Pre-proposal Conference/Site Visit June 28th, 2023
Reconstruct Mill Creek Water Control Structure
CACO 227735
Solicitation Number 140P2023R0112
Request for Proposals No.1443N5010070901
INTRODUCTIONS
• Tony Jasper, Contracting Officer, NPS Denver Service Center
• Tracey Cohen, Project Specialist, NPS Denver Service Center
• NPS CACO Staff
TODAY’S GOAL
• Provide offerors an opportunity to gain a better understanding of the project
• Provide potential offerors an opportunity for a thorough site investigation and to visit each building in order to better understand some of the logistical constraints of each building demo
• Questions are encouraged. Questions shall be asked in the open for the entire group to hear. Please no side-bar conversations. Questions that can not be answered today will be answered via a solicitation amendment.
PROJECT BACKGROUND
Reconstruction of the Mill Creek water control structure (WCS) is a key part of the 1100-acre Herring River Restoration Project (HRRP), a high-profile project with many federal, state, and local partners.
PROJECT BACKGROUND
Mill Creek Water Control Structure
The WCS will allow control of tidal exchange within the Mill Creek subbasin and thereby
• Prevent tidal flooding of nearby private properties
• Restore approximately 60 acres of Mill Creek salt marshes.
• Allow higher tides, and a greater degree of restoration, throughout the remainder of the 1100-acre project area.
PROJECT SCOPE
• Erosion & sediment control measures, including turbidity curtain
• Site clearing, vegetation removal
• Cofferdam construction
• Dewatering basin, diversion piping
• Gravel access road construction, including wetland crossing
(articulated concrete block matting)
• Water control structure construction
• sheet pile wall with concrete cap
• precast modular concrete block retaining wall
• 5 water control gates and power control system
• Tidal channel dredging – Offsite disposal
• Tidal channel dredging – Beneficial reuse*
• Reseeding disturbed areas
*In accordance with NPS soil handling protocol, testing
SITE CONDITIONS/CONSTRAINTS
Work in Tidal Environment
• Contractor required to install gauges and monitor tidal levels.
• Temporary water control measures needed
• cofferdams
• flow diversions
• sediment containment
REGULATORY REQUIREMENTS - WILDLIFE
Time of Year (TOY) Restrictions
U.S. Fish and Wildlife Service (Northern Long Eared Bat)
• No tree cutting from June 1 - July 31
• Limited tree removal (less than 10 acres) between April 1 -
October 31
• Identify and avoid any maternity roosts if cutting in the April
1 - October 31 window.
Time of Year (TOY) Restrictions
NOAA National Marine Fisheries Service
• Mill Creek is not designated as Essential Fish Habitat
(EFH), however impacts from Mill Creek construction must not affect conditions in the Herring River, which is designated as EFH.
• No in-water work, including the installation or removal of cofferdams, from February 1 through June 30 of any year.
• TOY restriction waived provided that adequate flow and overall passage conditions are maintained throughout the construction period
Time of Year (TOY) Restrictions
Massachusetts Division of Fisheries & Wildlife
• Alewife April 1 to June 15; Sept. 1 to Nov. 15
• Blueback Herring April 1 to June 30; Sept. 1 to Nov. 15
• American eel March 15 to June 30; Sept. 15 to Oct. 31
• White perch April 1 to June 15
• Work may occur within the diadromous fish TOY restriction periods provided that adequate flow and overall passage conditions are maintained throughout the construction period .
REGULATORY REQUIREMENTS
Environmental Permits
• Water Control Plan (Specification Section 35 01 30)
• Dredging/Dredge Material Handling Plan
• SWPPP
Invasive Species Control
Cleaning of Equipment:
• Equipment must be free of soil, seeds, vegetative matter, or other debris that could contain or hold seeds. Refer to plans and specs for requirements.
