4.1 EVER 235866 Specifications Manual
National Park Service
EVERGLADES NATIONAL PARK
Renovate Flamingo Visitor Center
Homestead, Florida
Division 01, Divisions 02‐49 Specifications
Final Construction Documents
May 31, 2019
Prepared by:
Croft & Associates, PC
3400 Blue Springs Road Kennesaw, GA 30144
DIVISION SECTION TITLE PAGES
SPECIFICATIONS GROUP
FACILITY CONSTRUCTION SUBGROUP
DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS
00 01 07 SEALS PAGE
DIVISION 01 - GENERAL REQUIREMENTS
01 11 00 SUMMARY OF WORK
01 26 01 CONTRACT MODIFICATION PROCEDURES
01 27 00 DEFINITION OF CONTRACT LINE ITEMS
01 31 00 PROJECT MANAGEMENT & COORDINATION
01 32 16 CONSTRUCTION SCHEDULE
01 32 33 PHOTOGRAPHIC DOCUMENTATION
01 33 23 SUBMITTAL PROCEDURES
01 35 23 SAFETY REQUIREMENTS
01 35 91 HISTORIC PRESERVATION TREATMENT PROCEDURES
01 40 00 QUALITY REQUIREMENTS
01 42 00 REFERENCE STANDARDS
01 50 00 TEMPORARY FACILITIES AND CONTROLS
01 57 19.11 INDOOR AIR QUALITY MANAGEMENT
01 57 19.12 NOISE & ACOUSTICS MANAGEMENT
01 57 23 TEMPORARY STORM WATER POLLUTION PREVENTION
01 67 00 PRODUCT REQUIREMENTS
01 73 29 CUTTING AND PATCHING
01 73 40 EXECUTION
01 74 19 CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL
01 77 00 CLOSEOUT PROCEDURES
01 78 23 OPERATION AND MAINTENANCE DATA
01 79 00 DEMOSTRATION AND TRAINING
01 81 13 SUSTAINABLE DESIGN REQUIREMENTS
01 91 14 TOTAL BUILDING COMMISSIONING
DIVISION 02 EXISTING CONDITIONS
02 41 19 SELECTIVE DEMOLITION
DIVISION 03 - CONCRETE
03 01 00 REHABILITATION OF CONCRETE
03 30 00 CAST-IN-PLACE CONCRETE
DIVISION 04 - MASONRY
04 22 00 CONCRETE UNIT MASONRY
DIVISION 05 - METALS
05 12 00 STRUCTURAL STEEL
05 21 00 STEEL JOISTS
05 31 00 STEEL DECK
05 40 00 COLD-FORMED METAL FRAMING
05 50 00 METAL FABRICATIONS
05 51 00 METAL STAIRS
05 52 13 PIPE AND TUBE RAILINGS
05 73 00 ORNAMENTAL HANDRAILS AND RAILINGS
DIVISION 06 - WOOD, PLASTICS, AND COMPOSITES
06 10 53 MISCELLANEOUS ROUGH CARPENTRY
06 20 23 INTERIOR FINISH CARPENTRY
06 40 23 INTERIOR ARCHITECTURAL WOODWORK
06 41 16 PLASTIC-LAMINATE-CLAD ARCHITECTURAL CABINETS
06 42 14 STILE AND RAIL WOOD PANELING
DIVISION 07 - THERMAL AND MOISTURE PROTECTION
07 21 00 THERMAL INSULATION
07 26 00 VAPOR RETARDERS
07 42 33 PHENOLIC WALL PANELS
07 52 16 STYRENE-BUTADIENE-STYRENE (SBS) MODIFIED BITUMOUS
MEMBRANE ROOFING
07 71 29 MANUFACTURED ROOF EXPANSION JOINTS
07 72 00 ROOF ACCESSORIES
07 84 13 PENETRATION FIRESTOPPING
07 91 00 PREFORMED JOINT SEALS
07 92 00 JOINT SEALANTS
07 92 19 ACOUSTICAL JOINT SEALANTS
DIVISION 08 - OPENINGS
08 11 13 HOLLOW METAL DOORS AND FRAMES
08 14 16 FLUSH WOOD DOORS
08 16 13 FIBERGLASS DOORS AND FRAMES
08 41 13 ALUMINUM-FRAMED ENTRANCES AND STOREFRONTS
08 42 29.33 SWINGING AUTOMATIC ENTRANCES
08 51 13 ALUMINUM WINDOWS
08 71 00 DOOR HARDWARE
08 80 00 GLAZING
08 88 13 FIRE-RATED GLAZING
DIVISION 09 - FINISHES
09 22 16 NON-STRUCTURAL METAL FRAMING
09 24 00 CEMENT PLASTERING
09 29 00 GYPSUM BOARD
09 30 13 CERAMIC TILING
09 30 23 GLASS MOSAIC TILING
09 51 13 ACOUSTICAL PANEL CEILINGS
09 51 33 ACOUSTICAL METAL PAN CEILINGS
09 65 13 RESILIENT BASE AND ACCESSORIES
09 65 16 RESILIENT SHEET FLOORING
09 65 19 RESILIENT TILE FLOORING
09 66 23 RESINOUS MATRIX TERRAZZO FLOORING
09 67 23 RESINOUS FLOORING
09 68 13 TILE CARPETING
09 84 36 SOUND-ABSORBING CEILING UNITS
09 91 13 EXTERIOR PAINTING
09 91 23 INTERIOR PAINTING
09 93 00 STAINING AND TRANSPARENT FINISHING
09 96 00 HIGH-PERFORMANCE COATINGS
09 96 53 ELASTOMERIC COATINGS
DIVISION 10 - SPECIALTIES
10 14 19 DIMENSIONAL LETTER SIGNAGE
10 14 23.16 ROOM-IDENTIFICATION PANEL SIGNAGE
10 21 13.17 PHENOLIC-CORE TOILET COMPARTMENTS
10 22 39.13 FOLDING GLASS-PANEL PARTITIONS
10 28 00 TOILET, BATH, AND LAUNDRY ACCESSORIES
10 44 13 FIRE PROTECTION CABINETS
10 44 16 FIRE EXTINGUISHERS
DIVISION 12 - FURNISHINGS
12 24 13 ROLLER WINDOW SHADES
