20180702_GATE_147079A&D_GATE201023B_Hazmat_Remediate_and_Demolish_Excess_Buildings_Specs.pdf

PDF 5 MB Posted

Attached to
GATE 147079 A&D and 201023 B Hazmat Remediate and Demolish Excess Building, FBF, GATE - Jamaica Bay Unit
Solicitation number
140P2018R0043
Issued by

About this file

Specifications

View the file

Other files

Show all 13

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

GATE 147079A&D, 201023B TOC-1

TABLE OF CONTENTS

DIVISION 01 - GENERAL REQUIREMENTS

01 11 00 Summary of Work

01 21 00 Allowances

01 26 01 Contract Modification Procedures

01 27 00 Definition of Contract Line Items

01 31 00 Project Management & Coordination

01 32 16 Construction Schedule

01 32 33 Photo Documentation

01 33 23 Submittal Procedures

01 35 13.22 Archeological Protection

01 35 23 Safety Requirements

01 40 00 Quality Requirements

01 42 00 References

01 50 00 Temporary Facilities and Controls

01 56 39 Temporary Tree & Plant Protection

01 57 19.12 Noise & Acoustics Management

01 57 23 Temporary Stormwater Pollution Prevention

01 73 40 Execution

01 74 19 Construction Waste Management and Disposal

01 74 19A Appendix A

01 74 19B Appendix B

01 77 00 Closeout Procedures

DIVISION 02 – EXISTING CONDITIONS

02 41 13.43 Utility Line Capping

02 41 16 Structure Demolition

02 41 16C Pre-Demolition Checklist

02 81 01 Off-Site Transportation & Disposal

02 82 14 Asbestos Abatement

02 83 13 Lead Paint Abatement

02 84 33 Removal and Disposal of PCB Containing Equipment

02 84 44 Removal and Disposal of Hazardous Waste Materials

DIVISION 31 – EARTHWORK

31 10 00 Site Clearing

31 11 60 Weed Eradication

31 20 00 Earth Moving

31 23 19 Dewatering

32 91 19.13 Salvaged Topsoil

32 92 20 Seeding

GATE 147079A&D, 201023B TOC-2

TABLE OF CONTENTS

APPENDIX A – REPORTS

Final Report of Environmental Investigation Services at Building 69, Floyd Bennett Field, Gateway

National Recreational Area, New York by Louis Berger – October 26, 2017.

Final Report of Environmental Investigation Services at Buildings 69, 129, 130, 131, 132, 133 & Walkway

Pavilion, Floyd Bennett Field, Gateway National Recreational Area, New York by Louis Berger – May 10, 2018.

GATE 147079A&D, 201023B 01 11 00 - 1

SUMMARY OF WORK

SECTION 01 11 00 - SUMMARY OF WORK

PART 1 - GENERAL

1.1 SUMMARY

A. This Section includes the following:

1. Work covered by the Contract Documents.

2. Contractor use of Site.

3. Public use of Site.

4. Occupancy requirements for buildings.

5. Conducts of Operation

6. Work Restrictions.

7. Special Demolition Requirements.

8. Additional Reports.

1.2 WORK COVERED BY CONTRACT DOCUMENTS

A. Location:

1. Park Office: 210 New York Avenue, Staten Island, NY 10305.

2. Project Site: Gateway National Recreation Area, Floyd Bennett Field, NY 11234. Building

69 site is located off Ranger Road adjacent to the US Parks Police Building. Job Corps Buildings are located along Ranger Road to the east of Building 69.

B. The Base Bid Work consists of the following:

1. The Work includes the removal of the Job Corp Buildings; Buildings #129, 130, 131, 132 and 133, adjacent paved parking, basketball court, handball court, fencing, brick wall, concrete sidewalks and appurtenances, including capping and abandoning in place underground utilities, as identified in the plans.

2. Site restoration to existing natural grade and provide a smooth transition between new and existing grade to maintain pre-demolition drainage patterns. Contractor shall take select survey shots to ensure proper drainage to existing drainage structures. Site restoration includes a 180 day maintenance period for native seed mix establishment.

C. The Bid Option A Work consists of the following:

1. The Work includes the removal of Building #69, adjacent paved parking, concrete sidewalks and appurtenances, including capping and abandoning in place underground utilities, as identified in the plans.

2. The Contractor is responsible to include the allowance sum of $100,479.82: For the Contractor and Verizon coordination, modification and installation of underground communication cabling as required to disconnect Verizon service to Building 69 and maintain service to Building 70 (EcoVillage) and Building 258 (Autoshop). Refer to 1.5.A of this section and Section 01 21 00 “Allowances”.

GATE 147079A&D, 201023B 01 11 00 - 2

3. Site restoration to existing natural grade and provide a smooth transition between new and existing grade to maintain pre-demolition drainage patterns. Contractor shall take select survey shots to ensure proper drainage to existing drainage structures. Site restoration includes a 180 day maintenance period for native seed mix establishment.

D. Project will be constructed under a single prime contract.

E. Wildlife: Prior to beginning work, Contractor shall conduct an inspection with the GATE Biologist to identify any wildlife or migratory birds that may be present.

1. The Contractor shall be aware that Building 69 has been subject to infestation by raccoons in the past and that raccoons are expected to be currently present. The Contractor is responsible for the removal of raccoon damage and fecal matter, specifically within but not limited to the attic space as further detailed in the hazardous material specification sections.

The Contractor shall be required to verify the presence of raccoons, and to trap and humanely remove any that exist in the building prior to demolition activities.

2. Raccoon relocation shall be coordinated with the GATE wildlife biologist and shall occur on the Floyd Bennett Field Property. The Park will provide a designated area for the release of any relocated raccoons.

