ATTACHMENT_1_GWMP_214371_Volume_1_Final_RFP.pdf

PDF 799 KB Posted

Attached to
GWMP 214371 Netherlands Carillon Federal contract opportunity
Solicitation number
140P2018R0067
Issued by
Department of the Interior National Park Service National Office

About this file

Attachment 1

View the file

Other files for this federal contract opportunity

Other files attached to GWMP 214371 Netherlands Carillon, newest first.
File Type Posted
ATTACHMENT_9_REV_1_WD_HEAVY_VA190043_FEB_22_2019_VA_43.pdf PDF
ATTACHMENT_14_WD_BUILDING_VA190178_April_05_2019_VA178.pdf PDF
140P2018R0067_amendment_0006.pdf PDF
ATTACHMENT_9_REV_1_WD_HEAVY_VA190043_FEB_08_2018_VA_43.pdf PDF
ATTACHMENT_13_ANSWERS_TO_PHASE_TWO_QUESTIONS.pdf PDF
ATTACHMENT_14_WD_BUILDING_VA190178_01042019_VA178.pdf PDF
140P2018R0067_Ammendment_0005.pdf PDF
140P2018R0067_Ammendment_0004.pdf PDF
140P2018R0067_Amendment_0003_FBO.pdf PDF
140P2018R0067_GWMP_214371_AMENDMENT_0002.pdf PDF
GWMP_214371_PHASE_1_Q&A_AM_0002.pdf PDF
140P2018R0067_GWMP_214371_AMENDMENT_0001.pdf PDF
GWMP_214371_PHASE_1_Q&A.pdf PDF
GWMP_214371_Netherland_Carillon-Nov_prebid.pdf PDF
PreProposal_Conference_Attendance_Record.pdf PDF
ATTACHMENT_2_GWMP_214371-Volume_2-_Final_RFP-Binder.pdf PDF
ATTACHMENT_9_Wage_Decision_No_VA180043_Heavy_092818.pdf PDF
ATTACHMENT_3_GWMP_214371_Volume_3_Final_Presdesign_binder_102017.pdf PDF
ATTACHMENT_10_PAST_PERFORMANCE_QUESTIONNAIRE.docx DOCX document
ATTACHMENT_11_PROPOSAL_SUBMISSION_PACKAGE.rtf RTF text file
ATTACHMENT_5_GWMP_214371-BellReanalysisReport-Final-030818.PDF PDF
ATTACHMENT_4_GWMP_214371_Full_Scanned_Drawings_Set.pdf PDF
ATTACHMENT_12__LIMITATIONS_ON_SUBCONTRACTING_REPORT.xlsx XLSX spreadsheet
140P2018R0067_GWMP_214371_FINAL_SOLICITATION.pdf PDF
ATTACHMENT_7_ACM-LBP_Survey_Report_-_Netherlands_Carillon.pdf PDF
ATTACHMENT_6_GWMP_214371-BellReanalysisCalcs-Final-030818.pdf PDF
ATTACHMENT_8_Carillon_Geotechnical_Report.pdf PDF
B01_Amended_PreSolicitation_Notice_GWMP_214371_10_24_18.pdf PDF
B01_Amended_PreSolicitation_Notice_GWMP_214371_Draft.pdf PDF
B01_PreSolicitation_Notice_GWMP_214371.pdf PDF
Show all 30

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

GEORGE WASHINGTON MEMORIAL PARKWAY

MCCLEAN, VIRGINA

SOLICITATION 140P2018R0067

REHABILITATE NETHERLANDS CARILLON TO IMPROVE SAFETY

AND VISITOR ACCESS

PMIS# GWMP 214371

DESIGN-BUILD (DB) PROJECT SCOPE

(DB Request for Proposal (RFP))

NATIONAL PARK SERVICE

DENVER SERVICE CENTER

Template Date 3-7-17 | Page 2 of 43

Table of Contents

1.0 PROJECT INTRODUCTION

1.1 SCOPE

1.2 NPS/DSC SHAREPOINT PROJECT WEBSITE

1.3 LOCATION

1.4 BACKGROUND

1.5 DESCRIPTION

1.6 SCHEDULE

1.7 INFORMATION

1.8 DATA AND MATERIALS TO BE PROVIDED BY THE NPS

2.0 PROJECT REQUIREMENTS

2.1 GENERAL REQUIREMENTS

2.1.1 SCOPE OF WORK AND PROJECT SUMMARY/REQUIREMENTS

2.1.2 DEFINITION OF CONTRACT LINE ITEMS

2.1.3 PROGRESS PAYMENTS

2.1.4 PROJECT MEETINGS

2.1.5 PROJECT SCHEDULE

2.2 DESIGN REQUIREMENTS

2.2.1 DB DESIGN DEVELOPMENT AND CONSTRUCTION DOCUMENTS

2.2.2 ENVIRONMENTAL AND SUSTAINABILITY REQUIREMENTS FOR DESIGN

2.3 CONSTRUCTION REQUIREMENTS

2.3.1 ENVIRONMENTAL AND SUSTAINABILITY REQUIREMENTS

2.3.2 SCHEDULE OF VALUES

2.3.3 CONSTRUCTION SUPPORT

2.3.4 SUBMITTALS DURING CONSTRUCTION

2.3.5 CONSTRUCTION COORDINATION

2.3.6 DIGITAL IMAGES

2.3.7 QUALITY CONTROL

2.3.8 WORKING HOUR RESTRICTIONS

2.3.9 TEMPORARY SERVICES

2.3.10 ACCESS

2.3.11 PRESERVATION OF ADJACENT FEATURES

2.3.12 EXISTING UTILITIES

2.3.13 HAULING RESTRICTIONS

2.3.14 ACCIDENT PREVENTION

2.3.15 TEMPORARY CONTROLS

2.3.16 FIELD ENGINEERING

2.3.17 PROJECT CLOSE-OUT

2.3.18 SUBSTANTIAL COMPLETION AND FINAL INSPECTION

2.4 FORMS

3.0 PERFORMANCE REQUIREMENTS

3.1 DESIGN IMPERATIVES

3.2 SUSTAINABILITY

3.4 FACILITY PERFORMANCE

3.5 ELEMENTS AND PRODUCTS

Template Date 3-7-17 | Page 3 of 43

4.0 TECHNICAL REQUIREMENTS

DC B1 Superstructure Criteria DC D1 Demolition Criteria DC D6 Electrical Criteria

