B09_QR_Tracker_-_WHIS_267466_-_140P2021R0170_Amd3_0003.xlsx

XLSX spreadsheet 21 KB Posted

Attached to
WHIS 267466 Replace Oak Bottom Consolidated Ranger
Solicitation number
140P2021R0170
Issued by

About this file

This document contains responses to questions from offerors on a federal solicitation for replacing the Oak Bottom Consolidated Ranger Operations Building. Key details include the National Park Service is soliciting offers to replace the operations building at Oak Bottom National Park. The project requires site work including concrete with a broom finish, connecting to an existing water main, and coordinating with PG&E for increased electrical service. Questions were answered clarifying concrete mix designs, finish types, and time extensions. The document confirmed the project is currently unfunded but intends to award in early fiscal year 2023, with an expectation the selected contractor would begin work within 30 days of award.

View the file

Other files

File Type Posted
B09_QR_Tracker_-_WHIS_267466_-_140P2021R0170_Amd5_0005.xlsx XLSX spreadsheet
Sol_140P2021R0170_Amd_0005.pdf PDF
B09_Waterline_Pressure_WHIS_Hydrant_Info_Amd4_0004.xlsx XLSX spreadsheet
Sol_140P2021R0170_Amd_0004.pdf PDF
B09_QR_Tracker_-_WHIS_267466_-_140P2021R0170_Amd4_0004.xlsx XLSX spreadsheet
Sol_140P2021R0170_Amd_0003.pdf PDF
Sol_140P2021R0170_Amd_0002.pdf PDF
B09_SignInSheet-PreProposalSiteVisit_Amd2_0002.pdf PDF
B09_TriFoldHandOut_-_WHIS_267466-140P2021R0170_Amd2_0002.pdf PDF
B09_PGE_Project_Contract_122103971_E_CONTRACTPK_Amd1_0001.pdf PDF
B09_PGE_35298209_ConDWGB_11x17_Amd1_0001.pdf PDF
B09_Attach_1_SpecificationsREV_220815_WHIS_267466_Amd1_0001.pdf PDF
Sol_140P2021R0170_Amd_0001.pdf PDF
B09_WHIS_267466_SolitRevPg5_ProvisionsClauses_-_Aug2022_Amd1_0001.pdf PDF
B09_Attach_2_DrawingsREV_220815_WHIS_267466_Amd1_0001.pdf PDF
B08_Attach_6__PastPerformanceQ.docx DOCX document
B08_Attach_2_Drawings_220809_WHIS_267466.pdf PDF
B08_WHIS_267466_Solit_ProvisionsClauses_-_Aug2022.pdf PDF
B08_Attach_8_GenRefs.doc DOC document
B08_Attach_7_ProjectExperienceQ.docx DOCX document
B08_Attach_1_Specifications_220809_WHIS_267466.pdf PDF
B08_Attach_4_Vaccination_Notification.pdf PDF
B08_Attach_5_Certification_of_Vaccination.pdf PDF
B08_Attach_3_CA20220007.pdf PDF
B08_Attach_9_SubcontractWorksheet.xlsx XLSX spreadsheet
Sol_140P2021R0170.pdf PDF
Show all 26

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Amendment 0003

AmendmentNumberQuestionResponse
Amd 3 - Issued 9/8/20221Refer to specification section 033300, paragraph 2.1.E calls for a slump of 4” max, however paragraph 2.2.G.1 allows for a high range water-reducing admixture (super plasticizer) which is typically used to bring concrete designed for a 4” slump up to a 6”-8” slump without adding additional water. Will a higher slump than 4” be allowed if a high range water-reducing admixture is used as long as the amount of water isn’t changed from the 4” slump mix design?Yes.
2Specification section 033315.3.7 provides requirements for an Exposed Aggregate finish on site concrete. The plans do not indicate any specific areas with exposed aggregate finish and the existing sidewalks and driveways at Oak Bottom have a standard broom finish. What areas (if any) of the exterior site concrete will require exposed aggregate finish or will all exterior concrete have a standard broom finish?The project only utilizes broom finish concrete. There is no exposed aggregate finish on site concrete.
3Specification section 033300.3.3.D requires concrete be cast within ninety minutes of adding water, will it be allowed to extend the ninety minute timeframe with the use of a water reducing-retarding admixture per ASTM C494 Type D as specified per 033300.2.2.G.3?Yes.
4Please provide a detail for the emergency generator pad/enclosure foundation.Question Received. Pending Response.
Amd 3 - Issued 9/8/20225We would like to request a Period of Performance (PoP) extension for generator procurement duration as they are currently 50 weeks out on lead time. Also, the duration for acquiring the FAA permit for proposed antenna will require at least 6 months once engineering and an antenna design has been submitted.If during Contract Performance a Time Extension is necessary, the Selected Awardee would need to submit a Request to the Government that includes an associated duration and Supplier documentation to support the Time Extension Request.

For the purposes of Proposing and Evaluation, Offerors shall identify any known challenges, potential impacts, proposed approach to mitigate or resolve these issues, as well as key considerations and/or constraints in their Written Narratives for Evaluation Factor # 3 - "Technical Approach and Schedule."