12 36 23.13 PLASTIC-LAMINATE-CLAD COUNTERTOPS
12 36 61.16 SOLID SURFACING COUNTERTOPS
12 36 61.19 QUARTZ AGGLOMERATE COUNTERTOPS
12 40 00 FURNISHINGS AND ACCESSORIES
12 48 13 ENTRANCE FLOOR MATS AND FRAMES
DIVISION 14 - CONVEYING EQUIPMENT
14 21 23.16 MACHINE-ROOM-LESS ELECTRIC TRACTION PASSENGER ELEVATORS
FACILITY SERVICES SUBGROUP
DIVISION 21 - FIRE SUPPRESSION
21 13 13 WET-PIPE SPRINKLER SYSTEMS
DIVISION 22 - PLUMBING
22 00 00 PLUMBING GENERAL
22 05 17 SLEEVES AND SLEEVE SEALS FOR PLUMBING PIPING
22 05 18 ESCUTCHEONS FOR PLUMBING PIPING
22 05 29 HANGERS AND SUPPORTS FOR PLUMBING PIPING AND EQUIPMENT
22 05 53 IDENTIFICATION FOR PLUMBING PIPING AND EQUIPMENT
22 07 19 PLUMBING PIPING INSULATION
22 11 16 DOMESTIC WATER PIPING
22 11 19 DOMESTIC WATER PIPING SPECIALTIES
22 13 16 SANITARY WASTE AND VENT PIPING
22 13 19 SANTIARY WASTE PIPING SPECIALTIES
22 13 29 SANITARY SEWERAGE PUMPS
22 33 00 ELECTRIC WATER HEATERS
22 42 13.13 COMMERCIAL WATER CLOSETS
22 42 13.16 COMMERCIAL URINALS
22 42 16.13 COMMERCIAL LAVATORIES
22 42 16.16 COMMERCIAL SINKS
22 42 23 COMMERCIAL SHOWERS
22 47 13 DRINKING FOUNTAINS
DIVISION 23 - HEATING, VENTILATING, AND AIR CONDITIONING (HVAC)
23 00 00 MECHANICAL GENERAL
23 05 17 SLEEVES AND SLEEVE SEALS FOR HVAC PIPING
23 05 18 ESCUTCHEONS FOR HVAC PIPING
23 05 29 HANGERS AND SUPPORTS FOR HVAC PIPING AND EQUIPMENT
23 05 53 IDENTIFICATION FOR HVAC PIPING AND EQUIPMENT
23 05 93 TEST, ADJUSTING, AND BALANCING FOR HVAC
23 07 13 DUCT INSULATION
23 07 19 HVAC PIPING INSULATION
23 09 23 DIRECT DIGITAL CONTROL SYSTEM FOR HVAC
23 09 94 SEQUENCE OF OPERATIONS FOR HVAC DDC
23 23 00 REFRIGERANT PIPING
23 31 13 METAL DUCTS
23 33 00 AIR DUCT ACCESSORIES
23 33 46 FLEXIBLE DUCTS
23 34 16 HVAC FANS
23 34 33.13 COMMERCIAL AIR CURTAINS
23 37 13.13 AIR DIFFUSERS
23 37 13.23 REGISTERS AND GRILLES
23 74 33 DEDICATED OUTDOOR AIR UNIT – ENERGY RECOVERY
23 81 25 VARIABLE REFRIGERANT VOLUME AIR CONDITIONING
DIVISION 26 - ELECTRICAL
26 05 00 COMMON WORK RESULTS FOR ELECTRICAL
26 05 19 LOW VOLTAGE POWER CONDUCTORS AND CABLES
26 05 26 GROUNDING AND BONDING FOR ELECTRICAL SYSTEMS
26 05 29 HANGERS AND SUPPORT FOR ELECTRICAL SYSTEMS
26 05 33 RACEWAYS AND BOXES FOR ELECTRICAL SYSTEMS
26 05 36 CABLE TRAYS FOR ELECTRICAL SYSTEMS
26 05 44 SLEEVES AND SLEEVE SEALS FOR ELECTRICAL RACEWAYS AND CABLING
26 05 53 IDENTIFICATION FOR ELECTRICAL SYSTEMS
26 05 73.19 ARC-FLASH HAZARD ANALYSIS
26 09 23 LIGHTING CONTROL DEVICES
26 09 43.23 RELAY-BASED LIGHTING CONTROLS
26 24 16 PANELBOARDS
26 27 13 ELECTRICITY METERING
26 27 26 WIRING DEVICES
26 28 16 ENCLOSED SWITCHES
26 36 00 TRANSER SWITCHES
26 41 13 LIGHTNING PROTECTION FOR STRUCTURES
26 43 13 SURGE PROTECTION DEVICES
26 51 19 LED INTERIOR LIGHTING
26 52 13 EMERGENCY AND EXIT LIGHTING
26 56 19 LED EXTERIOR LIGHTING
DIVISION 27 - COMMUNICATIONS
27 11 00 COMMUNICATIONS EQUIPMENT ROOM FITTINGS
27 13 13 COMMUNICATIONS COPPER CABLING
27 40 00 AUDIO VISUAL SYSTEMS
DIVISION 28 - ELECTRONIC SAFETY AND SECURITY
28 20 00 VIDEO SURVEILLANCE
28 31 00 INTRUSION DETECTION SYSTEMS
28 31 76 FIRE ALARM AND VOICE EVACUATION SYSTEM
SITE AND INFRASTRUCTURE SUBGROUP
DIVISION 31 - EARTHWORK
31 10 00 SITE CLEARING
31 66 16 HELICAL FOUNDATION PILES
DIVISION 32 - EXTERIOR IMPROVEMENTS
32 13 13 CONCRETE PAVING
32 17 13 PARKING BUMPERS
32 17 23 PAVEMENT MARKINGS
32 17 26 TACTILE WARNING SURFACING
32 92 00 TURF AND GRASSES
WATER LINE UPGRADES - SPECIFICATIONS
The following specifications are specific to the Water Line Upgrades portion of this project. These are in addition or in substitution of the specifications above. If a specification exists below that is duplicated above, it supersedes that above. Additionally, The specifications above apply to the water line upgrades project as well with the exception of the superseded repeat specifications.