DB F2020 Asbestos Abatement DB F2025 Lead in Construction

5.0 ATTACHMENTS

Template Date 3-7-17 | Page 4 of 43

1.0 PROJECT INTRODUCTION

Park Alpha and PMIS Number: GWMP 214371

Project Title: Rehabilitate Netherlands Carillon to Improve Safety and Visitor Access

Project Drawing Number: 850 140341

1.1 Scope

In accordance with the terms and conditions of the Contract, the Design-Build Contractor (DBC) shall perform the work of this Request for Proposal (RFP) for the National Park Service (NPS) as described below.

All Architect/Engineer (A/E) Services required in this RFP shall be performed by licensed Architects and Engineers registered in the Commonwealth of Virginia.

The work of this RFP shall be performed in accordance with the Denver Service Center (DSC) Design- Build (DB) Workflows website, https://www.nps.gov/dscw/designbuild.htm.

Listed on the DB homepage are links to the design phases which describe the required workflow process from Predesign (PD) through Construction Documents (CD). Each design phase webpage contains hypertext links to definitions, forms, templates, samples and guidelines.

The DB homepage also includes links to the Design Standards and Design Deliverables sections which provide design requirements and criteria that shall be used for completing the work of this contract:

• Design Standards (https://www.nps.gov/dscw/dstandards.htm): Design Standards arranged by discipline and/or specialty.

• DB Design Deliverables – Content and Format Requirements (https://www.nps.gov/dscw/del_designbuild.htm):

o Design phase submission requirements for:

Technical content Submission format (hard-copy and electronic)

In addition, there is an Information section (https://www.nps.gov/dscw/information.htm) with links directly to the following sections:

• Definitions (https://www.nps.gov/dscw/definitions.htm): A list of terms relevant to design and construction in national parks.

• Forms/Templates/Samples/Guidelines (https://www.nps.gov/dscw/publicforms.htm): A listing of forms/templates/samples/guidelines used for a typical project.

• Laws/Regulations/Policies/Guidance (https://www.nps.gov/dscw/laws-policies.htm): A listing of sources for retrieving laws/regulations/policies/guidance applicable to NPS projects.

• Quality Assurance Guideline & Review Checklists

(https://www.nps.gov/dscw/qaguideline.htm): Overview of the DSC Quality Assurance (QA) Process for reviewing Design Documents.

https://www.nps.gov/dscw/designbuild.htm https://www.nps.gov/dscw/dstandards.htm https://www.nps.gov/dscw/del_designbuild.htm https://www.nps.gov/dscw/information.htm https://www.nps.gov/dscw/definitions.htm https://www.nps.gov/dscw/publicforms.htm https://www.nps.gov/dscw/laws-policies.htm https://www.nps.gov/dscw/qaguideline.htm

Template Date 3-7-17 | Page 5 of 43

In case of conflict between this RFP and the DSC DB Workflows website, https://www.nps.gov/dscw/designbuild.htm, this RFP will take precedence over and will be used in lieu of such conflicting portions.

The A/E remains fully responsible for determining if the standards or provisions cited on the DSC DB Workflows website, https://www.nps.gov/dscw/designbuild.htm, have been revised or updated. Any such conflicts between the website and the identified standard or provisions shall be brought to the attention of the Contracting Officer (CO) requesting direction.

1.2 NPS/DSC SharePoint Project Website

Use the NPS/DSC SharePoint Project website for purposes of hosting and managing project communication and documentation until Final Completion. The NPS/DSC SharePoint Project website will be used for the following functions:

• Project directory

• Project correspondence

• Meeting agendas and minutes

• Contract modifications documentation and logs

• RFI form and processing

• Task and issue management

• Photo documentation

• Baseline schedule, schedule updates and calendar management

• Submittal form and processing

• Drawing and specification document hosting, viewing, and updating

• Online document collaboration

• Reminder and tracking functions

• Archiving functions

• Notification of submittal and RFI statuses and current responsible party

Submit to the CO a list of all employees who will need access to the website. The users will receive an invitation to register from the Department of Interior (DOI). Once the user is registered on the DOI website, they will be given access to the project website. For login procedures and other SharePoint information, refer to the DSC Workflows website at https://www.nps.gov/dscw/precon_spproj.htm.

All users will be required to have Internet Explorer version 7 or later and Adobe Acrobat Pro version 9 or later.

1.3 Location

This project is located in Arlington Ridge Park, Arlington, Virginia and is part of the George Washington Memorial Parkway.

1.4 Background

The carillon’s steel cladding is showing severe signs of deterioration and all public access is closed. The Netherlands Embassy plans to restore and retune the bells in the Netherlands and add three new bells to the carillon, along with a new playing console and operating equipment. A separate contractor will remove and https://www.nps.gov/dscw/designbuild.htm https://www.nps.gov/dscw/designbuild.htm https://www.nps.gov/dscw/precon_spproj.htm

Template Date 3-7-17 | Page 6 of 43 reinstall the bells and associated equipment. Coordination will be required between the DB contractor and the contractor hired by the Royal Eijbouts foundry.

1.5 Description

The current scope of work includes the rehabilitation of the steel cladding and superstructure with improvements to provide better drainage and ventilation within the structure. An alternate is included for waterproofing roof decks. Future work phase will implement public access, Clavier Room improvements, and mechanical and electrical work, as well as plaza repairs.

Commission of Fine Arts and National Capitol Planning Commission Final Review will be required.

