B09_Amd_1_Specs_01_27_00_Definition_of_Contract_Line_Items_0001.pdf

PDF 87 KB Posted

Attached to
YOSE 312448 Rehabilitate the Crane Flat Campground
Solicitation number
140P2021R0098
Issued by

About this file

This document defines the contract line items for the rehabilitation of the Crane Flat Campground located in Yosemite National Park. The contract includes five line items: mobilization and demobilization; campground and campsite improvements; pulverization of existing asphalt pavement; new hot mix asphalt pavement; and rock excavation. Mobilization and demobilization may not exceed 10% of the total contract price. Campground and campsite improvements include tasks such as temporary erosion control, site grading, culvert installation, furnishing of campsite amenities, concrete and earthen trail construction, and signage installation. Measurement and payment methods are defined for pulverized asphalt, new asphalt pavement, and rock excavation. The related federal contract opportunity is solicitation number 140P2021R0098 issued by the National Park Service for the rehabilitation of the Crane Flat Campground to enhance the visitor experience.

View the file

Other files

File Type Posted
B09_Amd_4_Crane_Flat_Campground_-_Loop_E_Improvement_Plans-Signed_-_Revision_0004.pdf PDF
B09_Amd_4_Crane_Flat_Campground_-_Loop_B_Revised_0004.pdf PDF
B09_Amd_4_Q_and_A_0004.pdf PDF
B09_Amd_4_Crane_Flat_Campground_-_Loop_C_Revised_0004.pdf PDF
Sol_140P2021R0098_Amd_0004.pdf PDF
B09_Amd_4_CD_Changes_0004.xlsx XLSX spreadsheet
B09_Amd_4_Crane_Flat_Campground_-_Loop_A_Improvement_Plans-Signed_-_Revision_0004.pdf PDF
B09_Amd_4_04_41_00_Dry_Stacked_Stone_Walls_-_REVISED_0004.pdf PDF
B09_Amd_4_Crane_Flat_Campground_-_Loop_D_Revised_0004.pdf PDF
Sol_140P2021R0098_Amd_0003.pdf PDF
B09_Amd_2_Drawings_Loop_E_8-10-2021_0002.pdf PDF
B09_Amd_2_Drawings_Loop_A_8-10-2021_0002.pdf PDF
B09_Amd_2_Q_and_A_0002.pdf PDF
Sol_140P2021R0098_Amd_0002.pdf PDF
B09_Amd_1_YOSE_312448_CONTRACT_PRICE_SCHEDULE_0001.xlsx XLSX spreadsheet
B09_Amd_1_Geotech_Investigation_Crane_Flat_Water_System_0001.pdf PDF
B09_Amd_1_Specs_04_41_00_Dry_Stacked_Stone_Walls_8-3-2021_0001.pdf PDF
B09_Amd_1_Sign-In_Sheet_0001.xlsx XLSX spreadsheet
B09_Amd_1_Yosemite_Crane_Flat_Soil_Condition_Assessment_Report_Technicon_0001.pdf PDF
Sol_140P2021R0098_Amd_0001.pdf PDF
B09_Amd_1_Q_and_A_0001.pdf PDF
B09_Amd_1_Specs_31_37_10_Riprap_8-3-2021_0001.pdf PDF
B09_Amd_1_Site_Visit_Tri_Fold_YOSE_Crane_Flat_0001.docx DOCX document
B08_Forms_for_use_in_proposalsubmission.pdf PDF
A06_Crane_Flat_Campground_-_Loop_E_Improvement_Plans-Signed.pdf PDF
Sol_140P2021R0098.pdf PDF
B03_Wage_Determination_CA20200018_07162021.pdf PDF
A06_Crane_Flat_SWPPP_July_2021.pdf PDF
A06_Crane_Flat_Campground_-_Loop_A_Improvement_Plans-Signed.pdf PDF
A06_Crane_Flat_Campground_-_LOOP_D_Improvement_Plans.pdf PDF
B08_Solicit_140P2021R0098.pdf PDF
A06_Crane_Flat_Campground_-_LOOP_B_Improvement_Plans.pdf PDF
A16_JOFOC_BrandName_YOSE_312448.pdf PDF
A06_Crane_Flat_Campground_-_LOOP_C_Improvement_Plans.pdf PDF
A06_CRANE_FLAT_FINAL_CONSTRUCTION_SPECS_REV_0_7-1-2021.pdf PDF
Show all 35