DIVISION 03 CONCRETE
03 30 00 CAST-IN-PLACE CONCRETE
DIVISION 22 PLUMBING
22 11 23 DOMESTIC WATER PUMPS
DIVISION 26 ELECTRICAL
26 24 19 MOTOR-CONTROL CENTERS
DIVISION 31 EARTHWORK
31 23 00 EXCAVATION AND FILL
31 23 23.33 FLOWABLE FILL
DIVISION 33 SITE UTILITIES
33 01 30.23 PIPE BURSTING (HDPE)
33 14 11 WATER UTILITY TRANSMISSION PIPING
33 14 19 VALVES AND HYDRANTS FOR WATER UTILITY SERVICE
33 14 20 WATER SERVICE CONNECTIONS AND ACCESSORIES
33 14 21 WATER MAIN ABANDONMENT
DIVISION 46 WATER AND WASTEWATER EQUIPMENT
46 01 00 OPERATIONS AND MAINTENANCE OF WATER AND WASTEWATER
EQUIPMENT
END OF TABLE OF CONTENTS
EVER-235866 Renovate Flamingo Visitor Facility 00 01 07-1 2017-308 Seals Page
Issued: May 31, 2019
DOCUMENT 000107 - SEALS PAGE
1.1 DESIGN PROFESSIONALS OF RECORD
A. Architect:
1. Jim Croft, R.A., Croft & Associates, 3400 Blue Springs Road, Suite 200, Kennesaw, GA, 30144, 770-529-7714, jim@croftae.com
2. License #: RA008571, Georgia
3. Responsible for Divisions 01-49 Sections except where indicated as prepared by other design professionals of record.
B. Civil Engineer (For Water Line Upgrades Only):
1. Lawrence Hale P.E., SM&E, 1615 Edgewater Drive, Suite 200, Orlando, FL, 32804, 404-975- 1273, lhale@smeinc.com
2. License #: 83465, Florida
3. Responsible for Divisions 01, 03, 32-33 Sections except where indicated as prepared by other design professionals of record.
C. Landscape Architect: None
D. Structural Engineer:
1. Michael Planer, P.E., PES Structural Engineers, 1852 Century Place NE, Suite 201, Atlanta, GA, 30345, 770-457-5923, mplaner@pesengineers.com
2. License #: 77406, Florida
3. Responsible for Divisions 03, 04, and 05 Sections except where indicated as prepared by other design professionals of record.
EVER-235866 Renovate Flamingo Visitor Facility 00 01 07-2
E. Fire-Protection Engineer:
1. Douglas Fisher, P.E., Fisher Engineering Inc., 10475 Medlock Bridge Road, Suite 520, Johns Creek, GA 30097, 770-495-7770, doug.fisher@feifire.com
2. License #: 59133, Florida
3. Responsible for Divisions 21 and 28 Sections except where indicated as prepared by other design
F. Plumbing Engineer:
1. Vincent Mazzei, P.E., Croft & Associates, 3400 Blue Springs Road, Suite 200, Kennesaw, GA, 30144, 770-529-7714, vmazzei@croftae.com
2. License #: 23002, Georgia
3. Responsible for Division 22 Section except where indicated as prepared by other design
EVER-235866 Renovate Flamingo Visitor Facility 00 01 07-3
G. HVAC Engineer:
1. Miles Johnson, P.E., Croft & Associates, 3400 Blue Springs Road, Suite 200, Kennesaw, GA, 30144, 770-529-7714, mjohnson@croftae.com
2. License #: PE041552, Georgia
3. Responsible for Division 22 Section except where indicated as prepared by other design
H. Electrical Engineer:
1. Jeffrey Morgan, P.E., Croft & Associates, 3400 Blue Springs Road, Suite 200, Kennesaw, GA, 30144, 770-529-7714, mjohnson@croftae.com
2. License #: PE033658, Georgia
3. Responsible for Divisions 26 and 27 Sections except where indicated as prepared by other design
END OF DOCUMENT 000107
EVER - 235866 01 11 00 - 1
091015 SUMMARY OF WORK
SECTION 01 11 00 - SUMMARY OF WORK
PART 1 - GENERAL
1.1 SUMMARY
A. This Section includes the following:
1. Work covered by the Contract Documents.
2. Work under other contracts.
3. Government Furnished Materials.
4. Contractor use of premises.
5. Public use of site.
6. Occupancy requirements for buildings.
7. Work Restrictions.
8. Special Construction Requirements.
9. Soils Investigation Report.
1.2 WORK COVERED BY CONTRACT DOCUMENTS
A. Project Location: Everglades National Park, Florida Bay, Flamingo Visitors Area located near Homestead, FL. The site is approximately 50 miles from the Everglades National Parks main entrance.
B. The Work consists of the following:
The Work includes the repurposing and renovation of the former Flamingo concessions restaurant and gift shop into the new Guy Bradley Visitor Center and the renovation of the Law Enforcement Wing (current Ranger Station). The structure was constructed in the Mission-66 era and has historical significance. The work includes provision for a new elevator location and to abandon the existing cargo elevator to provide handicapped access for both visitors and staff. The new visitor center will house spaces for offices, restrooms, a multi-purpose room, back country permit kiosk, conference room and bookstore. The Great Hall/Gallery space will be multi-purpose. Not only will this room be used to display the informational exhibits but it will also be used for special events. The building is 58 years old and all mechanical, electrical systems, architectural finishes and built in furnishings are being replaced due to the damage of past flooding. The ground level will house toilet rooms and back country permit kiosk. This project includes the installation of a new fire protection-sprinkler system, as well as a code compliant fire alarm and smoke detection system. A building sound/intercom system and an audio visual system will be installed for the great hall/exhibit area. All of the facility windows and exterior doors will be replaced to harden the building against future storms. The facility roof structure and roof system, which was damaged in previous hurricanes will be replaced in full with a new modified bitumen roof system. Minor modifications, including sidewalk additions and replacement, will be made to accommodate new entrance locations and flow of visitors. In addition to the general renovation tasks, this work also includes rehabilitation and repurposing of select interior and exterior building components, including monumental stairs, hand rails, sidewalks, and restrooms. Beyond the items highlighted in this paragraph, EVER - 235866 01 11 00 - 2 exterior work is limited. Work associated with the exterior envelope of the building outside of the windows, doors, and openings are not in scope. Landscape is not included in this scope of work. The Park is addressing these exterior scope items under different contracts.