CFA and NCPC Final Review submittal requirements can be found at http://www.cfa.gov and http://www.ncpc.gov. Submit materials as per submission deadline. Present to the CFA and attend the NCPC hearing. Respond to requests to modify and/ or add to submitted materials and attend follow-up meetings as required to obtain approval. The NPS requires a review of draft materials two weeks prior to the CFA and NCPC submission deadline.

1.6 Schedule

The work in this RFP shall be completed in accordance with the following schedule:

75% Draft DB Construction Documents (CD):

DB Design Development Documents submitted no later than __63__ calendar days after award.

NPS Review completed no later than __21__ calendar days after submission of DB Design Development Documents.

100% Draft DB Construction Documents (CD):

Work on 100% Draft DB Construction Documents shall continue during the DB Design Development Documents review and once DB Design Development review comments are received they shall be addressed and incorporated in the 100% Draft DB Construction Documents.

100% Draft DB Construction Documents and written responses to the NPS DB Design Development Document Review Comments submitted no later than __42__ calendar days after submission of DB Design Development Documents.

NPS Review completed no later than __21__ calendar days after receipt of 100% Draft DB Construction Documents.

100% Complete DB Construction Documents (CD):

100% Complete DB Construction Documents and written responses to the NPS 100% Draft DB Construction Documents Review Comments submitted no later than __14__ calendar days after submission of 100% Draft DB Construction Documents and final approvals by CFA and NCPC.

http://www.cfa.gov/ http://www.ncpc.gov/

Template Date 3-7-17 | Page 7 of 43

NPS Review completed no later than __21__ calendar days after receipt of 100% Complete DB Construction Documents.

Complete Stamped and Signed DB Construction Documents (CD):

Complete Stamped and Signed DB Construction Documents and written responses to the NPS 100% Complete DB Construction Document review comments submitted no later than __21__ calendar days after receipt of NPS 100% Complete DB Construction Document review comments.

Construction:

Construction shall not begin until the Contracting Officer (CO) has issued the DB Start Work Notice.

Construction completed no later than __590__ calendar days after award of the contract.

As-Constructed Drawings:

As-Constructed Drawings completed no later than __40__ calendar days after Substantial Completion.

All DB Design Development, DB Construction Documents and As-Constructed Drawings shall be submitted to the NPS Project Manager (PM).

1.7 Information

NPS Points of Contact:

Contractual:

Contracting Officer (CO): Karen La Bouff-Kind, 303-969-2181, karen_labouff-kind@nps.gov

Contract Specialist (CS): Paula Johnson, 303-987-6643, paula_johnson@nps.gov

Technical:

Project Manager (PM) and Contracting Officer’s Representative (COR): Brian Heitman, 303-987- 6656, Brian_Heitman@nps.gov

Project Specialist (PS) and Alternate Contracting Officer’s Representative (COR): Brian Frailey, 303-478-7428, brian_frailey@nps.gov

Address:

National Park Service – Denver Service Center 12795 West Alameda Parkway P.O. Box 25287 Denver, CO 80225

1.8 Data and Materials to be provided by the NPS

The following data and materials will be provided to the DBC and are included in Section 5 of this RFP:

Template Date 3-7-17 | Page 8 of 43

• Project Program

• Basis of Design Report (BDR)

• Approved Schematic Design Preferred Alternative Documents

• NPS Project Sustainability Checklist

• Existing Drawings

• Existing Site Map and Underground Utilities

• Geotechnical Report

• Historic Drawings

• Historic Photographs

• Finding of No Significant Impact (FONSI)

• Hazmat report

Template Date 3-7-17 | Page 9 of 43

2.0 PROJECT REQUIREMENTS

2.1 General Requirements

2.1.1 SCOPE OF WORK AND PROJECT SUMMARY/REQUIREMENTS

The project will consist of the design and construction of the rehabilitation of the Netherlands Carillon.

The project will include, but not be limited to, the following:

• Review the Schematic Design preferred alternative provided in the RFP package.

• Review Section 106 Assessment of Effect. Construction must comply with this document and the Secretary of the Interior’s Standards for Treatment of Historic Structures.

• Review site data.

• Upon award, determine and provide design schedule of work.

• Submit list of required permits.

• Complete design of rehabilitation.

• Submit DB Design Development and DB Construction Documents for review and approval, as required.

• Secure final approvals from US Commission of Fine Arts and National Capital Planning

Commission.

• Provide schedule of construction work.

• Secure work area and provide for protection of visitors.

• Construct project.

• Create and provide operations and maintenance manual.

• Provide as-constructed drawings.

2.1.2 Definition of Contract Line Items

The intent of this section is to explain, in general, what is included in each contract line item, limits or cut-off points where one item ends and another begins. If no item exists for a portion of the work, include the costs in a related line item.

CONTRACT LINE ITEM NO. 1 – DESIGN-BUILD DESIGN AND CONSTRUCTION

ADMINSTRATION: This item consists of Design-Build Design costs and construction administration.

CONTRACT LINE ITEM NO. 2 – CONSTRUCTION: Rehabilitation of carillon structure This item consists of rehabilitation of carillon superstructure, metal wall plates, floor and roofing plates, and railings.

CONTRACT LINE ITEM NO. 3 – OPTION 1 – Roofing membranes: This item consists of the addition of a liquid applied roofing membrane over the Soundboard roof plates and the Clavier Room roof plates.

2.1.3 Progress Payments

Template Date 3-7-17 | Page 10 of 43

Design Phase - Progress payments during the design phase of the work will be based on submission, review, and acceptance of design deliverables.

Construction Phase - Progress payments during construction will be based on the percentage of work completed on items listed on the approved schedule of values. Actual construction completed and in place will form the basis for payment. Verification of the % complete shall be initiated by the Contractor under the direction of a representative of the Contracting Officer, unless the Contracting Officer waives this requirement in a specific instance. The Contractor shall make the computations for payment based on the governments verification of work completed and in place for any periods for which progress payments are requested.

