Summary_of_Items_Amendmt_2_dated_6-18-2018.xls

XLS spreadsheet 35 KB Posted

Attached to
Utility Upgrades Phase II Federal contract opportunity
Solicitation number
140P2018R0018
Issued by
Department of the Interior National Park Service National Office

About this file

Summary of item changes

View the file

Other files for this federal contract opportunity

Other files attached to Utility Upgrades Phase II, newest first.
File Type Posted
SF30_Amendment__5.pdf PDF
3-Questions_and_Answers,_6-26-18.pdf PDF
1-Amend_No.4,_Narrative.pdf PDF
2-FOVA_SF30_Amendment_4.pdf PDF
4-B08_Solit_PSP_Vol_I_PastPerf,_Amend__4.pdf PDF
FOVA_AMENDMENT_NO_3.docx DOCX document
SF_30_FOVA_Amendment_3.pdf PDF
Revised_CD.pdf PDF
Amendment_No._2_SF30.pdf PDF
5-Revised_SF1442.pdf PDF
4-Meeting_Minutes_dated_6-6-2018.pdf PDF
2-Attendance_Record_5-31-2018.pdf PDF
3-Questions_and_Answers.xlsx XLSX spreadsheet
1-SF30.pdf PDF
FOVA_174966H,_Sol_140P2018R0018.pdf PDF
7_-_Phase_1_As-Builts.pdf PDF
8_-_Fillable_CPS_for_PSP2.xls XLS spreadsheet
6_-_COV_Right-of-Way_Permit_Requirements.pdf PDF
1_-_FOVA_174966H_Final_Specs_dated_5-17-2018_.pdf PDF
3-Wage_Determination.pdf PDF
2_-_Construction_Drawings_No._389134739.pdf PDF
5_-_RFP2.pdf PDF
4_-_RFP1.pdf PDF
Show all 23

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Overview

Included in Amendment #Amendment
Item #Amendment Language:
21Reference page 133 of 150 of the Solicitation. Change the proposal submission deadline from "June 27, 2018 2:00 PM MDT" to "July 2, 2018 2:00 PM MDT". Add, "The deadline to submit questions re: the Solicitation requirements is June 22, 2018 2:00 PM MDT."
22Reference page 134 of 150 of the Solicitation. Regarding the contractor's preparation of a "preliminary project schedule", please use the following dates in lieu of the original dates provided: use a projected contract award date of August 1, 2018; use a projected notice-to-proceed date of October 1, 2018; use a contract completion date of June 27, 2019 (which is 270 calendar days after the notice-to-proceed).
23Reference attached e:file entitled "Revised Construction Drawings dated 6-13-2018.pdf" (8 pages): Substitute revised sheets 1, 3, 5, 6, 8, 12, 26, and 33 that detail revisions to select sanitary sewers and also construction staging areas.
24Reference Sheet 2 of 75 (Sub Sheet No. G01). Modify Utility Locating Requirements as follows: Delete General Note 4 in its entirety and replace with the following, “CONTRACTOR SHALL CALL 1-800-424-5555 (or 811) CLARK COUNTY UTILITIES COORDINATING COUNCIL 3 BUSINESS DAYS BEFORE DIGGING. CONTRACTOR SHALL BE RESPONSIBLE FOR LOCATING ALL NPS OWNED UTILITIES ON NPS OWNED PROPERTY. THIS INCLUDES POTHOLING AND/OR HIRING A PROFESSIONAL UNDERGROUND UTILITY LOCATION SERVICE TO LOCATE NPS OWNED UTILTIES. NPS CANNOT PROVIDE THIS LOCATING SERVICE. ASSUME ALL EXISTING UTILITIES ON NPS PROPERTY ARE NPS OWNED.”
25Reference Sheet 11 of 75 (Sub Sheet C08), Detail C "Alvord Road Pavement Section". Reduce base course thickness to 8". Add 2" of asphalt pavement with integral earthtone color (ChemSystems, Inc. or equal). Change width of road section from 12' wide to 16' wide. The final centerline alignment of the restored Alvord Road shall be the same as the historic Alvord Rd. alignment. Cooperate with NPS staff in regard to centerline layout.
26Reference Sheet 12 of 75 (Sub sheet C09). Alvord Rd., in its entirety, shall be restored to 16' wide pavement section, as per revised Sheet 11 of 75 (Sub Sheet C08), Detail C.
27Reference Sheet 13 of 75 (Sub sheet C10). Alvord Rd., in its entirety, shall be restored to 16' wide pavement section, as per revised Sheet 11 of 75 (Sub Sheet C08), Detail C.
28Reference Sheet 14 of 75 (Sub sheet C11). Alvord Rd., in its entirety, shall be restored to 16' wide pavement section, as per revised Sheet 11 of 75 (Sub Sheet C08), Detail C. Modify construction note 3 to read, "Retain extruded curb".
29Reference Sheet Sheet 18 of 75 (Sub sheet C15): Only one service line and associated meter is needed to serve Building 993. Delete east meter, meter box, DCV and lateral to eastside of 993. Adjust location of blow-off accordingly (closer to hydrant).
210Reference Sheet 29 of 75 (Sub sheet C26): Modify construction note 6 to require connection of new 6" fire service line to existing fire service line at Building 402.
211Reference Sheet 29 of 75 (Sub sheet C26): Delete installation of new 6" sewer lateral from existing manhole to Building 402. (Existing sewer will remain in use)
212Reference Sheets 29-33 of 75. (Sub sheets C26 through C30) Modify Note 5 as follows: Delete building numbers 721, 410 and 989 from this note. Modify Note 4 as follows: Add Building 410, 721, and 989 to this note.
213Reference Sheet 31 of 75 (Sub Sheet C28): Delete 6" sewer line shown on the east side of Building 748. Cap the new 6" sewer line on the south side of Building 748 at the building's centerline.
214Reference Sheet 32 of 75 (Sub Sheet C29). Modify Note 14 to require connecting the new 6" sewer lateral to the existing Building 728 sewer stub out.
215Reference Sheet 32 of 75 (Sub Sheet C29). Modify Note 13 to require connecting new 6" fire service line to existing Building 728 fire service stub out.
216Reference Sheet 60 of 75 (Sub sheet E09). There are two wooden poles to the south of Building 993. Remove approximately 90' of overhead communication lines between these two poles. Replace the overhead lines with new underground communication lines. Make the necessary connections to retain existing communication service to the Visitor Center. Minimize disruption to Visitor Center communications.
217Reference sheet 64 of 75 (Sub sheet E13). Modify trench sections as necessary to provide two 4" NPS communications conduits to the following buildings: 405, 993, 704, 733, 746, 725, 989 and 410.