In addition to the Flamingo Visitors Center facility work, a performance specifications package is included to upgrade the main water line infrastructure from the NPS owned desalination domestic water plant to the Flamingo area. These upgrades are necessary to support fire suppression and domestic water needs for the Flamingo Visitor’s Center Facility and future lodge / restaurant buildings in the Flamingo area.
C. Project will be constructed under a single prime contract.
1.3 WORK UNDER OTHER CONTRACTS
A. General: Cooperate fully with separate contractors so work on those contracts may be carried out smoothly, without interfering with or delaying work under this Contract. Coordinate the Work of this Contract with work performed under separate contracts.
B. Other Work: Government may award separate contract(s) for the following construction operations at Project site. This work may precede, run concurrently, or take place after the scope of work outlined in these construction documents. The contractor must coordinate the requirements of these efforts and how they affect this project scope of work with the Contracting Officer.
1. Exhibit Design/Implementation: A separate contract has been awarded to Harpers Ferry for the design and implementation of the exhibit elements for the Visitors Center wing of the Flamingo Visitor. This effort will run concurrently with this project’s scope of work
2. Landscape Modifications/Improvements: A separate contract may be awarded to another contractor (TBD) for the modification and improvements of the existing landscaping surrounding the Flamingo Visitor.
3. Exterior Coating and Re-Painting: A separate contract may be awarded to another contractor (TBD) for the treatment and re-painting of the exterior of the Flamingo Visitor.
This project is critical to providing a fully operational Flamingo Visitor’s Center and must be done in parallel to the renovation project. The exterior building coating is the vapor barrier for this facility and is not included in this design project. The Designer, Croft & Associates, assumes that this project will be done by completion of the renovation project.
4. Federal Highway Upgrades: A separate contract may be awarded to another contractor (TBD) for the overlay of all main roadways at the Park between the entrance and this site.
This effort is projected to take place from September of 2019 to July of 2020.
1.4 GOVERNMENT-FURNISHED MATERIALS
A. Government will furnish products indicated.
1. Government will arrange and pay for delivery of Government-furnished items according to Contractor's Construction Schedule.
EVER - 235866 01 11 00 - 3
2. After delivery, Government will inspect delivered items for damage. Contractor shall be present for and assist in Government's inspection.
3. If Government-furnished items are damaged, defective, or missing, Government will arrange for replacement.
4. Contractor is responsible for receiving, unloading, and handling Government-furnished items at Project site.
5. Contractor is responsible for protecting Government-furnished items from damage during storage and handling, including damage from exposure to the elements.
6. If Government-furnished items are damaged as a result of Contractor's operations, Contractor shall repair or replace them.
7. Contractor shall install and otherwise incorporate Government-furnished items into the Work.
B. Government-Furnished Products:
1. Radio Antennas (Roof Mounted) & Supports – Law Enforcement Wing – Roof
2. (1) Touch Screen Monitor (Specified by Harpers Ferry) – Visitors Center Wing – Upper
Floor
3. NPS Arrowhead Sign – Visitor’s Center Wing Exterior – Mounted on Building
4. Gun Safe/Lockers - Law Enforcement Wing – Equipment located in Armory – Upper
Floor
1.5 CONTRACTOR USE OF SITE
A. General: Contractor shall have full use of the site for construction operations during the construction period. Contractor's use of the site is limited only by the Government's right to perform work or to retain other contractors on portions of Project.
B. Storage of Materials: Confine storage of materials to the Visitors Center courtyard and interior storage spaces not currently in construction.
C. Preservation of Natural Features:
1. Prevent damage to natural surroundings. Restore damaged areas, repairing or replacing damaged trees and plants, at no additional expense to the Government.
2. Provide temporary barriers to protect existing trees and plants and root zones.
3. Do not remove, injure, or destroy trees or other plants without prior approval. Consult with
Contracting Officer and remove agreed-on roots and branches that interfere with construction.
4. Do not fasten ropes, cables, or guys to existing trees.
5. Carefully supervise excavating, grading, filling, and other construction operations near trees to prevent damage.
D. Preservation of Cultural Resources: This property is listed on the National Register of Historic Places" NPS and Park intend to continue managing this site as a valued cultural resource. All work and the conduct of all Contractor activity on site must be cautiously undertaken so as not to result in unnecessary damage or loss to historic fabric, features or elements. All work that will impact the historic character of this property will adhere to recommended preservation treatment approaches of the Secretary of the Interior's Standards for Treatment of Historic Structures, especially the Standards for Rehabilitation. In addition, the DOI Guidelines for Treatment of Cultural Landscapes will be
EVER - 235866 01 11 00 - 4
enforced. Contractor is advised to follow the most sensitive treatment approaches, and favor conservative means and methods over radical and untested materials, products and techniques."
E. Driveways and Entrances: Keep driveways and entrances serving premises clear and available to Government, Government's employees, and emergency vehicles at all times. Do not use these areas for parking or storage of materials.
1. Schedule deliveries to minimize use of driveways and entrances.
2. Schedule deliveries to minimize space and time requirements for storage of materials and equipment on-site.
F. Construction Camp: Establishment of a camp within the park may be permitted. Contractor shall coordinate viability and requirements with Contracting Officer during the bid process.
G. Hauling Restrictions: Comply with all legal load restrictions in the hauling of materials. Load restrictions on park roads are identical to the state load restrictions with such additional regulations as may be imposed by the Park Superintendent. Information regarding rules and regulations for vehicular traffic on park roads may be obtained from the Office of the Park Superintendent. A special permit will not relieve Contractor of liability for damage which may result from moving of equipment.
1.6 PUBLIC USE OF SITE
A. The building will be closed to the public during construction.
1.7 OCCUPANCY REQUIRMENTS FOR BUILIDINGS
A. Existing Buildings
1. Partial Government Occupancy: Government will occupy temporary trailers near the premises, but not the building or the area within the existing construction fence perimeter surrounding the building, during entire construction period. Cooperate with Government during construction operations to minimize conflicts and facilitate Government usage.