F. Vegetation: The existing vegetation and stumps within limits of disturbance shall be completely removed and properly disposed of. Existing trees shall be protected and saved are noted on the plans.

Contractor shall protect trees per detail prior to demolition activities.

1.3 CONTRACTOR USE OF SITE

A. General: Contractor shall contain all demolition work, equipment and personnel within the limits of disturbance.

B. Storage of Materials: Confine storage of materials to the staging area as shown on the demolition drawings or as directed by the Contracting Officer. Contractor site office trailer anticipated to be located adjacent to the Job Corps Buildings near Building 74. Water and electrical services are best available at this location.

C. Preservation of Natural Features:

1. Prevent damage to natural surroundings by staying within the limits of disturbance. If contractor causes damage, contractor shall restore damaged areas, repairing or replacing damaged trees and plants, at no additional expense to the Government.

2. Contractor shall limit vegetation removal to within the limits of disturbance identified on the drawings.

3. Provide temporary barriers to protect existing trees to be preserved.

4. Protect Trees and vegetation from damage caused by runoff or spillage of noxious materials. If spill occurs, Contractor shall remediate soil immediately and follow regulations stated in Section 01 31 00 1.8.D.2.

5. Do not fasten ropes, cables, or guys to existing trees.

6. Exercise caution when excavating, grading, filling, and other demolition operations near trees shall be preserved to avoid damage.

D. Driveways and Entrances: Keep driveways and entrances serving premises clear and available to Government, Government's employees, and emergency vehicles at all times. Do not use these areas for parking or storage of materials.

GATE 147079A&D, 201023B 01 11 00 - 3

1. Schedule deliveries to minimize use of driveways and entrances.

2. Schedule deliveries to minimize space and time requirements for storage of materials and equipment on-site.

3. Coordinate any additional areas needed for staging with the Contracting Officer.

E. Construction Camp: Establishment of a camp within the park will not be permitted.

F. Hauling Restrictions: Comply with all legal load restrictions in the hauling of materials. Load restrictions on park roads and bridges are identical to the state loads, NYDOT load restrictions.

Information regarding rules and regulations for vehicular traffic on park roads may be obtained from the Park Police/Law Enforcement. A special permit will not relieve Contractor of liability for damage which may result from moving of equipment.

G. Parking Restrictions: In the Staging Areas, within limit of disturbance, as shown on the contract drawings or/as directed by the Contracting Officer.

1.4 PUBLIC USE OF SITE

A. Contractor shall at all times conduct his operations within the limits of disturbance. Public Access within the Limits of Disturbance will be prohibited during demolition operations. Unanticipated road closures will not be permitted.

Road Closure of Enterprise Avenue adjacent to the Job Corps Buildings will be allowed by the Park to facilitate construction traffic and operations. Advanced warning signs and barricades in accordance with the latest version of the Manual on Uniform Traffic Control Devices (MUTCD) shall be placed if Contractor choses to close the roadway. Temporary Closure measures shall be provided by the Contractor at no additional cost to the Government.

1.5 UTILITY FEES

A. The Contractor is responsible to obtain and pay for all utility permits, fees and inspections whether temporary or permanent. Contractor is also responsible to include in the bid amount any costs associated with work by Utility Companies.

B. The Contractor is responsible to include the sum of $100,479.82: For the coordination, modification and installation of underground communication cabling as required to disconnect Verizon service to Building 69 and maintain service to Building 70 (EcoVillage) and Building 258 (Autoshop). Through coordination with Park Staff, the understanding is that a 200 pair copper communications cable enters the Building 69 data closet by direct burial via a handhole on the southwest corner of the building.

Two 25 pair copper communication cables extend from the 200 pair copper cable via direct burial to a handhole serving Building 70 (EcoVillage) and Building 258 (Autoshop). The Verizon ID for the cable feeding Building 69 is “Cable B 8590 F, Pairs 1801-2000”. Coordination with Verizon regarding the work effort required to maintain service resulted in several potential splicing and relocation options, resolution of these options was not finalized by Verizon. Refer to Division 01 Section “01 21 00 Allowances”. Coordinate with Verizon for the performance of the designated utility company scope of work. Verizon contacts are as follows:

GATE 147079A&D, 201023B 01 11 00 - 4

Verizon Fitzgerald Porsenna OSP Core Design Engineering 395 Flatbush Avenue Ext, 3rd Floor Brooklyn, NY 11201 Office: 917-246-5404 Mobile: 437-229-6955

Verizon Michael Dawson Sr. Manager Wireline Network - Regional Business Customer Care 395 Flatbush Ave. Ext., Floor 7 Office: 917 246 - 5161 Mobile: 917 623 - 9297 mike.b.dawson@verizon.com

1.6 OCCUPANCY REQUIRMENTS FOR BUILIDINGS

A. Existing Buildings

1. Partial Government Occupancy: Government will not occupy the premises during demolition period, with the exception of an emergency. Cooperate with Government during demolition operations to minimize conflicts and facilitate emergency access.

Maintain existing travel way exits, unless otherwise indicated.

1.7 CONDUCT OF OPERATIONS

A. At all times the Contractor shall conduct his operations in conformance with the rules and regulations promulgated by the Secretary of the Interior for the National Park Service, and applicable park rules and regulations prescribed by the Park Superintendent.

B. Work on Saturdays, Sundays, Federal holidays or at night may not be performed without prior consent from the Contracting Officer. Submit requests 48 hours in advance of the work to the Contracting Officer for approval.

C. No signs or advertisements (except those specified herein) shall be displayed on the construction site or within the park unless approved by the Contracting Officer.