The Contractor shall furnish the originals of all field notes and all other records relating to the basis for payment, to the Contracting Officer, who shall use them as necessary to determine the final amount of progress payments. The Contractor shall retain copies of all such material furnished to the Contracting Officer.

2.1.4 Project Meetings

Design Meeting

After the award of the contract and acceptance of the Performance and Payment bonds, the CO will arrange a design meeting with the DBC at the Park. The meeting agenda shall include the following as a minimum:

• Review and emphasize the Park needs and design objectives.

• Environmental, sustainability, and historic preservation requirements

• Schedule of Values

• Design schedule (provide minimum of two color hard copies).

• Permitting

• Modifications during design

• Submittals during design

• Areas available for use by the DBC

• Access requirements of the Park

• Natural and Cultural Resource Protection

• Payments to the DBC

Preconstruction Meeting

The following Part 2 Project Requirement deliverables shall be submitted a minimum of one week prior to the Preconstruction Meeting.

• Letter designating your Project Superintendent

• Project Schedule with construction portion fully developed

• Schedule of Values

• Accident Prevention Program

• A list of subcontractors for this project (must be same as in your proposal)

Template Date 3-7-17 | Page 11 of 43

• Written statements from subcontractors certifying compliance with applicable labor standard clauses

• Evidence of liability insurance coverage and workmen’s compensation for the contractor and all subcontractors

• Waste Management Plan

• Quality Control Plan

• Storm Water Pollution Prevention Plan Submittal process

• Historic Preservation Treatment Program

• List of required permits

After 100% Complete DB Construction Documents are approved (or completed portions of DB CDs necessary for fast tracking the project), and prior to the start of construction, the CO will arrange an on-site Preconstruction meeting with the DBC. The meeting agenda will include the following as a minimum:

• Correspondence procedures

• Jobsite safety

• Roles and responsibilities

• Lines of Authority

• Schedule of Values

• Progress Payments

• Submittal process

• Resolution to comments provided by NPS on the Part 2 Project Requirements

• NPS/DSC SharePoint Project website

• Construction schedule (Provide a minimum of two color hard copies and electronic copy in software it was created in.)

• Labor standards

• Payroll reports

• Modifications

• Accident reporting

• Park Rules and Regulations

• Medical emergency processes, availability, emergency numbers, and contacts.

• Park permits, burning construction waste, rules of the road, alcohol use, housekeeping, firearms, pets, natural and cultural resource concerns.

• Bridge, access road and site constraints.

• Visitation and public relations.

• Environmental and sustainability requirements for the Project, required tracking for sustainability (related submittals), use of the NPS Project Sustainability Checklist.

• Archeological Resources Protection Requirements

• Saturdays, Sundays, holidays and night work.

• Traffic control

Progress Meetings

The DBC shall participate in weekly telephone conference calls with the Contracting Officer, and other project team members to update them on the following meeting agenda items:

Template Date 3-7-17 | Page 12 of 43

• Approval of minutes of previous meetings

• Submittal status

• Review of off-site fabrication and delivery

• Requests for Information (RFI’s) and issues

• Modifications

• Work in progress and projected

• Schedule update (provide updated CPM schedule)

• Status of Project Record Drawings and O&M Manuals

• Other business relating to work

2.1.5 Project Schedule

General: The Contractor shall upload the project schedule to the NPS/DSC SharePoint Project website and provide two (2) color copies after award and before the design meeting. The schedule shall include a detailed design phase with design deliverable submission dates, review periods as well as a summary construction schedule with important milestones included for both phases.

Fully develop the construction portion of the schedule and submit to the Contracting Officer on the NPS/DSC SharePoint Project website before the Preconstruction meeting or any construction begins.

The project schedule shall be updated on a monthly basis throughout the entire contract period and until project substantial completion. The status date of each schedule update shall be 10 days before the progress payment request date.

Construction work cannot begin until government approval is obtained for either:

• The entire set of 100% Complete DB Construction documents.

• For fast track construction, the 100% Complete DB Construction documents affecting the work to be constructed.

Purpose: The purpose of the project schedule is to ensure adequate planning, coordination, scheduling, and reporting during execution of design and construction activities of the DBC. The project schedule will assist the DBC and the Contracting Officer in monitoring the progress of the work, evaluating proposed changes, and processing the DBC's monthly progress payment requests.

Software: The software shall be the latest version of Microsoft Project, Primavera Project Planner, SureTrak, or approved equal.

Schedule Development: The project schedule shall cover the entire contract period. The late finish date of the project schedule shall be the same date as the established completion date of the contract.

The DBC shall use the Critical Path Method (CPM) with limited use of lead or lag durations between schedule activities. The DBC's project schedule shall consist of procurement activities (including mobilization, submittal, and the fabrication and delivery of key and long-lead procurement items) and construction activities.

The DBC's project schedule shall consist of, but not be limited to, the following for each activity:

• Identify each and every activity number with numerical designations (maximum 5-digit).

Numbering of activities shall be in increments of 10.

Template Date 3-7-17 | Page 13 of 43

• Concise description of the work represented by the activity (maximum 48 characters). Avoid the use of non-standard abbreviations. The work related to each activity shall be limited to one work trade.

• Activity duration in whole working days with a maximum duration of 15 work days each, unless otherwise approved by the Contracting Officer, except for non-construction activities including mobilization, shop drawing and sample submittals, fabrication of materials, delivery of materials and equipment, and concrete curing.

In developing the project schedule, the DBC shall be responsible for ensuring that subcontractor work at all tiers, as well as its own work, is included in the project schedule.

The project schedule shall show the sequence and interdependence of activities required for complete performance of the work. It shall be cost and resource loaded. The DBC shall be responsible for ensuring all work sequences are logical and the project schedule shows a coordinated work plan.