Perform the Work so as not to interfere with Government’s operations. Maintain existing exits, unless otherwise indicated.
a. Maintain access to existing walkways, corridors, and other adjacent occupied or used facilities. Do not close or obstruct walkways, corridors, or other occupied or used facilities without written permission from the Contracting Officer (CO).
1.8 CONDUCT OF OPERATIONS
A. At all times the contractor shall conduct his operations in conformance with the rules and regulations promulgated by the Secretary of the Interior for the National Park Service, and applicable park rules and regulations prescribed by the Park Superintendent.
B. Work on Saturdays, Sundays, Federal holidays or at night may not be performed without prior consent from the Contracting Officer. Submit requests 48 hours in advance of the work to the Contracting Officer for approval.
EVER - 235866 01 11 00 - 5
C. No signs or advertisements (except those specified herein) shall be displayed on the construction site or within the park unless approved by the Contracting Officer.
1.9 WORK RESTRICTIONS
A. On-Site Work Hours: Work shall be generally performed during normal business working hours matching Everglades National Park operating hours 7:00 am to 5:00 pm, Monday through Friday, except when otherwise indicated.
1. Weekend Hours: Coordinate with Contracting Officer.
2. Early Morning Hours: Coordinate with Contracting Officer.
B. Existing Utilities
1. Existing Utilities: Notify Contracting Officer and utility companies of proposed locations and times for excavation.
2. Contractor shall be responsible for locating and preventing damage to known utilities. If damage occurs, repair utility at no additional expense to the Government.
3. If damage occurs to an unknown utility, repair utility. An equitable adjustment will be made in accordance with the Changes clause of the contract.
C. Existing Utility Interruptions: Do not interrupt utilities serving facilities occupied by Government or others unless permitted under the following conditions and then only after arranging to provide temporary utility services according to requirements indicated:
1. Notify Contracting Officer not less than two days in advance of proposed utility interruptions.
2. Do not proceed with utility interruptions without Contracting Officer’s written permission.
3. Hours for Utility Shutdowns: Coordinate with Contracting Officer and Utility Provider.
Shutdowns that impact the remainder of the Flamingo area, not just the Flamingo Visitors Center building, can only be for a maximum of four hours.
D. Nonsmoking Building: Smoking is not permitted within the building or within 25 feet of entrances, operable windows, or outdoor air intakes.
1.10 SPECIAL CONSTRUCTION REQUIREMENTS
A. Project Website: A project website administered by the NPS will be used for purposes of managing communication and documents during the construction stage.
1. See Section 01 31 00 “Project Management and Coordination” for requirements on using the Project Website.
B. This area is prone to hurricanes and sever weather. The contractor is responsible for taking appropriate precautions and meeting all OSHA and Park safety standards with regards to inclement weather. The Park will provide a severe weather protocol and evacuation procedure to the contractor prior to work beginning. Hurricane season is considered June 1st through November 30th with the peak months being August, September, and October.
EVER - 235866 01 11 00 - 6
C. The contractor is responsible for maintaining a safe vicinity around the work site and shall re-direct visitors with appropriate signage and deterrents during the course of work. Peak visitor season for this Park is between Thanksgiving and Easter.
1.11 SOILS INVESTIGATION REPORT – Included in Design Submittal.
A. A soils investigation report entitled Geotechnical Engineer Report, Guy Bradley Flamingo Visitor Center – Proposed Elevator, Dated November 20, 2018 has been prepared by ECS Florida, LLC.
B. A copy of the report is available to all plan holders with this package.
C. If conflicts occur between the report and drawings or specifications, the drawings and specifications govern. Immediately inform the Contracting Officer when such conflicts arise.
PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION (Not Used)
END OF SECTION 01 11 00
EVER - 235866 01 26 01 - 1
031414 CONTRACT MODIFICATION PROCEDURES
SECTION 01 26 01 – CONTRACT MODIFICATION PROCEDURES
PART 1 - GENERAL
1.1 SUMMARY
A. The work of this section consists of administrative and procedural requirements for contract modifications.
1.2 DEFINITIONS AND ALLOWANCES
A. Home Office Overhead: Those costs incurred in support of all of a contractor’s projects and not attributable to a specific job. The cost for home office overhead is only allowed as a percentage of all direct work excluding profit. The following items represent allowable home office overhead costs identified in Part 31 of the Federal Acquisition Regulation (FAR):
1. Rent
2. Utilities
3. Furnishings
4. Office equipment
5. Executive and management staff not exclusively assigned to the project
6. Support, accounting, and administrative staff
7. Preparation of cost proposals, estimating, and schedule analyses connected with
Modifications
8. Estimating and preconstruction services
9. Mortgage costs
10. Real estate and corporate taxes
11. Automobile maintenance and travel costs for home office personnel
12. Home office insurances i.e. structure, automotive, umbrella, flood, etc.
13. Depreciation of equipment and other assets
14. Home office supplies (paper, staples, etc.)
15. Legal services
16. Accounting and data processing
17. Professional fees/registration
B. General Conditions (Field Office Overhead): Management and administrative costs incurred on site for the designated project. Costs associated with the preparation of modifications will not be allowed. The costs for these items are to be included only in the general conditions of the modification estimate. Only in the case of a contract time extension are additional general conditions included in modifications. The following items, if applicable, are considered allowable costs for calculating General Conditions:
1. Project Manager, Assistant Project Manager
2. Superintendent, Assistant Superintendent
3. Quality Control, Safety Officer, Environmental Manager, etc.
4. Engineers
5. Travel, lodging, and per diem (as established by Federal Travel Regulations)
EVER - 235866 01 26 01 - 2
6. Scheduling
7. Field Office Trailers and associated temporary utilities
8. Field office supplies
a. Mailing and couriers
b. Reproduction costs
c. Storage
d. Phones
e. Computers
f. Copiers
9. Personal vehicles i.e. Superintendent Pickup trucks
C. General Requirements: These are costs directly associated with the project and are necessary to perform the actual work of the modification. These costs shall be shown as direct costs in the estimate. The following items, if applicable, are considered allowable costs for calculating General Requirements:
1. Hoisting
2. Material handling
3. Temporary fencing
4. Port-a-lets
5. Trash removal, dumpsters
6. Barricades
7. Small tools
8. Safety supplies
9. Scaffolding
10. Daily cleaning
11. Traffic control
12. Temporary signage
13. Temporary heating and power
D. Personnel Costs: Costs included in the modification must only be for General Conditions staff and workers actually present and working on the project site. Modification costs for salaried workers are only allowed within the structure of a 40 hour week and no overtime or holiday pay will be allowed.