1. NPS will provide language to Contractor for signage.

2. Equipment: Signage must be displayed on each piece of equipment by the Contractor.

1.8 WORK RESTRICTIONS

A. On-Site Work Hours: Work shall be generally performed from 7am to 5pm, Monday through Friday, except when otherwise indicated. Contractor shall obtain written permission for work outside these hours.

GATE 147079A&D, 201023B 01 11 00 - 5

1. Weekend Hours: Weekend work will not be permitted, unless otherwise indicated by the Contracting Officer.

2. The staging and waste stockpile area is shown on the plans. Refueling shall be allowed only in the designated refueling area as shown on the plans or as designated within the Contractor’s SWPPP. Best Management Practices (BMPs) for refueling area detailed in the Contractor’s SWPPP shall comply with New York Department of Environmental Conservation regulations and rules.

B. Existing Utilities

1. Existing Utilities: Contractor shall be responsible for coordinating all utility shutoffs with the Park and National Grid prior to demolition.

2. Notify Contracting Officer and utility company of proposed locations and times for demolition.

a. Call Dig Safely NY – 811 prior to beginning work on utility lines. Dig Safely NY shall identify exact locations of utilities being removed or capped.

3. The Contractor shall engage a private underground utility line locating company to confirm underground utilities.

4. Contractor shall be responsible for preventing damage to known utilities. If damage occurs, repair utility at no additional expense to the Government.

5. If damage occurs to an unknown utility, repair utility. An equitable adjustment will be made in accordance with the Changes clause of the contract.

6. The existing electrical service shall be disconnected from Building 74 vault to Building

132A vault. Contractor will install live end caps in new manhole 10A outside of Building

74. Contractor shall have electrician familiar with high voltage splicing on team to coordinate with GATE facility manager to accomplish disconnect.

7. NPS owns the medium voltage distribution system at Floyd Bennett Field. There is no utility company except at several locations where the utility company provides power to the entire site. Work to the distribution system will be completed by the Contractor.

C. Existing Utility Interruptions: Do not interrupt utilities serving facilities occupied by Government or others unless permitted by the Government or the Contracting Officer. Any utility shutdown shall occur at night and be accomplished in a two (2) hour shutdown period. A one (1) week notice shall be provided for coordination with the Park.

D. Smoking or Vaping on Project Site: If desired, the Contractor may set up an area for smoking tobacco or vaping products in the staging area, which shall include a designated disposal area and fire safety measures and must be approved by the Contracting Officer. All smoking or vaping on site shall be confined to this area.

E. Noise: No loud music is allowed on site. See Section 01 57 19.12 “Noise and Acoustic Management” for acceptable decibel levels and durations for noise on site.

1.9 SPECIAL DEMOLITION REQUIREMENTS

A. Project Website: A project website administered by the NPS will be used for purposes of managing communication and documents during the demolition work.

GATE 147079A&D, 201023B 01 11 00 - 6

1. See Section 01 31 00 “Project Management and Coordination” for requirements on using the Project Website.

B. Archaeological Monitoring – Archeological monitoring of the project will be necessary for the removal of Building 69. 1. During the removal of the parking lot and 2. In any locations where 5 feet or more of excavation is anticipated. The Contractor shall notify the CO and Archeologist at least 2 weeks in advance of beginning this work, and work with the CO and Archeologist to ensure that the Archeologist can be on site during this work. Do not begin the work until the Archeologist is on site for the archeological monitoring. The Government will provide the archeological monitor for Building 69. This monitor will be contracted through NPS with NRAP acting as the COR. Job Corp Buildings 129, 130, 131, 132 and 133 including site areas will not require archeological monitoring however NPS NRAP reserves the right to archeologically inspect demolition activities below grade at any time. Should significant resources be unintentionally uncovered within the Job Corps demolition area work shall stop in that area immediately and the Park and NRAP consulted.

C. No blasting or use of explosives may be used on the site for demolition or any other purpose.

D. Salvage/Recycle Requirements:

1. Building 69.

a. Onan 250KvA Generator and Above Ground Fuel Storage Tank shall be salvaged.

The Park will pick this generator up at the site upon removal by Contractor.

Contractor shall coordinate with CO.

b. Building 69 Flagpole

c. Two wood framed sheds shall be salvaged and moved by the Contractor within

Floyd Bennett Field property, location shall be coordinated with CO.

d. Items to be salvaged and turned over to GATE’s curator at FOWA in Staten Island prior to demolition. Memo of items follows this spec section. Contractor shall verify list of items to be salvaged with CO prior to beginning any demolition. Contractor shall wrap and package materials to prevent damage to the salvaged items during delivery, coordinate with CO for specific requirements.

1) Door to Attic.

2) “69” Sign from exterior of building.

3) A single brick from the interior of the fireplace.

4) A single brick from the exterior of the fireplace.

1.10 ADDITIONAL REPORTS

A. Final Report of Environmental Investigation Services at Building 69, Floyd Bennett Field, Gateway National Recreational Area, New York by Louis Berger – October 26, 2017

B. Final Report of Environmental Investigation Services at Buildings 69, 129, 130, 131, 132, 133 & Walkway Pavilion, Floyd Bennett Field, Gateway National Recreational Area, New York by Louis Berger – May 10, 2018

C. A copy of these reports are available to all plan holders with this package.

GATE 147079A&D, 201023B 01 11 00 - 7

PART 2 - PRODUCTS (Not Used)

PART 3 - EXECUTION (Not Used)

END OF SECTION 01 11 00

GATE 147079A&D, 201023B 01 21 00 - 1

ALLOWANCES

SECTION 01 21 00 - ALLOWANCES

PART 1 - GENERAL

1.1

A.

RELATED DOCUMENTS

Drawings and general provisions of the Contract, including General and Supplementary

Conditions and other Division 01 Specification Sections, apply to this Section.