Proposed durations assigned to each activity shall be the DBC's best estimate of time required to complete the activity considering the scope and resources planned for the activity. Resource loading of each activity shall list all personnel by labor category and equipment type and capacity proposed to complete the activity in the duration shown. Include permit requirements and constraints. Seasonal weather conditions shall be considered and included in the planning and scheduling of all work influenced by high or low ambient temperatures, wind and/or precipitation to ensure completion of all work within the contract time.

Project Schedule Updates

Monthly updates: The monthly updating of the project schedule shall be an integral part and basic element of the estimate upon which progress payments shall be made under this contract. If, in the judgment of the Contracting Officer, the DBC fails or refuses to provide a schedule of values and a complete schedule update or revision as specified hereinafter, the DBC shall be deemed to have not provided the required information upon which the progress payment may be made, and shall be subject to retainage of a portion of the payment.

Narrative: The report shall include a brief description of the actual progress made during the update period; actual and potential delaying activities; any impediments to progress; issues related to inclement weather; progress toward established milestones and project float. The report shall include a brief description of the work anticipated to be performed in the next month. Any minor revisions to the schedule should be identified so they can be evaluated and accepted or rejected.

As the Work progresses, indicate Actual Completion percentage for each activity.

If the schedule update shows a late finish date after the contract completion date, at a minimum, include the following in the narrative with your submission:

• Any known delays.

• Actions that will be taken to get back on schedule.

• Pending modifications.

• Impediments or constraints affecting progress.

Progress Payments: The monthly updating of the currently accepted Construction Schedule shall be an integral part of the process upon which progress payments will be made under this contract. If the

Template Date 3-7-17 | Page 14 of 43

Contractor fails to provide schedule updates or revisions, then a portion of the monthly payment may be retained until such corrections have been made.

Time Impact Analysis for Contract Modifications, Changes, Delays, and Contractor Requests Requirements: When contract modifications or changes are initiated, delays are experienced, or the DBC desires to revise the project schedule, the DBC shall submit to the Contracting Officer a written time impact analysis illustrating the influence of each modification, change, delay, or DBC request on the contract time.

Time Extensions: Activity delays shall not automatically mean that an extension of the contract time is warranted or due the DBC. It is possible that a modification, change, or delay will not affect existing critical activities or cause non-critical activities to become critical. A modification, change, or delay may result in only absorbing a part of the available total float that may exist within an activity chain of the project schedule, thereby not causing any effect on the contract time. Time extensions will be granted in accordance with the terms of the contract.

Float: Float is not for the exclusive use or benefit of either the National Park Service or the DBC.

Extension of the contract time will be granted only to the extent the equitable time adjustments to the activity or activities affected by the modification, change, or delay exceeds the total (positive or zero) float available on a particular activity.

2.2 Design Requirements

2.2.1 Construction Documents (CD)

This element of work shall consist of the preparation of DB Construction Documents. All documents shall be prepared using the English System of Weights and Measurements, and shall be prepared in accordance with the DSC Design Standards, https://www.nps.gov/dscw/dstandards.htm.

DB Construction Documents shall be prepared per the Design Deliverable Content and Format Requirements for DB Construction Documents, https://www.nps.gov/dscw/del_constructiondb.htm.

Salient characteristics shall be listed for products and materials specified. Refer to the Guide for Specifiers, https://www.nps.gov/dscw/publicforms.htm#gfs.

Deliverables

The following deliverables are required (refer to Section 1.6 for schedule):

DB 75% Draft Construction Documents

DB 75% Draft Construction Documents:

• Documents for NPS Review:

Submit _11_ hard copies of the following DB 75% Draft Construction Documents for review:

o DB 75% Draft Construction Documents o Divisions 2 through 49 Outline Specifications o Product File https://www.nps.gov/dscw/dstandards.htm https://www.nps.gov/dscw/del_constructiondb.htm https://www.nps.gov/dscw/publicforms.htm#gfs

Template Date 3-7-17 | Page 15 of 43 o Statement of Structural Tests and Special Inspections o NPS Project Sustainability Checklist (DD portion completed)

Submit in native formats (no PDF formatted files) one electronic copy of the 75% Draft DB

Construction Drawings and the NPS Project Sustainability Checklist.

Denver Service Center: Submit seven (7) hard copies and one (1) electronic copy to:

Brian Frailey National Park Service / Denver Service Center Design and Construction Division 12795 West Alameda Parkway Lakewood, Colorado 80228-2838

303.969.2467 brian_frailey@nps.gov

George Washington Memorial Parkway Submit (2) hard copies and one (1) electronic copy to:

Ming-Yi Wong National Park Service / George Washington Memorial Parkway 2700 George Washington Memorial Parkway Arlington, VA 22202

703.419.6403 ming-yi_wong@nps.gov

National Capital Regional Office: Submit one (2) hard copies and one (1) electronic copy to:

Cherie Shepherd National Park Service National Capital Region 1100 Ohio Dr. SW Washington DC 20242

202.619.7058 cherie_shepherd@nps.gov

DB Construction Documents

100% Draft DB Construction Documents

Submit 11 hard copies of the following 100% Draft DB Construction Documents for review:

Template Date 3-7-17 | Page 16 of 43 o DB Construction Drawings o Divisions 2 through 49 Construction Specifications (Construction Specifications

Institute (CSI) MasterFormat 04 Edition). A/E shall utilize and modify their own Divisions 2 through 49 Construction Specifications templates.

o Product File o Statement of Structural Tests and Special Inspections o NPS Project Sustainability Checklist (CD Portion completed) o Design Calculations o Written responses to the DB Design Development Documents Review Comments

(Utilize NPS Review Form)

Submit in native formats (no PDF formatted files) one electronic copy of the 100% Draft DB Construction Drawings and written responses/resolutions to all DB Design Development Documents Review Comments.

Refer to Section 2.2.1 above for distribution of submittals.

