B08_SF1442_UPDATED_Attachment_10_Solit_PSP_Vol_II_PriceSched.xlsx
XLSX spreadsheet 24 KB Posted
- Solicitation number
- 140P2019R0080
About this file
Updated Attachment 10 Contract Price Schedule
View the file
Other files
Show all 24
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Price Schedule Template
| Contract Price Schedule Template | |||||
| National Park Service (NPS) - Denver Service Center (DSC) | 4/25-18 | |||||
| Solicitation Number: 140P2019R0080 | |||||
| PARK - PMIS (Project Management Information System): SHEN 151064 | |||||
| Developed Area: Shenandoah National Park | |||||
| Project Title: Construction of Water Wells, Pipelines and Treatment Facilities | |||||
| Notice: Offerors are required to submit, a minimum, an offer that conforms to the solicitation documents with pricing for Base line items and all | |||||
| option line items. Failure to do so may render the proposal unacceptable. On lump-sum line items, provide the total price only. For all unit-priced | |||||
| line items, provide the unit price and the extended total price. If no specific line item exists for a portion of the work, include the costs in a related | |||||
| item. In case of error in calculation of extended prices, the unit price governs. In case of error in summation, the total of the corrected amounts | |||||
| govern. Round totals and extended prices to whole dollars. Refer to solicitation section “H” for additional information regarding contract options | |||||
| Contract Line Item Number (CLIN) | Contract Line Item (CLI) Title | Quantity | Unit of Measure | Unit Price | Total Price |
| 1 | Skyland and Big Meadows Areas Improvements | 1 | Lump Sum | $0.00 | |
| TOTAL BASE PRICE (Contract Line Item Number 1) --------------------------------------------------------------------------------- | $0.00 | ||||
| 000A | OPTION A, Big Meadows Pipeline | 1 | Lump Sum | $0.00 | |
| 000B | OPTION B, Skyland Reservoirs Rehabilitation | 1 | Lump Sum | $0.00 | |
| 000C | OPTION C, Big Meadows Reservoirs Rehabilitation | 1 | Lump Sum | $0.00 | |
| 000D | OPTION D, Skyland Reservoirs Structural Repairs | 1 | Lump Sum | $0.00 | |
| 000E | OPTION E, Skyland Reservoirs Structural Repairs | 1 | Lump Sum | $0.00 | |
| 000F | OPTION F, Big Meadows Centralized Treatment Building Emergency | 1 | Lump Sum | $0.00 | |
| 000G | OPTION G, Skyland Centralized Treatement Building Emergency Generator | 1 | Lump Sum | $0.00 | |
| TOTAL PRICE FOR ALL OPTIONS (Contract Line Item Number 000A through 000G) ----------------------------------------------------------- | $0.00 | ||||
| TOTAL PROPOSED PRICE - BASE PLUS ALL OPTIONS (Contract Line Item Number 1 through 000G) -------------------------- | $0.00 | ||||
| All measurement and payment information is included in Division 01 Specifications Section 01 27 00 Definition of Contract Line Items. |
File details come from the government source that posted it.