1.2

SUMMARY

A. Section includes administrative and procedural requirements governing allowances.

1. Certain items are specified in the Contract Documents by allowances. Allowances have been established in lieu of additional requirements and to defer selection of actual materials and equipment to a later date when direction will be provided to the Contractor.

If necessary, additional requirements will be issued by Change Order.

B. Types of allowances include the following:

1. Lump-sum allowances.

C. Related Sections:

1. Divisions 02 through 49 Sections for items of Work covered by allowances.

1.3

SELECTION AND PURCHASE

A. At the earliest practical date after award of the Contract, advise Contracting Officer of the date when final selection and purchase of each product or system described by an allowance must be completed to avoid delaying the Work.

B. At Contracting Officer’s request, obtain proposals for each allowance for use in making final selections. Include recommendations that are relevant to performing the Work.

C. Purchase products and systems selected by Contracting Officer from the designated supplier.

1.4

SUBMITTALS

A. Submit proposals for purchase of products or systems included in allowances, in the form specified for Change Orders.

B. Submit invoices or delivery slips to show actual quantities of materials delivered to the site for use in fulfillment of each allowance.

C. Submit time sheets and other documentation to show labor time and cost for installation of allowance items that include installation as part of the allowance.

GATE 147079A&D, 201023B 01 21 00 - 2

D. Coordinate and process submittals for allowance items in same manner as for other portions of the Work.

1.5 COORDINATION

A. Coordinate allowance items with other portions of the Work. Furnish templates as required to coordinate installation.

1.6 LUMP-SUM ALLOWANCES

A. Allowance shall include cost to Contractor of specific products and materials ordered by Owner or selected by Architect under allowance and shall include applicable taxes, freight, and delivery to Project site.

B. Unless otherwise indicated, Contractor's costs for receiving and handling at Project site, labor, installation, overhead and profit, and similar costs related to products and materials under allowance shall be included as part of the Contract Sum and not part of the allowance.

C. Unused Materials: Return unused materials purchased under an allowance to manufacturer or supplier for credit to Government, after installation has been completed and accepted.

1. If requested by Contracting Officer, retain and prepare unused material for storage by Government. Deliver unused material to Government's storage space as directed.

1.7 ADJUSTMENT OF ALLOWANCES

A. Allowance Adjustment: To adjust allowance amounts, prepare a Change Order proposal based on the difference between purchase amount and the allowance, multiplied by final measurement of work-in-place where applicable. If applicable, include reasonable allowances for cutting losses, tolerances, mixing wastes, normal product imperfections, and similar margins.

1. Include installation costs in purchase amount only where indicated as part of the allowance.

2. If requested, prepare explanation and documentation to substantiate distribution of overhead costs and other margins claimed.

3. Submit substantiation of a change in scope of work, if any, claimed in Change Orders related to unit-cost allowances.

4. Owner reserves the right to establish the quantity of work-in-place by independent quantity survey, measure, or count.

B. Submit claims for increased costs because of a change in scope or nature of the allowance described in the Contract Documents, whether for the purchase order amount or Contractor's handling, labor, installation, overhead, and profit.

1. Do not include Contractor's or subcontractor's indirect expense in the Change Order cost amount unless it is clearly shown that the nature or extent of work has changed from what could have been foreseen from information in the Contract Documents.

2. No change to Contractor's indirect expense is permitted for selection of higher- or lower-priced materials or systems of the same scope and nature as originally indicated.

GATE 147079A&D, 201023B 01 21 00 - 3

PART 2 - PRODUCTS (Not Used)

PART 3 - EXECUTION

3.1 EXAMINATION

A. Examine products covered by an allowance promptly on delivery for damage or defects. Return damaged or defective products to manufacturer for replacement.

3.2 PREPARATION

A. Coordinate materials and their installation for each allowance with related materials and installations to ensure that each allowance item is completely integrated and interfaced with related work.

3.3 SCHEDULE OF ALLOWANCES

A. Allowance No. 1: Lump-Sum Allowance: Include the sum of $100,479.82: For the coordination, modification and installation of underground communication cabling as required to disconnect Verizon service to Building 69 and maintain service to Building 70 (EcoVillage) and Building 258 (Autoshop). Through coordination with Park Staff, the understanding is that a 200 pair copper communications cable enters the Building 69 data closet by direct burial via a handhole on the southwest corner of the building. Two 25 pair copper communication cables extend from the 200 pair copper cable via direct burial to a handhole serving Building 70 (EcoVillage) and Building 258 (Autoshop). The Verizon ID for the cable feeding Building 69 is “Cable B 8590 F, Pairs 1801-2000”. Coordination with Verizon regarding the work effort required to maintain service resulted in several potential splicing and relocation options, resolution of these options was not finalized by Verizon. Coordinate with Verizon for the performance of the designated utility company scope of work. Verizon contacts are as follows:

Fitzgerald Porsenna OSP Core Design Engineering 395 Flatbush Avenue Ext, 3rd Floor Brooklyn, NY 11201 Office: 917-246-5404 Mobile: 437-229-6955

Michael Dawson Sr. Manager Wireline Network - Regional Business Customer Care 395 Flatbush Ave. Ext., Floor 7 Office: 917 246 - 5161 Mobile: 917 623 - 9297 mike.b.dawson@verizon.com