100% Complete DB Construction Documents

Submit _11_ hard copies of the following 100% Complete DB Construction Documents for review and final approval:

o DB Construction Drawings o Divisions 2 through 49 Construction Specifications o Product File o Statement of Structural Tests and Special Inspections o NPS Project Sustainability Checklist (CD Portion completed and updated) o Design Calculations o Written responses to the 100% Draft DB Construction Documents review comments

(Utilize NPS Review Form)

Submit in native formats (no PDF formatted files) one electronic copy of the 100% Complete DB Construction Drawings and written responses/resolutions to all 100% Draft DB Construction Documents Review Comments.

Refer to Section 2.2.1 above for distribution of submittals.

Complete Stamped and Signed DB Construction Documents

• Upon final approval of the 100% Complete DB Construction Documents, submit per the following table, the Complete Stamped and Signed DB Construction Documents for construction, NPS archiving and general use (see the DSC DB Workflows website “Submittal Formats” portion of the “Design Deliverables – Content and Format Requirements” for format and media submission requirements.)

COMPLETE STAMPED AND SIGNED DB

CONSTRUCTION DOCUMENTS

ELECTRONIC

FORMATS *

HARD COPY

FORMATS

Template Date 3-7-17 | Page 17 of 43

DB Construction Drawings ** AutoCAD Full-Size Paper

(ANSI D)

Divisions 2 through 49 Construction Specifications PDF & MS-Word N/A Product File PDF N/A Statement of Structural Tests and Special Inspections PDF & MS-Word N/A NPS Project Sustainability Checklist PDF & MS-Excel N/A Supplemental Design Reports (if applicable) PDF N/A Design Calculations PDF N/A Written responses to the 100% Complete DB Construction Documents review comments PDF & MS-Excel N/A

* The recipient of the electronic files is TIC.

** DB Construction Drawings shall be printed from the native software (e.g. AutoCAD .dwg or Revit .rvt). DB Construction Drawings printed from secondary software (e.g. Adobe .pdf) are not acceptable as they often result in off-scale product.

2.2.2 Environmental and Sustainability Requirements for Design

The National Park Service has established environmental and sustainability requirements for the project.

Notify the CO if conflicts arise between performance of the work and environmental and sustainability requirements. The National Park Service does not intend to limit alternative means of achieving these requirements.

Specific sustainability requirements for design may be found in Part 3, Performance Requirements, of this document and the NPS Project Sustainability Checklist, https://www.nps.gov/dscw/publicforms.htm#psc. Complete this checklist by concisely explaining how each credit/requirement will be met.

2.3 Construction Requirements

2.3.1 Environmental and Sustainability Requirements

Specific sustainability requirements generated in design will dictate more stringent environmental requirements for this project. Refer to part 3, Performance Requirements, of this document and the NPS Project Sustainability Checklist. The following are general requirements:

• Site Disturbance: Minimize the construction limits of the project to reduce the project’s impact on the site.

• Toxic Chemicals: Avoid materials that can leach toxic chemicals into the ground water. Do not allow toxic chemicals to enter sewers or storm drains or contaminate land or any body of water.

Refer to NPS Project Sustainability Checklist for additional requirements.

• Soil Erosion: Protect against erosion and topsoil depletion in accordance with the Stormwater Pollution Prevention Plan.

• Habitats: Protect natural habitats and ecological systems on facility site (as identified in the Environmental Assessment).

https://www.nps.gov/dscw/publicforms.htm#psc

Template Date 3-7-17 | Page 18 of 43

• Noise: Minimize noise generation during construction. Operate power equipment in accordance with local noise restrictions.

• Waste Management: Employ processes that ensure the generation of as little waste as possible.

Waste disposal in landfills shall be minimized. Recycling is a requirement of this project.

Specific recycling goals were established in the NPS Project Sustainability Checklist. All material unsuitable for recycling must be disposed of, in a legal manner, at public or private dumping areas outside the park.

The DBC shall designate an on-site party (or parties) responsible for instructing workers and overseeing the environmental and sustainability requirements of this project. Distribute copies of the environmental and sustainability requirements to the Job Site Foreman and each Subcontractor.

Waste Management Plan: Prior to the scheduled Preconstruction meeting, the Contractor shall submit a draft Waste Management Plan to the Contracting Officer for approval. Develop and implement in accordance with ASTM E1609 and as required in the contract documents. The plan shall include (but not be limited to) the following:

• List of the recycling facilities, reuse facilities, municipal solid waste landfills, and other disposal area(s) to be used. Include name, location, and phone number.

• List of proposed materials to be reused or recycled.

• List of materials that cannot be recycled or reused with explanation or justification.

• Storage and collection methods of waste and recyclables, handling procedures, and means of keeping recyclables free of contamination.

• Description of the means of transportation of the recyclable materials and an estimate of how often bins will need to be emptied.

• Identity person or persons responsible for ensuring project recycling goals are achieved.

• Revise and resubmit Plan as required by the Contracting Officer. Approval of the Contractor’s Plan will not relieve the Contractor of responsibility for compliance with applicable environmental regulations.

Progress Documentation: Supplemental to the Waste Management Plan, document solid waste disposal, diversion, and cost/revenue analysis and submit a completed worksheet on a monthly basis. Use Appendix A - Project Waste Management Plan Worksheet, and report totals to date for all column headings. Use Appendix B for solid waste volume to weight conversions.

Prior to the commencement of the Work, schedule and conduct a meeting with the Contracting Officer to discuss the proposed Waste Management Plan and to develop mutual understanding relative to details of environmental protection.

Minimize Construction Impacts

Template Date 3-7-17 | Page 19 of 43

The following mitigation measures shall be implemented to minimize the impacts of construction activities:

Soil Erosion: Protect against erosion and topsoil depletion. Storm Water Pollution Prevention Plan required.

Exotic Vegetation and Noxious Weeds: Prevent the introduction and minimize the spread of exotic vegetation and noxious weeds. Incorporate the following procedures:

Any fill, rock, or additional topsoil needed shall be obtained from a Government approved source. All areas disturbed by construction shall be re-vegetated using approved native seed and/or plants.