1. Worker Hourly Rates are costs directly associated with the individual worker and consist of the following:
a. Base Rate: This is the hourly rate paid directly to the worker
b. Labor Burden: Employer payments of all applicable burdens, this includes insurance and taxes that the business must pay on behalf of the worker to government entities and educational forums , such as:
1) Social Security
2) Medicare
3) Workers Compensation– Policy and company calculation to be made available.
4) FUTA– Cap Rate and percentage to be proportionally allocated over one year.
5) SUTA– Cap Rate and percentage to be proportionally allocated over one year.
EVER - 235866 01 26 01 - 3
6) Union agreement costs – Other costs required under an enforceable collective bargaining agreement.
c. Fringe Benefits: Various non-wage compensations provided to employees such as:
1) Health Care Insurance Premiums
2) Cell Phone
3) Clothing
4) 401K and Pensions
5) Vehicle allowances
6) Gas allowance
7) Life insurance premiums
8) Disability insurance
9) Other Fringe Benefits required under an enforceable collective bargaining agreement
E. Bonuses or Deferred Compensation: No Bonus or Deferred Compensation will be allowed within any components of pricing including Home Office Overhead, General Conditions, General Requirements, Hourly Worker Rates, or the direct costs of work.
F. General Liability Insurance: An insurance policy that protects the contractor from claims resulting from bodily injury or property damage to a third party. Include this as a separate line item within all modification proposals and provide a current insurance quote upon request.
G. Performance and Payment Bonds: A performance bond is a surety bond issued by an insurance company or bank to guarantee satisfactory completion of a project. The Payment Bond guarantees that the contractor will pay the labor and material costs they have incurred. Banks and Insurance companies charge a premium for each individual project based on a sliding scale which relates to the size of the project. Include this as a separate line item in modification proposals and provide current company bonding rates upon request.
H. Builder’s Risk Insurance: This covers the contractor’s loss due to fire, high winds, or other natural forces. This is not reimbursed by the National Park Service (NPS) and shall not be included in modification proposals.
1.3 MODIFICATION PROPOSAL PRICING REQUIREMENTS
A. General:
1. Your proposal must be received in the format and within the time frame specified in the Request for Proposal letter. Costs or delays resulting from failure of contractor to submit within the time frame specified will not be compensable.
2. The proposal must be detailed with itemized lists of equipment, materials, labor, production rates, overhead, profit, and bond markup for each item. Labor costs must be itemized by craft and hourly rate, including Fringe Benefits and Labor Burden. If the costs of Fringe Benefits and Labor Burden are not itemized, it is assumed that that they are included in the hourly rate shown, or contractor is not requesting reimbursement.
Contractor may utilize the government provided Contractor Estimate Form, or their
EVER - 235866 01 26 01 - 4
own form, provided that it contains the same information and level of detail as the Gov’t provided form.
3. Requests for extensions of contract time as a result of this change must be justified with a Time Impact Analysis (TIA). Refer to Division 01 Specification, “Construction Schedule”, for time impact analysis requirements. TIA and associated costs must be received with the proposal by the date shown within the Request for Proposal letter.
Contractor’s failure to submit within the specified time frame will be construed as the Contractor waiving the right for additional time and no time extension will be allowed.
4. All supporting documentation used to justify the proposed modification will be made available to the Contracting Officer upon request.
5. Contractor must review and approve all subcontractor/supplier pricing in detail for proper format, scope, production rates, and pricing prior to submission to the NPS. All delay costs associated with not reviewing and approving subcontractor/supplier pricing will be borne by the Contractor.
6. All pricing and production rates within the estimate must be based on fair and reasonable pricing and cannot include built-in contingency.
B. Labor:
1. Contractor shall estimate the cost of labor by itemizing each craft involved, indicating worker hourly rate (base rate + labor burden + fringe benefits) for each and itemizing the hours required for each craft that will be directly engaged in modification work.
Any work proposed that will require overtime work or premium pay shall be itemized separately. All rates shall be in accordance with the Davis-Bacon Act as incorporated herein. Labor Burden may include payroll taxes, Social Security, unemployment insurances, workers compensation insurance, FICA, FUTA, and other direct costs resulting from Federal, State or local laws.
2. Itemize labor costs for equipment operators separate from equipment costs.
3. The labor cost for foremen shall only be costs for related work required for the modification.
C. Materials:
1. The estimated cost for materials shall include quotes from multiple sources. Material prices must include all applicable fees and credits, including but not limited to, sales tax, freight and delivery charges, and tax rebates.
2. No markup shall be applied to any material provided by the NPS.
D. Equipment:
1. Equipment used for the project must be appropriately sized for the work being performed.
2. Do not include costs for “miscellaneous tools and equipment”, in your proposal for a replacement value of $500 or less. Costs shown in excess of $500 must be broken out separately.
3. Regardless of ownership, the rates to be used in determining equipment rental costs shall be the lowest cost from one of the following sources:
a. U.S. Army Corps of Engineers , Ownership and Operating Expense Schedule (use latest edition and applicable region)
b. Construction Blue Book
EVER - 235866 01 26 01 - 5
c. Local equipment rental rates, documented by actual invoice charges, or itemized vendor quotes.
4. The estimated equipment rates shall include the operating costs of all fuel, oil, lubrication, supplies, small tools, necessary attachments, ground engaging components, tires & tracks, routine repairs and maintenance (cost of major repair and overhaul is not allowed per FAR 31.105(d)(2)), depreciation, storage, insurance, and all incidentals.
Mobilization, if applicable, may be included for equipment solely used on the modification work but must be listed separately.
5. Estimate the full rate for equipment only for the duration that the equipment will be utilized to accomplish the work of the modification.
6. Standby unit rates used are to be in accordance with paragraph 1.3, D, 2, above. If the US Army Corp of Engineers is utilized then their standby rates prevail. If Bluebook or local equipment pricing is accepted, then ½ of the equipment costs minus any operating costs, major repair and overhaul will be accepted.