1. This allowance includes all costs associated with the utility company’s services for the project.

END OF SECTION 01 21 00

GATE 147079A&D, 201023B 01 26 01 - 1

CONTRACT MODIFICATION PROCEDURES

SECTION 01 26 01 – CONTRACT MODIFICATION PROCEDURES

PART 1 - GENERAL

1.1 SUMMARY

A. The work of this section consists of administrative and procedural requirements for contract modifications.

1.2 DEFINITIONS AND ALLOWANCES

A. Home Office Overhead: Those costs incurred in support of all of a contractor’s projects and not attributable to a specific job. The cost for home office overhead is only allowed as a percentage of all direct work excluding profit. The following items represent allowable home office overhead costs identified in Part 31 of the Federal Acquisition Regulation (FAR):

1. Rent

2. Utilities

3. Furnishings

4. Office equipment

5. Executive and management staff not exclusively assigned to the project

6. Support, accounting, and administrative staff

7. Preparation of cost proposals, estimating, and schedule analyses connected with

Modifications

8. Estimating and pre-demolition services

9. Mortgage costs

10. Real estate and corporate taxes

11. Automobile maintenance and travel costs for home office personnel

12. Home office insurances i.e. structure, automotive, umbrella, flood, etc.

13. Depreciation of equipment and other assets

14. Home office supplies (paper, staples, etc.)

15. Legal services

16. Accounting and data processing

17. Professional fees/registration

B. General Conditions (Field Office Overhead): Management and administrative costs incurred on site for the designated project. Costs associated with the preparation of modifications will not be allowed. The costs for these items shall be included only in the general conditions of the modification estimate. Only in the case of a contract time extension are additional general conditions included in modifications. The following items, if applicable, are considered allowable costs for calculating General Conditions:

1. Project Manager, Assistant Project Manager

2. Superintendent, Assistant Superintendent

3. Quality Control, Safety Officer, Environmental Manager, etc.

4. Engineers

5. Travel, lodging, and per diem (as established by Federal Travel Regulations)

GATE 147079A&D, 201023B 01 26 01 - 2

6. Scheduling

7. Field Office Trailers and associated temporary utilities

8. Field office supplies

a. Mailing and couriers

b. Reproduction costs

c. Storage

d. Phones

e. Computers

f. Copiers

9. Personal vehicles i.e. Superintendent Pickup trucks

C. General Requirements: These are costs directly associated with the project and are necessary to perform the actual work of the modification. These costs shall be shown as direct costs in the estimate. The following items, if applicable, are considered allowable costs for calculating General Requirements:

1. Hoisting

2. Material handling

3. Temporary fencing

4. Port-a-lets

5. Trash removal, dumpsters

6. Barricades

7. Small tools

8. Safety supplies

9. Scaffolding

10. Daily cleaning

11. Traffic control

12. Temporary signage

13. Temporary heating and power

D. Personnel Costs: Costs included in the modification must only be for General Conditions staff and workers actually present and working on the project site. Modification costs for salaried workers are only allowed within the structure of a 40 hour week and no overtime or holiday pay will be allowed.

1. Worker Hourly Rates are costs directly associated with the individual worker and consist of the following:

a. Base Rate: This is the hourly rate paid directly to the worker

b. Labor Burden: Employer payments of all applicable burdens, this includes insurance and taxes that the business must pay on behalf of the worker to government entities and educational forums , such as:

1) Social Security

2) Medicare

3) Workers Compensation– Policy and company calculation shall be made available.

4) FUTA– Cap Rate and percentage shall be proportionally allocated over one year.

5) SUTA– Cap Rate and percentage shall be proportionally allocated over one year.

GATE 147079A&D, 201023B 01 26 01 - 3

6) Union agreement costs – Other costs required under an enforceable collective bargaining agreement.

c. Fringe Benefits: Various non-wage compensations provided to employees such as:

1) Health Care Insurance Premiums

2) Cell Phone

3) Clothing

4) 401K and Pensions

5) Vehicle allowances

6) Gas allowance

7) Life insurance premiums

8) Disability insurance

9) Other Fringe Benefits required under an enforceable collective bargaining agreement

E. Bonuses or Deferred Compensation: No Bonus or Deferred Compensation will be allowed within any components of pricing including Home Office Overhead, General Conditions, General Requirements, Hourly Worker Rates, or the direct costs of work.

F. General Liability Insurance: An insurance policy that protects the contractor from claims resulting from bodily injury or property damage to a third party. Include this as a separate line item within all modification proposals and provide a current insurance quote upon request.

G. Performance and Payment Bonds: A performance bond is a surety bond issued by an insurance company or bank to guarantee satisfactory completion of a project. The Payment Bond guarantees that the contractor will pay the labor and material costs they have incurred. Banks and Insurance companies charge a premium for each individual project based on a sliding scale which relates to the size of the project. Include this as a separate line item in modification proposals and provide current company bonding rates upon request.

H. Builder’s Risk Insurance: This covers the contractor’s loss due to fire, high winds, or other natural forces. This is not reimbursed by the National Park Service (NPS) and shall not be included in modification proposals.

1.3 MODIFICATION PROPOSAL PRICING REQUIREMENTS

A. General:

1. Your proposal must be received in the format and within the time frame specified in the Request for Proposal letter. Costs or delays resulting from failure of contractor to submit within the time frame specified will not be compensable.

2. The proposal must be detailed with itemized lists of equipment, materials, labor, production rates, overhead, profit, and bond markup for each item. Labor costs must be itemized by craft and hourly rate, including Fringe Benefits and Labor Burden. If the costs of Fringe Benefits and Labor Burden are not itemized, it is assumed that that they are included in the hourly rate shown, or contractor is not requesting reimbursement.

Contractor may utilize the government provided Contractor Estimate Form, or their

GATE 147079A&D, 201023B 01 26 01 - 4

own form, provided that it contains the same information and level of detail as the Gov’t provided form.