Visitor Experience: The following mitigation measures shall be incorporated into the action alternatives to minimize the impacts of construction activities on the visitor experience:

• Do not block paths around Carillon.

• Protect visitors from falling debris.

• Do not allow vehicles to idle and create noise or fumes.

• Coordinate with NPS for installation of temporary signage.

Air and Water Pollution Control: Air quality impacts are expected to be temporary and localized. To minimize these impacts, the following actions shall be taken:

• To reduce tailpipe emissions, construction equipment shall not be left idling any longer than is necessary for safety and mechanical reasons.

• To reduce construction dust, water shall be applied to problem areas. Equipment shall be limited to the fenced project area to minimize soil disturbance and dust generation.

• Take all necessary reasonable measures to reduce air and water pollution by any material or equipment used during construction. Keep volatile wastes in covered containers.

• Storm Water Pollution Prevention Plan (SWPPP): Submit a SWPPP according to the applicable State Water Resources Control Board's (SWRCB) requirements to the Contracting Officer for approval. (See Technical Requirements) Before starting construction, the Contractor shall implement the approved SWPPP.

Cultural Resources: An archeological monitor will not be present at the work site. If archeological resources are discovered at the project site, all work in the vicinity of the discovery must stop immediately, and the discovery must be reported to the CO.

2.3.2 Schedule of Values

After contract award and before the Design Meeting, submit a schedule of dollar values based on the Contract Price Schedule. Breakdown each lump-sum item into component parts of design deliverables or construction work for which progress payments may be requested. The total costs for the component parts of work shall equal the contract line item amount for that lump-sum item. The Contracting Officer may request data to verify accuracy of dollar values. Include mobilization, general condition costs, Template Date 3-7-17 | Page 20 of 43 overhead and profit in the total dollar value of unit price items and in the component parts of work for each lump-sum item, as described below. Do not include mobilization, general condition costs, overhead or profit as a separate item.

Do not break down unit price items. Use only the contract line item amount for unit price items.

The total cost of all items shall equal the contract sum. The Schedule of Values will form the basis for progress payments.

An acceptable Schedule of Values shall be agreed upon by the Contractor and Contracting Officer before the first progress payment is processed. A cost loaded project schedule is an acceptable substitute for a schedule of values in some cases.

2.3.3 Construction Support

Staging Areas

Construction sites will be limited to the smallest feasible area. Ground disturbance and site management will be carefully controlled to prevent undue damage to vegetation, soils, and archeological resources and to minimize air, water, soil, and noise pollution.

Staging is limited in or near the construction area for a construction office or trailer. Construction equipment and material storage shall be located in previously disturbed areas near the construction site.

All staging areas shall be returned to pre-construction conditions once construction is complete.

Standards for this, and methods for determining when the standards are met, shall be developed in consultation with the CO.

Structures: Trailers, Storage, Field Offices, Staging Area and Sheds: Location to be approved by the CO.

DBC's Field Office: Field office shall be structurally sound construction, and weather tight. The location will be determined by NPS prior to issuing a Start Work Notice.

Storage Sheds: If used, provide weather tight sheds or other covered facilities for storage of materials subject to weather damage.

If used, all temporary water, sewer, sanitary facilities and electric utilities, shall be completely removed upon project completion. Remove temporary utility connections.

The location of the Staging Area for construction equipment will require CO approval.

Construction Camp: Establishment of a construction camp will not be permitted.

Construction Zones

Construction zones shall be fenced with CO approved construction barrier fencing, plastic or portable fencing, before any construction activity. The fencing shall define the construction zone and confine activity to the minimum area required for construction. All protection measures shall be clearly stated in the construction specifications, and workers will be instructed to avoid conducting activities beyond the construction zone as defined by the construction zone fencing.

Template Date 3-7-17 | Page 21 of 43

Protection of Public: Fence, barricade, or otherwise block off the immediate work area to prevent unauthorized entry. Erect and maintain fencing, barricades, lights, signals, and warning signs in accordance with the most current version of the Manual on Uniform Traffic Control Devices (MUTCD).

The DBC shall protect tree trunks and root systems of trees in or adjacent to work areas.

Special Construction Requirements

Parking of Construction Vehicles Parking of vehicles shall be limited to areas designated by the Contracting Officer, and within approved staging area(s).

Construction Fence Construction fence to include dark privacy netting/scrim that provides approximately 90% visual blockage.

Memorial Scaffolding Exterior face of temporary scaffolding shall have ½” plywood sheathing at the base with minimum 12’ height for added security. Secure scaffolding entry to prevent unauthorized entry. Plywood to be covered with light scrim. See specification section DC B1 Part 3.4.C for additional information.

2.3.4 Submittals During Construction

NPS Project Sustainability Checklist: Complete the construction column of the checklist by concisely explaining how each credit/requirement is met. Indicate what products or actions were installed/performed to comply with each credit/requirement.

Construction Submittals:

Construction Submittal Types

Action Submittals: Written, graphic information, and physical samples that require Government’s responsive action.

• Product Data: Collect information into a single submittal for each element of construction and type of product or equipment

• Shop Drawings: Prepare Project-specific information, drawn accurately to scale. Do not base Shop Drawings on reproductions of the Contract Documents or standard printed data [, unless submittal of CAD Drawings is otherwise permitted].

• Samples: Submit Samples for review of kind, color, pattern, and texture for a check of these characteristics with other elements and for a comparison of these characteristics between submittal and actual component as delivered and installed.

• Construction Materials: The Contractor is encouraged to submit for approval products made out of recycled or environmentally responsible material. Every effort will be made by the National Park Service to approve these materials

Informational Submittals: Written information that does not require Government’s responsive action. Submittals may be rejected for not complying with requirements.

Template Date 3-7-17 | Page 22 of 43

• General: Prepare and submit Informational Submittals required by individual Specification Sections.

