B09_CACO_227735_PreProposal_Conf_Slides_0002.pdf

PDF 2 MB Posted

Attached to
CACO 227735 - Reconstruct Mill Creek Water Control Federal contract opportunity
Solicitation number
140P2023R0112
Issued by
Department of the Interior National Park Service National Office

View the file

Other files for this federal contract opportunity

Other files attached to CACO 227735 - Reconstruct Mill Creek Water Control, newest first.
File Type Posted
Sol_140P2023R0112_Amd_0004.pdf PDF
B09_AM_004_Bidder_Q_and_A_0004.pdf PDF
B09_AM_004_Revised_Construction_Price_Schedule_20230719_0004.pdf PDF
B09_AM_004_Updated_7_10_23_CACO_MillCreek_100_CDPlans__0004.pdf PDF
B08_Attachment_13_Eastern_Box_Turtle_Protection_Plan_0003.pdf PDF
Sol_140P2023R0112_Amd_0003.pdf PDF
Sol_140P2023R0112_Amd_0002.pdf PDF
B09_CACO_227735_140P2023R0112_AM_002_0002.pdf PDF
B08_Attachment_05_CACO_227735_CD_FINAL_Design_Structural_Calculations_0001.pdf PDF
B08_Attachment_07__CD_FINAL_Permits_PAGES_1001_to_2002_0001.pdf PDF
B08_Attachment_10_Specifications_Exhibits_PAGES_1001_to_1500_0001.pdf PDF
B08_Attachment_10_Specifications_Exhibits_PAGES_1_to_1000_0001.pdf PDF
B08_Attachment_08_CD_FINAL_Permits_Draft_SWPPP_PAGES_1_to_800_0001.pdf PDF
B08_Attachment_06__CD_FINAL_Design_Supplemental_Hydraulic_Analysis_0001.pdf PDF
B08_Attachment_09_Statement_of_Structural_Tests_Special_Inspections_0001.pdf PDF
B08_Attachment_04_CACO_227735_CD_FINAL_Design_Report_Shoring_Analysis_20230602_0001.pdf PDF
B08_Attachment_02_CACO_227735_CD_FINAL_Specifications_0001.pdf PDF
B08_Attachment_08_CD_FINAL_Permits_Draft_SWPPP_PAGES_800_to_1662_0001.pdf PDF
B08_Attachment_03_CACO_227735_CD_FINAL_Design_Report_Foundation_Support__0001.pdf PDF
B08_Attachment_12_Proposal_Submission_Package_CACO_0001.docx DOCX document
B08_Attachment_10_Specifications_Exhibits_PAGES_1501_to_2068_0001.pdf PDF
B08_Attachment_07__CD_FINAL_Permits_PAGES_1_to_1000_0001.pdf PDF
Sol_140P2023R0112_Amd_0001.pdf PDF
B08_Attachment_01_CACO_227735_CD_FINAL_Drawings_0001.pdf PDF
B08_Attachment_11_DOL_Wage_Determination_MA20230008_0001.pdf PDF
B08_CACO_227735_140P2023R0112_0001.pdf PDF
B01_Synopsis_PreSolitNotice.pdf PDF
Show all 27

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Pre-proposal Conference/Site Visit June 28th, 2023

Reconstruct Mill Creek Water Control Structure

CACO 227735

Solicitation Number 140P2023R0112

Request for Proposals No.1443N5010070901

INTRODUCTIONS

• Tony Jasper, Contracting Officer, NPS Denver Service Center

• Tracey Cohen, Project Specialist, NPS Denver Service Center

• NPS CACO Staff

TODAY’S GOAL

• Provide offerors an opportunity to gain a better understanding of the project

• Provide potential offerors an opportunity for a thorough site investigation and to visit each building in order to better understand some of the logistical constraints of each building demo

• Questions are encouraged. Questions shall be asked in the open for the entire group to hear. Please no side-bar conversations. Questions that can not be answered today will be answered via a solicitation amendment.

PROJECT BACKGROUND

Reconstruction of the Mill Creek water control structure (WCS) is a key part of the 1100-acre Herring River Restoration Project (HRRP), a high-profile project with many federal, state, and local partners.

PROJECT BACKGROUND

Mill Creek Water Control Structure

The WCS will allow control of tidal exchange within the Mill Creek subbasin and thereby

• Prevent tidal flooding of nearby private properties

• Restore approximately 60 acres of Mill Creek salt marshes.

• Allow higher tides, and a greater degree of restoration, throughout the remainder of the 1100-acre project area.

PROJECT SCOPE

• Erosion & sediment control measures, including turbidity curtain

• Site clearing, vegetation removal

• Cofferdam construction

• Dewatering basin, diversion piping

• Gravel access road construction, including wetland crossing

(articulated concrete block matting)

• Water control structure construction

• sheet pile wall with concrete cap

• precast modular concrete block retaining wall

• 5 water control gates and power control system

• Tidal channel dredging – Offsite disposal

• Tidal channel dredging – Beneficial reuse*

• Reseeding disturbed areas

*In accordance with NPS soil handling protocol, testing

SITE CONDITIONS/CONSTRAINTS

Work in Tidal Environment

• Contractor required to install gauges and monitor tidal levels.

• Temporary water control measures needed

• cofferdams

• flow diversions

• sediment containment

REGULATORY REQUIREMENTS - WILDLIFE

Time of Year (TOY) Restrictions

U.S. Fish and Wildlife Service (Northern Long Eared Bat)

• No tree cutting from June 1 - July 31

• Limited tree removal (less than 10 acres) between April 1 -

October 31

• Identify and avoid any maternity roosts if cutting in the April

1 - October 31 window.