3. Requests for extensions of contract time as a result of this change must be justified with a Time Impact Analysis (TIA). Refer to Section 01 32 16 “Construction Schedule”, for time impact analysis requirements. TIA and associated costs must be received with the proposal by the date shown within the Request for Proposal letter. Contractor’s failure to submit within the specified time frame will be construed as the Contractor waiving the right for additional time and no time extension will be allowed.

4. All supporting documentation used to justify the proposed modification will be made available to the Contracting Officer upon request.

5. Contractor must review and approve all subcontractor/supplier pricing in detail for proper format, scope, production rates, and pricing prior to submission to the NPS. All delay costs associated with not reviewing and approving subcontractor/supplier pricing will be borne by the Contractor.

6. All pricing and production rates within the estimate must be based on fair and reasonable pricing and cannot include built-in contingency.

B. Labor:

1. Contractor shall estimate the cost of labor by itemizing each craft involved, indicating worker hourly rate (base rate + labor burden + fringe benefits) for each and itemizing the hours required for each craft that will be directly engaged in modification work.

Any work proposed that will require overtime work or premium pay shall be itemized separately. All rates shall be in accordance with the Davis-Bacon Act as incorporated herein. Labor Burden may include payroll taxes, Social Security, unemployment insurances, workers compensation insurance, FICA, FUTA, and other direct costs resulting from Federal, State or local laws.

2. Itemize labor costs for equipment operators separate from equipment costs.

3. The labor cost for foremen shall only be costs for related work required for the modification.

C. Materials:

1. The estimated cost for materials shall include quotes from multiple sources. Material prices must include all applicable fees and credits, including but not limited to, sales tax, freight and delivery charges, and tax rebates.

2. No markup shall be applied to any material provided by the NPS.

D. Equipment:

1. Equipment used for the project must be appropriately sized for the work being performed.

2. Do not include costs for “miscellaneous tools and equipment”, in your proposal for a replacement value of $500 or less. Costs shown in excess of $500 must be broken out separately.

3. Regardless of ownership, the rates to be used in determining equipment rental costs shall be the lowest cost from one of the following sources:

a. U.S. Army Corps of Engineers , Ownership and Operating Expense Schedule (use latest edition and applicable region)

b. Construction Blue Book

GATE 147079A&D, 201023B 01 26 01 - 5

c. Local equipment rental rates, documented by actual invoice charges, or itemized vendor quotes.

4. The estimated equipment rates shall include the operating costs of all fuel, oil, lubrication, supplies, small tools, necessary attachments, ground engaging components, tires & tracks, routine repairs and maintenance (cost of major repair and overhaul is not allowed per FAR 31.105(d)(2)), depreciation, storage, insurance, and all incidentals.

Mobilization, if applicable, may be included for equipment solely used on the modification work but must be listed separately.

5. Estimate the full rate for equipment only for the duration that the equipment will be utilized to accomplish the work of the modification.

6. Standby unit rates used shall be in accordance with paragraph 1.3, D, 2, above. If the US Army Corp of Engineers is utilized then their standby rates prevail. If Bluebook or local equipment pricing is accepted, then ½ of the equipment costs minus any operating costs, major repair and overhaul will be accepted.

7. If equipment is in standby mode due solely to a documented NPS delay, the established standby rate shall apply from the first day of the delay.

8. Equipment that is not used and on the jobsite for up to five consecutive days may be classified at standby rates, provided that the equipment is or has been used solely to perform work on the modification and will be necessary to complete additional modification work. Equipment that is still on the jobsite but not in use after five consecutive days will not be considered in the modification pricing.

9. Requests for compensation for equipment stand by time must be justified, documented and itemized separately.

10. The estimated timeframe (daily, weekly, monthly) for use of the equipment must reflect the lowest cost to the Government.

E. Establishment and Application of Overhead and Profit Percentages:

1. Home Office Overhead and Profit (OH&P) shall be applied to direct costs only. Profit shall not be applied to overhead amounts; and overhead shall not be applied to profit.

Home office overhead shall contain only allowable, allocable, and reasonable costs per the contract documents and FAR Part 31. Profit percentages are based on risk factors found in FAR Part 31which have been applied to the specific type of work included in this project. Negotiated rates shall not exceed the following percentages for OH&P for contractor self-performed work:

Overhead………………10% Profit……………………8.25%

2. Total aggregate limit of markup (OH&P) for contractor and subcontractors on modification work shall not exceed 25%. The NPS will not be responsible for allocation of percentages between contractor and subcontractors at any tier.

3. If contractors form a partnership, then the partnership may only receive home office overhead and profit in the same amount as an individual contractor (refer to par 1.3,E,1 above). It is the responsibility of the partners to decide on the division of revenue.

4. Combined Increases and Decreases: On proposals involving both increases and decreases in the Contract Price, the overhead and profit mark-ups are required on the net increases and deducted on net decreases.

5. At no time can profit be calculated on Overhead or itself, it must be calculated on direct costs of work only.

GATE 147079A&D, 201023B 01 26 01 - 6

PART 2 - PRODUCTS

PART 3 - EXECUTION

END OF SECTION 01 26 01

GATE 147079A&D, 201023B 01 27 00 - 1

DEFINITION OF CONTRACT LINE ITEMS

SECTION 01 27 00 – DEFINITION OF CONTRACT LINE ITEMS

PART 1 - GENERAL

1.1 SUMMARY

A. The intent of this section is to explain, in general, what is and what is not included in a contract line item, and the limits or cut-off points where one item ends and another begins.