• Informational submittals include but are not limited to Coordination Drawings LEED™ Submittals Product Data, Certificates, Test reports, Manufacturer’s instructions, Division 01 Management Plans, etc.

Contractors Review

Review each submittal and check for coordination with other Work of the Contract and for compliance with the Contract Documents. Note corrections and field dimensions.

General Submittal Procedures

Prepare and submit submittals shown in Part 4.0, Technical Requirements. Details on the specific requirements for each can be found in the individual technical sections.

Contracting Officer reserves the right to require submittals in addition to those called for in individual sections.

Coordination: Coordinate preparation and processing of submittals with performance of construction activities. Review them for legibility, accuracy, completeness, and compliance with Contract Documents.

1. Coordinate each submittal with fabrication, purchasing, testing, delivery, other submittals, and related activities that require sequential activity.

2. Partial submittals are not acceptable, will be considered non-responsive, and will be returned without review.

Processing Time: Allow enough time for submittal review, including time for re-submittals. Time for review shall commence when an e-mail notification is received by the Contracting Officer (or designee) indicating the submittal has been posted on the NPS/DSC SharePoint Project website and is ready for review. When the Contracting Officer has completed their review, an e-mail notification will be sent to the Contractor indicating the submittal has been processed. No extension of the Contract Time will be authorized because of failure to transmit submittals enough in advance of the Work to permit processing, including re-submittals.

1. Action Submittals: Allow 30 days for initial review of each submittal. Allow additional time if coordination with subsequent submittals is required.

2. Informational submittals: Allow 10 days for review of each submittal.

Electronic Submittals: Identify and incorporate information in each electronic submittal file as follows:

1. CM-SPE Transmittal Form: All submittals shall be transmitted using National Park Service form CM-SPE form. The form is accessed and completed on the NPS/DSC SharePoint Project website. No action will be taken on a submittal item unless accompanied by the CM- SPE transmittal form.

a. Complete the general information at the top of the form.

b. Provide all required information based on the submittal type

c. Attach all related documents.

Template Date 3-7-17 | Page 23 of 43

d. Sign the CM-SPE form in the contractor section at the bottom of the form, and select “submit” when complete.

2. Physical samples: Complete the CM-SPE on the NPS/DSC SharePoint Project website as described above. Deliver the physical sample to the CO (or designee) on site for processing.

All comments and actions will be documented on the CM-SPE form on the NPS/DSC SharePoint Project website.

Contracting Officer's Review

Action Submittals: Contracting Officer will review each submittal, generate comments on corrections or modifications required, and indicate the appropriate action on the CM-SPE Transmittal Form. The submittal will be marked in one of three ways as defined below:

1. Approved: Acceptable with no corrections.

2. Approved with Notations: Minor corrections or clarifications required. All comments are clear and no further review is required. The Contractor shall address all review comments when proceeding with the work.

3. Disapproved – Resubmit: Rejected as not in accordance with the contract or as requiring major corrections or clarifications. The Contracting Officer will identify the reasons for disapproval. The Contractor shall revise and resubmit with changes clearly identified.

Informational Submittals: Contracting Officer will review each submittal and will either accept or reject them.

Submittal List

An example of a Submittal List has been attached to the end of this section. (The latest version of the Submittal List and Review Estimate template is on the DSC Workflows website, https://www.nps.gov/dscw/publicforms.htm#dt. The intent is to provide an overall summary of submittal requirements and not a comprehensive list. The technical requirements indicate the type and specify submittal requirements. The terms and conditions of the Contract still apply regardless of what is shown on the submittal list.

Use for Construction

Use only final submittals with mark indicating “Approved” or “Approved with notations”. Ensure all notations have been incorporated and, at a minimum, keep one copy of the final approved submittal on site for use during construction

2.3.5 Construction Coordination

Notification: The Contracting Officer (CO) will provide all necessary written notification and/or direction to the contractor. An on-site independent Construction Management Representative (CMR) will co-ordinate the contractor’s construction efforts with the park staff’s daily operations and will transmit and receive correspondence between the Denver Service Center and the DBC. However, the CMR will have no authority to accept or reject work, or to authorize changes to the terms and conditions of the contracts, or to obligate the NPS for time or money.

2.3.6 Digital Images

https://www.nps.gov/dscw/publicforms.htm#dt

Template Date 3-7-17 | Page 24 of 43

Provide 20 existing condition images, and 10 images per week documenting construction. Upload digital images to the NPS DSC SharePoint Project website and identify each set of images with a date, location, title, description, and any other useful information pertinent to the subject captured in the photos.

Take appropriate digital images documenting construction progress and problems, such as capturing items that will not be seen later, etc. Post digital images on a weekly basis, or as directed by Contracting Officer, of each work activity.

2.3.7 Quality Control

General

The quality of all work shall be the responsibility of the Contractor. Testing shall be the responsibility of an independent testing laboratory. Inspect and test all work as needed to ensure that the quality of materials, workmanship, construction, finish, and functional performance is in compliance with applicable specifications and drawings.

Utilize the CQC Accessibility Inspection Report form, https://www.nps.gov/dscw/publicforms.htm#cf, to document compliance with the Architectural Barriers Act (ABA) Accessibility Standards. Inspect at various stages of construction as needed to insure the finished product meets the guidelines. Fill out the applicable sections of the Accessibility Inspection Report and attach to the Quality Control Daily Report.

Quality Control Daily Reports shall be completed by the Quality Control Supervisor.

Test reports shall be completed by person performing the test.

The Contracting Officer may designate locations of tests.

Quality Control Staff The Contractor's Quality Control Supervisor may also perform other duties such as those of Project Superintendent.

The Contractor's designated Quality Control Supervisor shall be on the project site whenever contract work is in progress.

The Contractor's job supervisory staff may be used to assist the Quality Control Supervisor supplemented, as necessary, by additional certified testing technicians.

Testing…

This is the start of the file's text. The full file is on GovTribe.