FOVA_AMENDMENT_NO_3.docx
DOCX document 14 KB Posted
- Attached to
- Utility Upgrades Phase II Federal contract opportunity
- Solicitation number
- 140P2018R0018
About this file
Amendment No. 3 - Summary of Changes
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| SF30_Amendment__5.pdf | ||
| 2-FOVA_SF30_Amendment_4.pdf | ||
| 4-B08_Solit_PSP_Vol_I_PastPerf,_Amend__4.pdf | ||
| 3-Questions_and_Answers,_6-26-18.pdf | ||
| 1-Amend_No.4,_Narrative.pdf | ||
| SF_30_FOVA_Amendment_3.pdf | ||
| Amendment_No._2_SF30.pdf | ||
| Summary_of_Items_Amendmt_2_dated_6-18-2018.xls | XLS spreadsheet | |
| Revised_CD.pdf | ||
| 3-Questions_and_Answers.xlsx | XLSX spreadsheet | |
| 1-SF30.pdf | ||
| 2-Attendance_Record_5-31-2018.pdf | ||
| 5-Revised_SF1442.pdf | ||
| 4-Meeting_Minutes_dated_6-6-2018.pdf | ||
| 1_-_FOVA_174966H_Final_Specs_dated_5-17-2018_.pdf | ||
| 8_-_Fillable_CPS_for_PSP2.xls | XLS spreadsheet | |
| 6_-_COV_Right-of-Way_Permit_Requirements.pdf | ||
| 3-Wage_Determination.pdf | ||
| 2_-_Construction_Drawings_No._389134739.pdf | ||
| 5_-_RFP2.pdf | ||
| 4_-_RFP1.pdf | ||
| FOVA_174966H,_Sol_140P2018R0018.pdf | ||
| 7_-_Phase_1_As-Builts.pdf |
Show all 23
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT NO. 3 - Summary of Changes
Question
Note 5, There is not a revised C08 to go with the changes to detail C, can we anticipate a new drawing?
-Note 6 – 8; These notes are changing the roadway width for Alvord Rd from 12’ to 16’ without new drawings to show the change. How are we to determine impacts to landscaped areas, existing curbs, existing asphalt road connections, etc. without new drawings showing the additional roadway width? Can we anticipate new drawings detailing this change?
Answer
Note 5, There is not a revised C08 to go with the changes to detail C, can we anticipate a new drawing?
Answer: Drawing C08 and associated detail C will not be revised prior to bid time. Please bid the revised Alvord Rd. section as described in the amendment, that being 16' wide with 8" of base course and 2" of asphalt extended across the full 16' width.
-Note 6 – 8; These notes are changing the roadway width for Alvord Rd from 12’ to 16’ without new drawings to show the change. How are we to determine impacts to landscaped areas, existing curbs, existing asphalt road connections, etc. without new drawings showing the additional roadway width? Can we anticipate new drawings detailing this change?
Answer: Revised plans for Alvord Rd. will not be provided prior to bid time. Please bid using the revised Alvord Rd. width = 16' and the same centerline, Please bid assuming logical field adjustments will need to be made to accommodate the wider road width and same design intent regarding roadside restoration, etc.
Change to the Submit date of Proposals from July 2, 2018, 2:00 pm MDT to July 3rd, 2018, 2:00 pm MDT. To allow for proposals to be received other than on a Monday when using courier services ( e.g.) FedEx or UPS.