B. If no contract line item exists for a portion of the work, include the costs in a related item.

PART 2 - PRODUCTS (Not Used)

PART 3 - EXECUTION

3.1 LIST OF CONTRACT LINE ITEMS

A. Contract Line Bid Item: 1 Building 129 Demolition.

1. This item consists of the hazardous material abatement, demolition and removal of a one story brick faced building with 15-20 foot ceilings and backfilling foundation and crawl space identified as Building #129 Administration/Cafeteria (15,352 SF), located along Ranger Road adjacent to the intersection of Enterprise Avenue at Floyd Bennett Field, and appurtenances, including but not limited to a covered walkway pavilion to Buildings 130, 131 and 132. (Walkway pavilion is a concrete roof structure with brick faced columns and concrete slab and foundation).

Removal includes slabs and below-grade construction, including basements/crawl spaces, exterior foundation walls/grade beams and other appurtenances in their entirety. If encountered pile caps and piles supporting grade beams shall be abandoned in place.

Contractor shall be aware of the possibility of recycling the following items:

a. CMU

b. Bricks

c. Wires

d. Concrete

e. Pipes

f. Pavement

g. Steel Railing, Rebar, Utility Ducting & Piping

h. Wood framing

B. Contract Line Bid Item: 2 Building 130 Demolition.

This item consists of the hazardous material abatement, demolition, removal and backfilling of foundation of Building 130. Building 130 (Dorms/Barracks) is a two story brick faced building (15,180 SF) with a flat pitched roof. Building is anticipated to be

GATE 147079A&D, 201023B 01 27 00 - 2

founded on slab on grade with foundation walls anticipated at a five (5) foot depth.

Building removal shall also include fire escapes and other building appurtenances.

Removal includes slabs and below-grade construction, exterior foundation walls/grade beams and other appurtenances in their entirety. If encountered pile caps and piles supporting grade beams shall be abandoned in place.

Contractor shall be aware of the possibility of recycling the following items:

a. CMU

b. Bricks

c. Wires

d. Concrete

e. Pipes

f. Pavement

g. Steel Railing, Rebar, Utility Ducting & Piping

h. Wood/Steel framing

C. Contract Line Bid Item: 3 Building 131 Demolition.

This item consists of the hazardous material abatement, demolition, removal and backfilling of foundation of Building 131. Building 131 (Dorms/Barracks) is a two story brick faced building (15,180 SF) with a flat pitched roof. Building is anticipated to be founded on slab on grade with foundation walls anticipated at a five (5) foot depth.

Building removal shall also include fire escapes and other building appurtenances.

Removal includes slabs and below-grade construction, exterior foundation walls/grade beams and other appurtenances in their entirety. If encountered pile caps and piles supporting grade beams shall be abandoned in place.

Contractor shall be aware of the possibility of recycling the following items:

a. CMU

b. Bricks

c. Wires

d. Concrete

e. Pipes

f. Pavement

g. Steel Railing, Rebar, Utility Ducting & Piping

h. Wood/Steel framing

D. Contract Line Bid Item: 4 Building 132 Demolition.

This item consists of the hazardous material abatement, demolition, removal and backfilling of foundation of Building 132. Building 132 is a one story brick faced building (1,320 SF) that housed laundry facilities in the front half and an electrical transformer room (Building 132A) this is still active in the back half. This item also includes disconnect and removal of the existing electrical transformer and appurtenances. Building is anticipated to be founded on slab on grade with foundation walls anticipated at a five (5) foot depth.

Removal includes slabs and below-grade construction, exterior foundation walls/grade beams and other appurtenances in their entirety. If encountered pile caps and piles supporting grade beams shall be abandoned in place.

GATE 147079A&D, 201023B 01 27 00 - 3

Contractor shall be aware of the possibility of recycling the following items:

a. CMU

b. Bricks

c. Wires

d. Concrete

e. Pipes

f. Pavement

g. Steel Railing, Rebar, Utility Ducting & Piping

h. Wood/Steel framing

E. Contract Line Bid Item: 5 Building 133 Demolition.

This item consists of the hazardous material abatement, demolition, removal and backfilling of foundation of Building 133. Building 133 is a one story brick faced building (1,100 SF) that served as the Physical Plant/Boiler building. Building is anticipated to be founded on slab on grade with foundation walls anticipated at a five (5) foot depth.

Removal includes slabs and below-grade construction, exterior foundation walls/grade beams and other appurtenances in their entirety. If encountered pile caps and piles supporting grade beams shall be abandoned in place.

Contractor shall be aware of the possibility of recycling the following items:

a. CMU

b. Bricks

c. Wires

d. Concrete

e. Pipes

f. Pavement

g. Steel Railing, Rebar, Utility Ducting & Piping

h. Wood/Steel framing

F. Contract Line Bid Item: 6 Site Demolition for Job Corps

This item consists of the demolition and removal of site elements associated with the Job Corps Buildings 129, 130, 131, 132 and 133 site area. Demolition and removal shall include paved parking lot areas, basketball and handball courts, basketball court wood shade pavilions, fencing, picnic tables, brick wall along Enterprise Ave, concrete sidewalk, slabs and misc. site features and items within the limit of disturbance as detailed within the plans or as directed. Contractor shall be aware of the possibility of recycling the following items:

a. CMU

b. Bricks

c. Wires

d. Concrete

e. Pavement

f. Steel Railing, Rebar, Utility Ducting & Piping

GATE 147079A&D, 201023B 01 27 00 - 4

G. Contract Line Bid Item: 7 Site Restoration for Job Corps.

1. This item consists of the site restoration required subsequent to the demolishing of

Buildings 129, 130, 131, 132 and 133 and associated appurtenances and site features. Site restoration shall include backfill, concrete curbing, grading, topsoil and seeding to return the site to natural conditions. Site restoration includes a 180 day maintenance period for native seed mix establishment.