Inspections:
• Provide minimum of 5 days notice to CO prior to delivery of heavy equipment to allow for scheduling of inspections.OVIDE
AT LEAST FIVE (5) DAYS ADVANCE NOTICE TO THE
CONTRACTING OFFICER PRIOR TO DELIVERY OF ANY/ALL
HEAVY EQUIPMENT TO ALLOW FOR
• SCHEDULING OF INSPECTIONS.
Local Requirements
• Town of Wellfleet The Limit of Work at the entrance to the access road must remain tight as possible and remain fully intact during the entirety of the construction.
• Residential driveway near construction entrance must remain unobstructed throughout construction.
SOLICITATION OVERVIEW
• Period of Performance 540 calendar days after NTP.
• Total Small Business Set-Aside
• One Firm-Fixed-Price contract will be awarded
• Source selection will be made using Best Value/Tradeoff
Base CLINS (001-028):
Optional CLIN (029):
029: Pavement Micromilling and Overlay
CLIN STRUCTURE
1 Mobilization 2 General Requirements 3 Demobilization 4 Site Clearing and Demolition 5 Remnant Dike Excavation 6 Temporary Access and Erosion and Sedimentation Controls 7 Control of Water 8 Precast Modular Concrete Block Retaining Wall 9 Permanent Gravel Access Drive 10 Articulating Concrete Block Matting Access Drive 11 Steel Sheet Pile Wall 12 Steel Sheeting Concrete Cap 13 Cantilevered Steel Walkway 14 Earthwork 15 Steel-Backed Timber Guardrail 16 Water Control Structure 17 Soil-Filled Stone Armor Slope and Overtopping Protection 18 Sediment-Filled Stone Armor Channel Scour Protection 19 Trailer-Mounted Generator 20 Water Control Gates and Power/Control System 21 Water Control Gate System Testing and Commissioning 22 Site Restoration 23 Unsuitable Soil Structural Excavation 24 Crushed Stone for Structure Foundation 25 Tidal Channel Dredging - Off-Site Disposal 26 Tidal Channel Dredging - Benefical Reuse 27 Steel H-Piles 28 Additional Subgrade Reinforcement Stone
Key Solicitation Clauses
• H.3 – Option for Additional Services
– States that optional CLINs may be exercised unilaterally up to 90 days after contract award
• H.6 - Key Personnel
– PM, Superintendent, QC Manager and Safety Manager – no substitutions for 120 days)
• H.8 - Liquidated Damages ($1,482/day)
PROPOSAL INSTRUCTIONS
• Please read Section L thoroughly
• Email submissions to CO/CS on or before 5ET, July 21st
– Tony_Jasper@nps.gov, Tracy_Mcconnor@nps.gov, and CS_DSC_Proposal_Submission@nps.gov
• Make sure you verify receipt from NPS
• Pay attention to detailed page limitation requirements
PROPOSAL EVALUATION
Basis of Award
• Evaluation process is explained in Section M
• Source Selection using FAR 15 – Best Value/Tradeoff
• NPS can award to a higher priced offer if we determine it to be the overall best value to the Government
PROPOSAL EVALUATION (Technical Volume)
• Technical Volume must contain the following five sections pertaining to each evaluation factor:
– Factor 1 – Technical Approach
– Factor 2 – Project Experience
– Factor 3 – Key Personnel
– Factor 4 – Schedule
– Factor 5 – Past Performance
PROPOSAL EVALUATION
Volume 2 – Business and Price Proposal
• Signed SF1442
• Acknowledgement of Solicitation Amendments
• Completed Contract Price Schedule
• Section K: Reps & Certs
• General References
• Limitations on Subcontracting Worksheet
REMINDER
• Questions are due to the CO/CS by 14 days prior to bid deadline. It is the Offeror’s responsibility to take notes and submit questions in writing by the deadline.
• Submit questions only to Tracy_Mcconner@nps.gov and Tony_Jasper@nps.gov
• Direct all inquiries to contracting until contract award. All inquiries will be redirected to contracting.
• Email proposals on or before July 21st, 2023
• Solicitation and project documents are only changed with a formal amendment.
QUESTIONS?
Thank you for your time and interest in this project!