B09_CHOH_245002_287711_Amd_6_-_013233_PhotoDocs_2023_04_03_0006.docx
DOCX document 32 KB Posted
- Attached to
- CHOH 245002 287711 -Locks and Wall
- Solicitation number
- 140P2022R0130
About this file
This document outlines requirements for photo documentation on a federal construction project. It requires the contractor to take digital photographs on a monthly basis to document construction progress, as well as before construction begins and during key milestones. The photos must be a minimum of 8 megapixels and 3200 by 2400 pixels, in JPEG format. The contractor must submit photos electronically within 7 days of being taken with detailed file names noting the date, time and location. At project completion, the contractor must provide all photos on a DVD in sRGB color format along with an index listing each photo's file name, date, time and description. This project involves repairs and construction of locks and walls at a National Park Service site, as indicated in the related federal contract opportunity for solicitation number 140P2022R0130.
View the file
Other files
Show 40 more
Latest 50 of 85 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
CHOH 245002 & 287711
SECTION 01 32 33 – PHOTO DOCUMENTATION
GENERAL
SUMMARY
Section includes administrative and procedural requirements for:
Existing condition images Periodic construction images See Section 01 77 00 "Closeout Procedures" for a complete listing of closeout documents.
See Section 01 79 00 "Demonstration and Training" for submitting videotapes of demonstration of equipment and training of National Park Service (NPS) personnel.
SUBMITTALS
Construction Images: Submit images electronically within 7 days of taking the image. Include:
Date, time and number (sequentially number all images) in filename.
Description of vantage point, indicating location, direction (by compass point), and elevation or story of construction.
Submit digital images exactly as originally recorded in digital camera, without alteration, or modifications using image-editing software.
Closeout: Submit complete set of digital image electronic files as a Project Record Document. Submit on Hard-drive or FTP as well as Digital Video Disc (DVD).
Provide index as separate file on Disc. List each image as a file name with number, date, and time. Include description and or vantage point image was taken.
Submit images that have the same aspect ratio as the sensor, un-cropped.
PRODUCTS
FORMAT REQUIREMENTS
Media: DVD-R Archival Gold.
Media Labels: Archival DVD labeling markers, archival labels, or direct print.
Images: Provide sRGB (standard Red Green Blue) color images in JPEG (Joint Photographic Experts Group) format. Minimum sensor size of 8 megapixels, and at image resolution of not less than 3200 by 2400, and 300 dpi (dots per inch).
EXECUTION
CONSTRUCTION IMAGES
General: Take digital images using the maximum range of depth of field, in-focus, to clearly show the Work. No blurry or out-of-focus areas accepted.
Maintain index with each set of Construction images and identify the number, date, time, and description for each.
Maintain one set of images accessible in field office at Project site available for reference.
Existing Condition Images: Before and when starting construction, take color digital images of Project site and surrounding properties, including existing items to remain during construction, from different vantage points.
Flag and construction limits before recording construction images.
Take a minimum of 10 separate images at each individual work area to show existing conditions adjacent to property before starting Work.
Take a minimum of 14 images of existing buildings either on or adjoining property to accurately record physical conditions at start of construction.
Include horizontal and vertical scales for reference.
Include photos of walls before vegetation is removed as well as after.
Periodic Construction Images: Take minimum of 25 color, digital images monthly, coinciding with cutoff date associated with each Application for Payment. Select vantage points to show status of construction and progress since last images were taken.
Additional Images: Contracting Officer may issue requests for additional images.
Three days advance, where feasible.
In emergency situations, take additional images within 24 hours of request.
Additional images include, but are not limited to:
Immediate follow-up when on-site events result in construction damage or losses.
Fabrication locations away from Project site.
Substantial Completion of a major phase or component of Work.
Extra record images at time of final acceptance.
Prior to anticipated heavy rainfall or flooding events.
END OF SECTION 01 32 33
| CHOH – 245002 & 287711 | 01 32 33 - 2 |
| 012721 | PHOTO DOCUMENTATION |