B09_Q_and_A_Amendment_0002_PEFO_267538_0002.pdf

PDF 121 KB Posted

Attached to
Source Sought Notice Federal contract opportunity
Solicitation number
140P2024R0113
Issued by
Department of the Interior National Park Service National Office

About this file

This document is a set of questions and answers (Q&A) related to Amendment 0002 for the Request for Proposals (RFP) to Rehabilitate the Painted Desert Community Complex at Petrified Forest National Park, Solicitation Number 140P2024R0113.

The key details are: 1) The Management Approach section is limited to 5 pages, but signed letters of commitment from key subcontractors do not count against this limit. 2) The National Park Service (NPS) will provide the required archaeological monitoring personnel. 3) The contractor must provide a dedicated field office for the NPS Construction Management Representative. 4) The RFP allows contractors to use their own forms for the Small Business Subcontracting Plan, but fillable forms are also provided. 5) The Limit on Subcontracting form is only required for small business prime contractors, as this is a full and open competition. 6) Large businesses are only required to submit the Small Business Subcontracting Plan form.

View the file

Other files for this federal contract opportunity

Other files attached to Source Sought Notice, newest first.
File Type Posted
Sol_140P2024R0113_Amd_0004.pdf PDF
Sol_140P2024R0113_Amd_0003.pdf PDF
B09_Amendment_0003_responses_2024_10_30_0003.pdf PDF
B09_Amendment_0003_DOL-WD20240022_ApacheCty_10-04-2024_0003.pdf PDF
B09_Amendment_0003-Small_Business_Participation_Plan_Worksheet_0003.docx DOCX document
PEFO_267538_10-22-24_Prebid_2_Sign_In_Sheet_0002.pdf PDF
B08_Atch_7_Solit_PSP_SubKPlan_Vol2_0002.docx DOCX document
B08_Atch_5_Solit_PSP_Vol_I_Exp_REQD_0002.docx DOCX document
B08_Atch_5_Solit_PSP_Vol_I_PastPerf_REQD(1)_0002.docx DOCX document
PEFO_267538_Attendee_List_09-12-2024_0002.pdf PDF
Sol_140P2024R0113_Amd_0002.pdf PDF
Sol_140P2024R0113_Amd_0001.pdf PDF
B09_PEFO_267538_Amendment_0001_SITE_VISIT_No_2_0001.pdf PDF
B09_Amendment_0001_Q_A_PEFO_267538_0001.pdf PDF
B08_PEFO_267538_Atch_5_Solit_PSP_Vol_1.pdf PDF
B08_PEFO_267538_Atch_9_Price_Schedule.xlsx XLSX spreadsheet
Sol_140P2024R0113.pdf PDF
B08_PEFO_267538_Atch_1_Construction_Specifications_REV_003.pdf PDF
B08_PEFO_267538_Atch_6_Solit_PSP_Vol2.pdf PDF
B08_PEFO_267538_Atch_2_Construction_Drawings_REV_003_Part2.pdf PDF
B08_PEFO_267538_Atch_2_Construction_Drawings_REV_003_Part3.pdf PDF
B08_PEFO_267538_Atch_2_Construction_Drawings_REV_003_Part1.pdf PDF
B08_PEFO_267538_Atch_7_Rehab_PDCC_Product_File_Final.pdf PDF
B08_PEFO_267538_Atch_11-Closeout_O_M_Requirements.pdf PDF
B08_PEFO_267538_Solicitation_140P2024R0113.pdf PDF
B08_PEFO_267538_Atch_2_Construction_Drawings_REV_003_Part4.pdf PDF
B08_PEFO_267538_Atch_4__Construction_Contract_Administration.pdf PDF
B08_PEFO_267538_Atch_3_DOL_WD_AZ20240007.pdf PDF
B08_PEFO_267538_Atch_8_StatementOfStructuralTestsSpecialInspections.pdf PDF
B08_PEFO_267538_Atch_10_Submittal_List.pdf PDF
B08_PEFO_267538_Atch_12_Historic_Preservation_Report.pdf PDF
B08_PEFO_267538_Atch_13_Housing_Rehab_Design_Guidelines.pdf PDF
B08_PEFO_267538_Atch_14_CMU___Mortar_Testing_Report.pdf PDF
B08_PEFO_267538_Atch_15_Sanitary_Line_Inspection_Report.pdf PDF
Show all 34

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Rehabilitate Painted Desert Community Complex

Petrified Forest National Park

RFP 140P2024R0113 – PEFO 267538

Amendment 0002 – October 23, 2024

Q & A

1. Factor 3 – Management Approach – Page limitation required is five (5) pages, however, 1 page is for organization chart, plus each key subcontractor will have a signed letter of commitment, plus narratives are required in this section. Please confirm if the signed letter of commitment from key subcontractors are not included in the five (5) page count.

NPS Response: Letters of commitment do not count against 5 page limit for management approach.

2. Per spec 01 35-13.22 section 3.2 Archeological Investigation. Will NPS be providing this person, or will the contractor need to hire?

NPS Response: NPS shall provide Archaeological Monitoring personnel for duration of the

Construction Contract.

3. Per spec 01 50 00 section 2.2 Temporary Facilities (A) it references “Field Office’s” does the contractor need to provide a field office for NPS?

NPS Response: YES, PER 01 50 00, 2.2 Temporary Facilities, A. Field Offices - Contractor shall provide a dedicated field office for the On-Site, Full Time NPS Construction Management

Representative (CMR) for the duration of the Construction Contract period.

4. Per RFP Volume II- Business and Price Proposal section (G) Small Business Subcontracting Plan.

Can the contractor use its own generated forms that meets all requirements per the example in section (B08_Atch 7_Solit_PSP_SubkPlan_Vol2) Or can NPS provide forms that can be edited?

NPS Response: Fillable forms provided as an attachment to Amendment 0002.

5. Please confirm that the attached (B08_Atch 7_Solit_PSP_LmtOnSubcontracting_Vol2) form is to be only completed by a small business that is submitting as a prime contractor as this form is for small business set-asides.

NPS Response: It is confirmed,, the attached Limit on Subcontracting form (B08_Atch

7_Solit_PSP_LmtOnSubcontracting_Vol2) is to be completed only by small businesses submitting their proposal as a prime contractor. Please note, this solicitation is being issued as full and open competition.

6. Please confirm that for large business they are required to submit only the attached (B08_Atch

7_Solit_PSP_SubKPlan_Vol 2) form.

NPS Response: It is confirmed large businesses are required to submit only (B08_Atch 7

_Solit_PSP-SubKPlan_Vol2).

1 Atch: SITE VISIT No. 2 Agenda

File details come from the government source that posted it. Updated .