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

REHABILITATE CRANE FLAT CAMPGROUND FINAL CONSTRUCTION DOCUMENTS

August 2021

YOSE – 312448 01 27 00 - 1

DEFINITION OF CONTRACT LINE ITEMS

SECTION 01 27 00 – DEFINITION OF CONTRACT LINE ITEMS

PART 1 - GENERAL

1.1 SUMMARY

A. The intent of this section is to explain, in general, what is and what is not included in a contract line item, and the limits or cut-off points where one item ends, and another begins.

B. If no contract line item exists for a portion of the work, include the costs in a related item.

C. The pricing submitted, and payment made, for each item listed shall constitute full compensation for furnishing all labor, materials, and equipment, and all associated contractor quality control, survey lay-out, environmental protection, safety requirements, submittals, testing, reports, demolition/deconstruction, and legal disposal of removed items, and for performing all work as required and specified by the contract documents.

PART 2 - PRODUCTS (Not Used)

PART 3 - EXECUTION

3.1 LIST OF CONTRACT LINE ITEMS

A. Contract Line Item No. 1: Mobilization and Demobilization

1. This item includes full compensation for all labor, materials, tools, equipment, and incidentals making up the cost of mobilization, move-in, move-out, all necessary bonds, insurance, permits, licenses, fees, and developing pre-mobilization submittals as required for the work. This item also includes demobilization, including the removal of all equipment, supplies, personnel, and incidentals from the project at the end of construction, and the completion of all project close-out submittals.

2. Payment shall not exceed 10% of the total contract price. Payment for mobilization shall be made with the first progress payment and shall not exceed 80 percent of the bid item amount. Payment for demobilization shall be made with the last progress payment and shall not be less than 20 percent of the bid item amount.

B. Contract Line Item No. 2: Campground and Campsite Improvements

1. This item includes full compensation for all labor, materials, tools, equipment, and incidentals for campground and campsite improvements as described in the contract drawings and specifications, and not otherwise listed in other contract line items. This work includes, but is not limited to: 1) temporary erosion control and SWPPP implementation, 2) clearing and grubbing, 3) grading, fine grading of campsites, excavation, earthwork, 4) culvert installation, 5) campsite furnishings (bear boxes, fire rings, and picnic tables), 6) concrete trails, pads, sidewalks, and steps, 7) earthen trails

YOSE – 312448 01 27 00 - 2

with timber steps, 8) rock-lined ditches, 9) stacked rock retaining walls, 10) boulder, log, and post barriers, 11) signage, striping, and snow post holders, 12) wheel stops, 13) water spigots, 14) dumpster pads, and 15) adjusting manhole rings, and valve boxes, and installing concrete collars.

2. Payment will be made at the contract lump sum price based on agreed percentage of work successfully completed in accordance with the project drawings and specifications.

C. Contract Line Item No. 3: Pulverize Existing Asphalt Pavement

1. This item includes full compensation for all labor, materials, tools, equipment, and incidentals for full depth pulverization of existing asphalt cement pavement section including existing base materials, in preparation for re-use as a base material for paving operations.

2. Measurement for payment will be based on the agreed square yards of Existing Asphalt

Pavement Pulverized successfully completed in accordance with the project drawings and specifications.

3. Quantities shown are estimated, and may vary in accordance with the “Variation in

Estimated Quantity” clause.

D. Contract Line Item No. 4: Hot Mix Asphalt Pavement

1. This item includes full compensation for all materials, equipment, and labor for completing the AC paving section as shown on the drawings. The work includes but is not limited to: 1) saw-cutting and preparing edge of existing AC pavement, 2) final shaping and preparation of the pulverized AC pavement, 3) compaction, 4) furnishing, installation, and testing of supplemental aggregate base (AB) materials, including shoulders, 5) tack coat, and 6) furnishing, installation, and testing of Mot Mix Asphalt

Pavement to the lines and grades as shown on the drawings and as required by the specifications.