7. If equipment is in standby mode due solely to a documented NPS delay, the established standby rate shall apply from the first day of the delay.
8. Equipment that is not used and on the jobsite for up to five consecutive days may be classified at standby rates, provided that the equipment is or has been used solely to perform work on the modification and will be necessary to complete additional modification work. Equipment that is still on the jobsite but not in use after five consecutive days will not be considered in the modification pricing.
9. Requests for compensation for equipment stand by time must be justified, documented and itemized separately.
10. The estimated timeframe (daily, weekly, monthly) for use of the equipment must reflect the lowest cost to the Government.
E. Establishment and Application of Overhead and Profit Percentages:
1. Home Office Overhead and Profit (OH&P) shall be applied to direct costs only. Profit shall not be applied to overhead amounts; and overhead shall not be applied to profit.
Home office overhead shall contain only allowable, allocable, and reasonable costs per the contract documents and FAR Part 31. Profit percentages are based on risk factors found in FAR Part 31which have been applied to the specific type of work included in this project. Negotiated rates shall not exceed the following percentages for OH&P for contractor self-performed work:
Overhead………………10% Profit………………8.00%
2. Total aggregate limit of markup (OH&P) for contractor and subcontractors on modification work shall not exceed 25%. The NPS will not be responsible for allocation of percentages between contractor and subcontractors at any tier.
3. If contractors form a partnership, than the partnership may only receive home office overhead and profit in the same amount as an individual contractor (refer to par 1.3,E,1 above). It is the responsibility of the partners to decide on the division of revenue.
4. Combined Increases and Decreases: On proposals involving both increases and decreases in the Contract Price, the overhead and profit mark-ups are required on the net increases and deducted on net decreases.
5. At no time can profit be calculated on Overhead or itself, it must be calculated on direct costs of work only.
EVER - 235866 01 26 01 - 6
PART 2 - PRODUCTS
PART 3 - EXECUTION
END OF SECTION 012601
EVER - 235866 01 27 00 - 1
082714 DEFINITION OF CONTRACT LINE ITEMS
SECTION 01 27 00 – DEFINITION OF CONTRACT LINE ITEMS
PART 1 - GENERAL
1.1 SUMMARY
A. The intent of this section is to explain, in general, what is and what is not included in a contract line item, and the limits or cut-off points where one item ends and another begins.
B. If no contract line item exists for a portion of the work, include the costs in a related item.
PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION
3.1 LIST OF CONTRACT LINE ITEMS
A. Contract Line Item No.0001 – Interior Renovation of Visitor Center Wing.
1. This item consists of the repair and renovation of the interior of the Visitor Center Wing of the Flamingo Visitor Facility. All work referenced this associated specifications and drawings package is included in this project.
2. Measurement for payment will be based on construction progress.
3. Payment will be made periodically based on progress against the contract lump sum price.
B. Contract Line Item No.0002 – Interior Renovation of Law Enforcement Wing.
1. This item consists of the repair and renovation of the interior of the Law Enforcement Wing of the Flamingo Visitor Facility. All work referenced this associated specifications and drawings package is included in this project.
2. Measurement for payment will be based on construction progress.
3. Payment will be made periodically based on progress against the contract lump sum price.
C. Contract Line Item No.0003 – Site Work – Repair Flamingo Visitors Center Project.
1. This item consists of the repair and renovation of limited exterior scope items for the Flamingo Visitor Facility. All work referenced this associated specifications and drawings package is included in this project.
2. Measurement for payment will be based on construction progress.
3. Payment will be made periodically based on progress against the contract lump sum price.
D. Contract Line Item No.0004 – Exterior Window/Door Replacement – Both Wings.
1. This item consists of the replacement and addition of exterior doors and windows for both wings of the Flamingo Visitor Facility. All work referenced this associated specifications and drawings package is included in this project.
EVER - 235866 01 27 00 - 2
082714 DEFINITION OF CONTRACT LINE ITEMS
2. Measurement for payment will be based on construction progress.
3. Payment will be made periodically based on progress against the contract lump sum price.
E. Contract Line Item No.0005 – Roof Replacement
1. This item consists of the replacement of the roof joists, roof, and lightning protection system at the Flamingo Visitor Facility. All work referenced this associated specifications and drawings package is included in this project.
2. Measurement for payment will be based on construction progress.
3. Payment will be made periodically based on progress against the contract lump sum price.
F. Contract Line Item No.0006 – Furniture, Fixtures, & Equipment (FF&E)
1. This item consists of the purchase and installation of the FF&E package at the Flamingo Visitor’s Center facility. All work referenced this associated specifications and drawings package is included in this project.
2. Measurement for payment will be based on construction progress.
3. Payment will be made periodically based on progress against the contract lump sum price.
G. Contract Line Item No.0007 – Water Line Upgrades
1. This item consists of the upgrade of water service lines from the Domestic Water Plant to the future lodge/concessionaire site as well as pump upgrades at the Domestic Water Plant.
All work referenced this associated specifications and drawings package is included in this project.
2. Measurement for payment will be based on construction progress.
3. Payment will be made periodically based on progress against the contract lump sum price.
H. Contract Line Item No.0008 (Option) – Water Line Upgrades – Additional Length
1. This item consists of the upgrade of water service lines from the future lodge/concessionaire site to the main water service line servicing the campground loops.
All work referenced this associated specifications and drawings package is included in this project.
2. Measurement for payment will be based on construction progress.
3. Payment will be made periodically based on progress against the contract lump sum price.
I. Contract Line Item No.0009 (Option) – Water Line Upgrades – Visitor Center to Hotel Stub Out
1. This item consists of the upgrade of water service lines from the Flamingo Visitor Center to the future lodge/concessionaire. All work referenced this associated specifications and drawings package is included in this project.
