures were identified at the site.

The contractor has the construction drawings. The report indicates what is installed and what is not installed. The contractor should have enough information to determine what is still required to complete this scope of work. If items are not listed in the document, the contractor is to assume they need to complete 100% of that scope. If items in remaining work articles throughout the report are listed as installed, the contractor is to assume that scope is complete.

NPS, AE and Contracto will perform walkthrough to verify and accept existing conditions.

During the site visit, the 225A/3P circuit breaker was not found in the LDP1 panel.Kindly confirm if this breaker has been removed or if there has been any change in the design?

The 225A/3P circuit breaker is part of the design per the contract documents. This is the overcurrent protective device for the circuit that feeds Panel LM1. There has been no change in the design.

It has been observed that the LDP1 panel is installed as two separate panels at the site.Kindly confirm whether this configuration has been changed and not as per plans?

This configuration is not as intended on the contract documents. Panel LDP1 is a 600-Amp distribution panel and should be installed as a single panelboard.

There is a spec section 26 05 48 SEIMIC CONTROLS FOR ELECTRICAL SYSTEMS will this spec be required to be a part of this project?

Sheet S0.2 indicates that the Seismic Design Category (SDC) for the site is D. Section 26 05 48 Seismic Controls for Electrical Systems applies to this project.

On drawing E1.1 note #9 ask for a power demand meter and there are 7 of them shown on the drawings. We need more information, specs or a part number.

Information for power demand meters can be found under Specification Section 26 27 13

"ELECTRICITY METERING".

On drawing E0.4 site plan note #18 shows an emergency disconnect for the generator. Is this a separate item or part of the generator. Need more information.

The disconnect indicated by special note 18 on sheet E0.4 is specified to be provided with the generator. The disconnect is the "EPO" switch indicated on the one-line diagram on sheet E6.2.

This is the "remote manual-stop shutdown device" specified in Section 26 23 13.16, Article 2.6.E.3.y.

29 On drawing E0.4 site plan note #6 calls for a new 250-gallon LP tank. Who provides? Contractor provide new.

30 Can a full revision of the drawings be provided by the design firm to show current condition of the building across all trades and a list of all new scope to be performed so that all contractors are proposing on the same scope of work without making assumptions?

Refer to the A/E assessment report.

31 Can the client confirm that any work that is considered to already be done and that is not touched by the awarding contractor will not be warrantied by the awarding contractor?

Yes

32 It is our understanding contractors and subcontractors will not be required to warrant work that has been installed previously, accepted and allowed to remain. Please confirm.

Yes

In some instances, the Site Condition Survey Report mentions work which has been deemed unacceptable but does not in turn specify the action required of the contractor. Are contractors to assume all work deemed unacceptable is to be removed and reinstalled per the plans and specifications?

Yes

The Site Condition Survey Report, Page 2, para. 3 states, “The Project Team did not perform an exhaustive on-site inspection to check the quality or quantity of every aspect of the construction work and did not conduct destructive investigation. There may be defects that were not visually apparent and as such were not discovered or noted by our team but are required to complete the work.” It is our understanding contractors are to bid the work as outlined in the Report; work not identified in the Report will be treated as unforeseen conditions following award.

Yes

All work which has been installed and assumed by the Project Team to be in compliance with the contract documents are to be considered accepted and not part of the current project scope, excepting, accepted work which must be removed to address non-compliant items. Please confirm.

Yes

37 Can the RFIs and RFI Logs with the latest status from the previous contract be provided? NPS will provide RFI's and responses on DSC managed project.

Can all the submittals with attachments for vendor data, samples, and shop drawings from the previous contract be provided?

NPS will provide Submittals and comments on DSC managed project.

Can a submittal log with latest disposition for each submittal from the previous contract be provided?

NPS will provide Submittals and comments on DSC managed project.

Will the NPS be interfacing with Cummins concerning the generator and transfer gear as suggested in the Site Condition Survey Report or is the contractor to install a new generator and transfer switch?

The Contractor shall contact the local Cummins Service Representative to coordinate an assessment of all existing Cummins units, including evaluation of their operational condition and verification of warranty status. Any unit determined to be out of warranty shall be replaced with new equipment. A written assessment report shall be submitted to the Contracting Officer (CO) for review and approval.

Will the NPS take possession of the HVAC equipment that will be removed and replaced, or is the contractor to remove from site?

Remove from Site

41 Can a second site visit be granted for additional subcontractors to view the site? 2nd site visit is November 19, 2025 42 Can the RFI due date be extended by a period of 2 weeks? See Amendment 01 43 Can the bid due date be extended by a period of 4 weeks? See Amendment 01