Time of Year (TOY) Restrictions

NOAA National Marine Fisheries Service

• Mill Creek is not designated as Essential Fish Habitat

(EFH), however impacts from Mill Creek construction must not affect conditions in the Herring River, which is designated as EFH.

• No in-water work, including the installation or removal of cofferdams, from February 1 through June 30 of any year.

• TOY restriction waived provided that adequate flow and overall passage conditions are maintained throughout the construction period

Time of Year (TOY) Restrictions

Massachusetts Division of Fisheries & Wildlife

• Alewife April 1 to June 15; Sept. 1 to Nov. 15

• Blueback Herring April 1 to June 30; Sept. 1 to Nov. 15

• American eel March 15 to June 30; Sept. 15 to Oct. 31

• White perch April 1 to June 15

• Work may occur within the diadromous fish TOY restriction periods provided that adequate flow and overall passage conditions are maintained throughout the construction period .

REGULATORY REQUIREMENTS

Environmental Permits

• Water Control Plan (Specification Section 35 01 30)

• Dredging/Dredge Material Handling Plan

• SWPPP

Invasive Species Control

Cleaning of Equipment:

• Equipment must be free of soil, seeds, vegetative matter, or other debris that could contain or hold seeds. Refer to plans and specs for requirements.

Inspections:

• Provide minimum of 5 days notice to CO prior to delivery of heavy equipment to allow for scheduling of inspections.OVIDE

AT LEAST FIVE (5) DAYS ADVANCE NOTICE TO THE

CONTRACTING OFFICER PRIOR TO DELIVERY OF ANY/ALL

HEAVY EQUIPMENT TO ALLOW FOR

• SCHEDULING OF INSPECTIONS.

Local Requirements

• Town of Wellfleet The Limit of Work at the entrance to the access road must remain tight as possible and remain fully intact during the entirety of the construction.

• Residential driveway near construction entrance must remain unobstructed throughout construction.

SOLICITATION OVERVIEW

• Period of Performance 540 calendar days after NTP.

• Total Small Business Set-Aside

• One Firm-Fixed-Price contract will be awarded

• Source selection will be made using Best Value/Tradeoff

Base CLINS (001-028):

Optional CLIN (029):

029: Pavement Micromilling and Overlay

CLIN STRUCTURE

1 Mobilization 2 General Requirements 3 Demobilization 4 Site Clearing and Demolition 5 Remnant Dike Excavation 6 Temporary Access and Erosion and Sedimentation Controls 7 Control of Water 8 Precast Modular Concrete Block Retaining Wall 9 Permanent Gravel Access Drive 10 Articulating Concrete Block Matting Access Drive 11 Steel Sheet Pile Wall 12 Steel Sheeting Concrete Cap 13 Cantilevered Steel Walkway 14 Earthwork 15 Steel-Backed Timber Guardrail 16 Water Control Structure 17 Soil-Filled Stone Armor Slope and Overtopping Protection 18 Sediment-Filled Stone Armor Channel Scour Protection 19 Trailer-Mounted Generator 20 Water Control Gates and Power/Control System 21 Water Control Gate System Testing and Commissioning 22 Site Restoration 23 Unsuitable Soil Structural Excavation 24 Crushed Stone for Structure Foundation 25 Tidal Channel Dredging - Off-Site Disposal 26 Tidal Channel Dredging - Benefical Reuse 27 Steel H-Piles 28 Additional Subgrade Reinforcement Stone

Key Solicitation Clauses

• H.3 – Option for Additional Services

– States that optional CLINs may be exercised unilaterally up to 90 days after contract award

• H.6 - Key Personnel

– PM, Superintendent, QC Manager and Safety Manager – no substitutions for 120 days)

• H.8 - Liquidated Damages ($1,482/day)

PROPOSAL INSTRUCTIONS

• Please read Section L thoroughly

• Email submissions to CO/CS on or before 5ET, July 21st

– Tony_Jasper@nps.gov, Tracy_Mcconnor@nps.gov, and CS_DSC_Proposal_Submission@nps.gov

• Make sure you verify receipt from NPS

• Pay attention to detailed page limitation requirements

PROPOSAL EVALUATION

Basis of Award

• Evaluation process is explained in Section M

• Source Selection using FAR 15 – Best Value/Tradeoff

• NPS can award to a higher priced offer if we determine it to be the overall best value to the Government

PROPOSAL EVALUATION (Technical Volume)

• Technical Volume must contain the following five sections pertaining to each evaluation factor:

– Factor 1 – Technical Approach

– Factor 2 – Project Experience

– Factor 3 – Key Personnel

– Factor 4 – Schedule

– Factor 5 – Past Performance

PROPOSAL EVALUATION

Volume 2 – Business and Price Proposal

• Signed SF1442

• Acknowledgement of Solicitation Amendments

• Completed Contract Price Schedule

• Section K: Reps & Certs

• General References

• Limitations on Subcontracting Worksheet

REMINDER

• Questions are due to the CO/CS by 14 days prior to bid deadline. It is the Offeror’s responsibility to take notes and submit questions in writing by the deadline.

• Submit questions only to Tracy_Mcconner@nps.gov and Tony_Jasper@nps.gov

• Direct all inquiries to contracting until contract award. All inquiries will be redirected to contracting.

• Email proposals on or before July 21st, 2023

• Solicitation and project documents are only changed with a formal amendment.

QUESTIONS?

Thank you for your time and interest in this project!