Amendment No. 3 - Summary of Changes

View the file

Other files for this federal contract opportunity

Other files attached to Utility Upgrades Phase II, newest first.
File Type Posted
SF30_Amendment__5.pdf PDF
2-FOVA_SF30_Amendment_4.pdf PDF
4-B08_Solit_PSP_Vol_I_PastPerf,_Amend__4.pdf PDF
3-Questions_and_Answers,_6-26-18.pdf PDF
1-Amend_No.4,_Narrative.pdf PDF
SF_30_FOVA_Amendment_3.pdf PDF
Amendment_No._2_SF30.pdf PDF
Summary_of_Items_Amendmt_2_dated_6-18-2018.xls XLS spreadsheet
Revised_CD.pdf PDF
3-Questions_and_Answers.xlsx XLSX spreadsheet
1-SF30.pdf PDF
2-Attendance_Record_5-31-2018.pdf PDF
5-Revised_SF1442.pdf PDF
4-Meeting_Minutes_dated_6-6-2018.pdf PDF
1_-_FOVA_174966H_Final_Specs_dated_5-17-2018_.pdf PDF
8_-_Fillable_CPS_for_PSP2.xls XLS spreadsheet
6_-_COV_Right-of-Way_Permit_Requirements.pdf PDF
3-Wage_Determination.pdf PDF
2_-_Construction_Drawings_No._389134739.pdf PDF
5_-_RFP2.pdf PDF
4_-_RFP1.pdf PDF
FOVA_174966H,_Sol_140P2018R0018.pdf PDF
7_-_Phase_1_As-Builts.pdf PDF
Show all 23

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT NO. 3 - Summary of Changes

Question

Note 5, There is not a revised C08 to go with the changes to detail C, can we anticipate a new drawing?

-Note 6 – 8; These notes are changing the roadway width for Alvord Rd from 12’ to 16’ without new drawings to show the change. How are we to determine impacts to landscaped areas, existing curbs, existing asphalt road connections, etc. without new drawings showing the additional roadway width? Can we anticipate new drawings detailing this change?

Answer

Note 5, There is not a revised C08 to go with the changes to detail C, can we anticipate a new drawing?

Answer: Drawing C08 and associated detail C will not be revised prior to bid time. Please bid the revised Alvord Rd. section as described in the amendment, that being 16' wide with 8" of base course and 2" of asphalt extended across the full 16' width.

-Note 6 – 8; These notes are changing the roadway width for Alvord Rd from 12’ to 16’ without new drawings to show the change. How are we to determine impacts to landscaped areas, existing curbs, existing asphalt road connections, etc. without new drawings showing the additional roadway width? Can we anticipate new drawings detailing this change?

Answer: Revised plans for Alvord Rd. will not be provided prior to bid time. Please bid using the revised Alvord Rd. width = 16' and the same centerline, Please bid assuming logical field adjustments will need to be made to accommodate the wider road width and same design intent regarding roadside restoration, etc.

Change to the Submit date of Proposals from July 2, 2018, 2:00 pm MDT to July 3rd, 2018, 2:00 pm MDT. To allow for proposals to be received other than on a Monday when using courier services ( e.g.) FedEx or UPS.