2. Measurement for payment will be based on the agreed square yards of Hot Mix Asphalt

Pavement successfully completed in accordance with the project drawings and specifications.

3. The Contractor shall install Hot Mix Asphalt Pavement to the limits designated on the contract drawings, and will not be paid for pavement installed in excess of that shown in the project drawings, unless previously approved by the CO.

4. Quantities shown are estimated, and may vary in accordance with the “Variation in

Estimated Quantity” clause.

E. Contract Line Item No. 5: Rock Excavation

1. This item consists of providing all labor, material, and equipment for removing rock, as defined in Section 31 11 01.

2. Measurement will be as described in Section 31 11 01.

YOSE – 312448 01 27 00 - 3

3. Payment will be made at the contract unit price per cubic yard removed. This Contract Line

Item may not be utilized, depending on actual field conditions. The full bid quantity may not be utilized.

END OF SECTION

YOSE – 312448 01 27 00 - 4

THIS PAGE INTENTIONALLY LEFT BLANK

PART 1 - GENERAL
1.1 SUMMARY
A. The intent of this section is to explain, in general, what is and what is not included in a contract line item, and the limits or cut-off points where one item ends, and another begins.
B. If no contract line item exists for a portion of the work, include the costs in a related item.
C. The pricing submitted, and payment made, for each item listed shall constitute full compensation for furnishing all labor, materials, and equipment, and all associated contractor quality control, survey lay-out, environmental protection, safety req...
PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION
3.1 LIST OF CONTRACT LINE ITEMS
A. Contract Line Item No. 1: Mobilization and Demobilization
1. This item includes full compensation for all labor, materials, tools, equipment, and incidentals making up the cost of mobilization, move-in, move-out, all necessary bonds, insurance, permits, licenses, fees, and developing pre-mobilization submitt...
2. Payment shall not exceed 10% of the total contract price. Payment for mobilization shall be made with the first progress payment and shall not exceed 80 percent of the bid item amount. Payment for demobilization shall be made with the last progre...
B. Contract Line Item No. 2: Campground and Campsite Improvements
1. This item includes full compensation for all labor, materials, tools, equipment, and incidentals for campground and campsite improvements as described in the contract drawings and specifications, and not otherwise listed in other contract line item...
2. Payment will be made at the contract lump sum price based on agreed percentage of work successfully completed in accordance with the project drawings and specifications.
C. Contract Line Item No. 3: Pulverize Existing Asphalt Pavement
1. This item includes full compensation for all labor, materials, tools, equipment, and incidentals for full depth pulverization of existing asphalt cement pavement section including existing base materials, in preparation for re-use as a base materia...
2. Measurement for payment will be based on the agreed square yards of Existing Asphalt Pavement Pulverized successfully completed in accordance with the project drawings and specifications.
3. Quantities shown are estimated, and may vary in accordance with the “Variation in Estimated Quantity” clause.
D. Contract Line Item No. 4: Hot Mix Asphalt Pavement
1. This item includes full compensation for all materials, equipment, and labor for completing the AC paving section as shown on the drawings. The work includes but is not limited to: 1) saw-cutting and preparing edge of existing AC pavement, 2) fina...
2. Measurement for payment will be based on the agreed square yards of Hot Mix Asphalt Pavement successfully completed in accordance with the project drawings and specifications.
3. The Contractor shall install Hot Mix Asphalt Pavement to the limits designated on the contract drawings, and will not be paid for pavement installed in excess of that shown in the project drawings, unless previously approved by the CO.
4. Quantities shown are estimated, and may vary in accordance with the “Variation in Estimated Quantity” clause.
E. Contract Line Item No. 5: Rock Excavation
1. This item consists of providing all labor, material, and equipment for removing rock, as defined in Section 31 11 01.
2. Measurement will be as described in Section 31 11 01.
3. Payment will be made at the contract unit price per cubic yard removed. This Contract Line Item may not be utilized, depending on actual field conditions. The full bid quantity may not be utilized.