2. Measurement for payment will be based on construction progress.
3. Payment will be made periodically based on progress against the contract lump sum price.
END OF SECTION 01 27 00
EVER - 235866 01 31 00 - 1
091015 PROJECT MANAGEMENT AND COORDINATION
SECTION 01 31 00 - PROJECT MANAGEMENT AND COORDINATION
PART 1 - GENERAL
1.1 SUMMARY
A. This Section includes administrative provisions for coordinating construction operations on Project including, but not limited to, the following:
1. Definitions
2. Construction Coordination.
3. Submittals
4. Coordination Drawings.
5. Requests for Information (RFIs).
6. NPS/DSC SharePoint Project Website.
7. Project meetings.
8. Environmental Coordination.
9. Permits
B. Related Requirements:
1. Section 01 32 16 “Construction Schedule” for preparing and submitting Contractor’s construction schedule.
2. Section 01 73 40 “Execution” for procedures for coordinating general installation and field-engineering services, including establishment of benchmarks and control points.
3. Section 01 77 00 “Closeout Procedures” for coordinating closeout of the Contract.
4. Section 01 91 14 “Total Building Commissioning” for coordinating the work with Owner’s
Commissioning Authority.
1.2 CONSTRUCTION COORDINATION
A. Coordination: Coordinate construction operations included in different Sections of the Specifications to ensure efficient and orderly installation of each part of the Work. Coordinate construction operations, included in different Sections, which depend on each other for proper installation, connection, and operation.
1. Schedule construction operations in sequence required to obtain the best results where installation of one part of the Work depends on installation of other components, before or after its own installation.
2. Coordinate installation of different components with other Contractors to ensure maximum accessibility for required maintenance, service, and repair.
3. Make adequate provisions to accommodate items scheduled for later installation.
4. Where availability of space is limited, coordinate installation of different components to ensure maximum performance and accessibility for required maintenance, service, and repair of all components, including mechanical and electrical.
EVER - 235866 01 31 00 - 2
5. Properly plan construction operations to include permit requirements. Allow enough time to execute permit provisions to maintain work schedule, site visits, inspections, and reporting deadlines.
B. Prepare memoranda for distribution to each party involved, outlining special procedures required for coordination. Include such items as required notices, reports, and list of attendees at meetings.
C. Administrative Procedures: Coordinate scheduling and timing of required administrative procedures with other construction activities and activities of other contractors to avoid conflicts and to ensure orderly progress of the Work. Such administrative activities include, but are not limited to, the following:
1. Preparation of Contractor's Construction Schedule.
2. Preparation of the Schedule of Values.
3. Installation and removal of temporary facilities and controls.
4. Delivery and processing of submittals.
5. Progress meetings.
6. Permit requirements.
7. Pre-installation conferences.
8. Project closeout activities.
9. Commissioning activities.
1.3 SUBMITTALS
A. Coordination Drawings: Prepare Coordination Drawings if limited space availability necessitates maximum utilization of space for efficient installation of different components or if coordination is required for installation of products and materials fabricated by separate entities.
1. Content: Project-specific information, drawn accurately to scale. Do not base Coordination Drawings on reproductions of the Contract Documents or standard printed data. Include the following information, as applicable:
a. Indicate functional and spatial relationships of components of architectural, structural, civil, mechanical, and electrical systems.
b. Indicate dimensions shown on the Contract Drawings and make specific note of dimensions that appear to be in conflict with submitted equipment and minimum clearance requirements. Provide alternate sketches to the Contracting Officer (CO) for resolution of such conflicts.
c. Indicate space requirements for routine maintenance and for anticipated replacement of components during the life of the installation.
d. Show location and size of access doors required for access to concealed dampers, valves, and other controls.
e. Indicate required installation sequences.
2. Sheet Size: At least 8-1/2 by 11 inches but no larger than 30 by 40 inches.
3. Number of Copies: Submit two opaque copies of each submittal. Contracting Officer will return one copy.
4. Refer to individual Sections for Coordination Drawing requirements for Work in those
Section
EVER - 235866 01 31 00 - 3
B. Coordination Drawing Organization: Organize coordination drawings as follows:
1. Floor Plans and Reflected Ceiling Plans: Show architectural and structural elements, and mechanical, plumbing, fire-protection, fire-alarm, and electrical Work. Show locations of visible ceiling-mounted devices relative to acoustical ceiling grid. Supplement plan drawings with section drawings where required to adequately represent the Work.
2. Plenum Space: Indicate subframing for support of ceiling and wall systems, mechanical and electrical equipment, and related Work. Locate components within ceiling plenum to accommodate layout of light fixtures indicated on Drawings. Indicate areas of conflict between light fixtures and other components.
3. Utility Rooms: Provide coordination drawings for utility rooms showing plans and elevations of mechanical, plumbing, fire-protection, fire-alarm, and electrical equipment.
4. Structural Penetrations: Indicate penetrations and openings required for all disciplines.
5. Slab Edge and Embedded Items: Indicate slab edge locations and sizes and locations of embedded items for metal fabrications, sleeves, anchor bolts, bearing plates, angles, door floor closers, slab depressions for floor finishes, curbs and housekeeping pads, and similar items.
6. Mechanical and Plumbing Work: Show the following:
a. Sizes and bottom elevations of ductwork, piping, and conduit runs, including insulation, bracing, flanges, and support systems.
b. Dimensions of major components, such as dampers, valves, diffusers, access doors, cleanouts and electrical distribution equipment.
c. Fire-rated enclosures around ductwork.
7. Electrical Work: Show the following:
a. Runs of vertical and horizontal conduit 1-1/4 inches in diameter and larger.
b. Light fixture, exit light, emergency battery pack, smoke detector, and other fire-alarm locations.
c. Panel board, switch board, switchgear, transformer, busway, generator, and motor control center locations.
d. Location of pull boxes and junction boxes, dimensioned from column center lines.
8. Fire-Protection System: Show the following:
a. Locations of mains piping, branch lines, pipe drops, and sprinkler heads.
9. Review: Contracting Officer (CO) will review coordination drawings to confirm that the Work is being coordinated, but not for the details of the coordination, which are Contractor's responsibility. If CO determines that coordination drawings are not being prepared in sufficient scope or detail, or are otherwise deficient, CO will so inform Contractor, who shall make changes as directed and resubmit.
10. Coordination Drawing Prints: Prepare coordination drawing prints according to requirements in Section 01 33 23 "Submittal Procedures."
C. Coordination Digital Data Files: Prepare coordination digital data files according to the following requirements:
1. File Preparation Format: Same digital data software program, version, and…