6When will the 8” water line project be completed for this work to be connected? We foresee the potential for pushing the Oakbottom Ranger Operations Building TCO potentially, if project is not on schedule.Presently the direction for the waterline project is that if the LE building facility is constructed, connect to existing main west of vale and if the LE facility is not constructed, they will stub out 6 LF from the valve. The waterline project is most likely going first, but Park/Project coordination is still needed for the waterline connection.
7(i) Is the parking lot at the park a place of refuge for neighboring residents during fire season and how could this impact the project?

(ii) Will water availability be impacted if/when people are at the park?

(iii) Same question for services available pertains to temp power available for the construction team. i. NO, the parking lot is not a place of refuge.

ii. NO, water use will not be impacted.

iii. NO, temp power will not be impacted.

8Would it be possible to use the existing parking lot to set the Owner trailer to prevent congestion of the site?Question Received. Pending Response.
Amd 3 - Issued 9/8/20229Has PG&E already completed the design for the added service? Is there a specific contact with PG&E that has been working on this already? If not, the PG&E design to increase of voltage can easily take 6 months, not including scheduling of any PG&E work onsite/installation of the new equipment, which could potentially impact the PoP duration of the project.Please see page 01 2700 - 1 CLIN No. 4 for all coordination and design effort the contractor will conduct with PG&E. PG&E's Design information (Construction Sketch) was issued with Amendment 001. PG&E contact information is listed on the PG&E Construction Sketch. Ed Normand with PG&E has been the primary point of contact.
10Please verify that the project is currently unfunded, but NPS is intending on awarding this project before the end of September 2022 and will require the successful contractor to begin work within 30 days.This project requirement is currently unfunded, with a high expectation that funding will be available. When and if funds become available, a Contract will be awarded at that time. The Government cannot guarantee that a Contract will be awarded prior to the end of Fiscal Year 2022 / September 30, 2022; however, anticipates an early 1st Quarter / Fiscal Year 2023 Contract award instead.
11Will the Gantt schedule be considered a picture and not count towards the 7-page limit for Factor 3 - Technical Approach and Schedule?The Gantt Chart Schedule will NOT count towards the 7 page limitation for Evaluation Factor #3. Only the Written Narratives for both the Technical Approach and Schedule, combined, count towards the 7 page limitation for this section of Volume I.
12Will a cover page and/or section divider pages count towards the page limits or is bookmarked PDF document preferred without divider pages?Cover Pages and/or Section Divider Pages will NOT count towards the page limitations for each Evaluation Factor. Bookmarked PDF Documents are acceptable as well.
13Refer to specification section 033300, paragraph 2.1.E calls for a slump of 4” max, however paragraph 2.2.G.1 allows for a high range water-reducing admixture (super plasticizer) which is typically used to bring concrete designed for a 4” slump up to a 6”-8” slump without adding additional water. Will a higher slump than 4” be allowed if a high range water-reducing admixture is used as long as the amount of water isn’t changed from the 4” slump mix design?Refer to Question/Response # 1.
14Specification section 033315.3.7 provides requirements for an Exposed Aggregate finish on site concrete. The plans do not indicate any specific areas with exposed aggregate finish and the existing sidewalks and driveways at Oak Bottom have a standard broom finish. What areas (if any) of the exterior site concrete will require exposed aggregate finish or will all exterior concrete have a standard broom finish?Refer to Question/Response # 2.
15Specification section 033300.3.3.D requires concrete be cast within ninety minutes of adding water, will it be allowed to extend the ninety minute timeframe with the use of a water reducing-retarding admixture per ASTM C494 Type D as specified per 033300.2.2.G.3?Refer to Question/Response # 3.
16Please provide a detail for the emergency generator pad/enclosure foundation.Question Received. Pending Responses.

*Refer to Question/Response # 4.

17Specification section 033300.2.1.A requires concrete contain between 30% and 50% fly ash. The local concrete supplier is not able to obtain fly, can slag cement be used in lieu of fly ash? See attached mill cert for reference.Question Received. Pending Response.
18Specification section 033300.2.1.A requires concrete contain between 30% and 50% fly ash. Mix designs with that high of fly ash (or slag cement) content are slow to come up to full strength and typically are given 56 days to achieve design strength rather than the standard 28 days. Can the 28 day strength required in section 0333000.2.1.B be changed to 56 day strength for mixes with high fly ash (or slag cement) content?Question Received. Pending Response.
19Specification section 033300.2.1.A requires concrete contain between 30% and 50% fly ash. The local concrete supplier is not able to obtain fly, can slag cement be used in lieu of fly ash? See attached mill cert for reference.Question Received. Pending Response.

*Refer to Question/Response #17.

20 Specification section 033300.2.1.A requires concrete contain between 30% and 50% fly ash. Mix designs with that high of fly ash (or slag cement) content are slow to come up to full strength and typically are given 56 days to achieve design strength rather than the standard 28 days. Can the 28 day strength required in section 0333000.2.1.B be changed to 56 day strength for mixes with high fly ash (or slag cement) content? Question Received. Pending Response.

*Refer to Question/Response #18.