H. Contract Line Bid Item: 8 Building 69 Demolition. (Bid Option A)

1. This item consists of the hazardous material abatement, demolition and removal of two story building with attic and backfilling of foundation and crawl space identified as Building #69 (17,180 SF), located along Ranger Road adjacent to the U.S. Park Police Building at Floyd Bennett Field, and appurtenances, including but not limited to a covered breezeway (a wood frame roof structure with concrete block columns and concrete foundation).

Removal includes slabs and below-grade construction, including basements/crawl spaces, exterior foundation walls/grade beams to two (2) feet below grade. Concrete slabs located in mechanical room shall be completely removed. Interior concrete grade beams supporting building shall be completely removed to depth. Pile caps and piles supporting grade beams shall be abandoned in place.

Building removal shall also include wildlife (raccoon) removal as required, generator salvage, paved parking lot areas, concrete sidewalk, handicap ramp, concrete stairs and items within the limit of disturbance as detailed within the plans or as directed. Contractor shall be aware of the possibility of recycling the following items:

a. CMU

b. Bricks

c. Wires

d. Concrete

e. Pipes

f. Pavement

g. Steel Railing, Rebar, Utility Ducting & Piping

h. Wood framing

I. Contract Line Bid Item: 9 Site Restoration for Building 69 (Bid Option A)

1. This item consists of the site restoration required subsequent to the demolishing of Building

#69 and associated appurtenances and site features. Site restoration shall include backfill, grading, topsoil and seeding to return the site to natural conditions. Site restoration includes a 180 day maintenance period for native seed mix establishment.

J. Contract Line Bid Item: 10 Site Telecom Utilities Building 69 Allowance (Bid Option A)

1. Lump-Sum Allowance: Include the sum of $100,479.82: For the Contractor and Verizon coordination, modification and installation of underground communication cabling as required to disconnect Verizon service to Building 69 and maintain service to Building 70

GATE 147079A&D, 201023B 01 27 00 - 5

(EcoVillage) and Building 258 (Autoshop). Through coordination with Park Staff, the understanding is that a 200 pair copper communications cable enters the Building 69 data closet by direct burial via a handhole on the southwest corner of the building. Two 25 pair copper communication cables extend from the 200 pair copper cable via direct burial to a handhole serving Building 70 (EcoVillage) and Building 258 (Autoshop). The Verizon ID for the cable feeding Building 69 is “Cable B 8590 F, Pairs 1801-2000”. Coordination with Verizon regarding the work effort required to maintain service resulted in several potential splicing and relocation options, resolution of these options was not finalized by Verizon.

Coordinate with Verizon for the performance of the designated utility company scope of work.

END OF SECTION 01 27 00

GATE 147079A&D, 201023B 01 31 00 - 1

PROJECT MANAGEMENT AND COORDINATION

SECTION 01 31 00 - PROJECT MANAGEMENT AND COORDINATION

PART 1 - GENERAL

1.1 SUMMARY

A. This Section includes administrative provisions for coordinating demolition operations on Project including, but not limited to, the following:

1. Definitions

2. Demolition Coordination.

3. Submittals

4. Coordination Drawings.

5. Requests for Information (RFIs).

6. NPS/DSC SharePoint Project Website.

7. Project meetings.

8. Environmental Coordination.

9. Permits

B. Related Requirements:

1. Section 01 32 16 “Construction Schedule” for preparing and submitting Contractor’s construction schedule.

2. Section 01 73 40 “Execution” for procedures for field-engineering services, including establishment of benchmarks and control points.

3. Section 01 77 00 “Closeout Procedures” for coordinating closeout of the Contract.

1.2 DEFINITIONS

A. Authority Having Jurisdiction (AHJ): An AHJ is an agency that has been granted legal authority over a location, action or resource. This authority includes the ability to issue a permit or other legal permission document.

B. Contracting Officer (CO): A person with the authority to enter into, administer and/or terminate contracts and make related determinations and findings.

C. Contracting Officer Representative (COR): Also referred to as Contracting Officer Technical

Representative. A person designated by the Contracting Officer to assist in the technical monitoring or administration of a contract.

D. Permits: Are those permits obtained by the contractor based on means and methods used to execute the work. Permits are issued to the Contractor and not to the National Park Service (NPS).

E. Government Furnished Permits: Are those permits that are obtained by NPS during the design process and provided to the Contractor for compliance with the provisions throughout demolition.

These permits may address impacts to natural resources, demolition stormwater, etc.

GATE 147079A&D, 201023B 01 31 00 - 2

F. “Remove” as identified in the plans and specifications shall be defined as safe and complete demolition, removal and disposal of all items and appurtenances in a legal manner offsite as paid by the contractor at no additional cost to the Government.

1.3 DEMOLITION COORDINATION

A. Coordination: Coordinate demolition operations included in different Sections of the

Specifications to ensure efficient and orderly removal of each part of the Work. Coordinate demolition operations, included in different Sections, which depend on each other for proper removal.

1. Schedule demolition operations in sequence required to obtain the best results where demolition of one part of the Work depends on demolition of other components, before or after its own demolition.

2. Make adequate provisions to accommodate items scheduled for later demolition.

3. Properly plan demolition operations to include permit requirements. Allow enough time to execute permit provisions to maintain work schedule, site visits, inspections, and reporting deadlines.

B. Prepare memoranda for distribution to each party involved, outlining special procedures required for coordination. Include such items as required notices, reports, and list of attendees at meetings.

C. Administrative Procedures: Coordinate scheduling and timing of required administrative procedures with other demolition activities and activities of other contractors to avoid conflicts and to ensure orderly progress of the Work. Such administrative activities include, but are not limited to, the following:

1. Preparation of Contractor's Construction Schedule.

2. Preparation of the Schedule of Values.

3. Installation…