Sol_140P1221R0014_Amd_0003.pdf

PDF 88 KB Posted

Attached to
ROMO HQE WATERLINE REHAB PHASE 7 & 8
Solicitation number
140P1221R0014
Issued by

About this file

This is an amendment to a solicitation for the ROMO HQE Waterline Rehab Phase 7 & 8 project. The amendment provides revised specifications, price schedule, and wage determinations for heavy and highway construction. It also includes questions and answers from potential offerors.

The solicitation is for construction services to rehabilitate waterlines in phases 7 and 8 of the ROMO HQE project. The National Park Service Intermountain Region is the contracting agency. The amendment provides revised specifications, a revised price schedule with minor quantity adjustments to three line items, and updated wage determinations applicable to heavy and highway construction. It also attaches a question and answer document from an earlier date. The period of performance for any resulting contract is from May 6, 2022 to February 20, 2023.

View the file

Other files

File Type Posted
B09_0040548566_Soliciation_Amendment_4__Specs_Revised_2022Mar3_152_pgs_0004.pdf PDF
B09_0040548566_Soliciation_Amendment_4__DWGs_final_20220228_0004.pdf PDF
Sol_140P1221R0014_Amd_0004.pdf PDF
B09_0040548566_Soliciation_Amendment_4__Spec-Draw-Price_2022Mar4_0004.pdf PDF
B09_0040548566_Soliciation_Amendment_4__Price_Schedule_Rev_2022Mar3_0004.xlsx XLSX spreadsheet
Wage_Determination_Highway_-_Ashalt_Classifications___Rates__CO20220014_2022Jan07_6_pgs_0003.pdf PDF
Amendment_3_Q_A_0003.pdf PDF
Specs_Revised_2022Feb23_151_pgs_0003.pdf PDF
Solicitation_Price_Schedule_Rev_2022Feb23_0003.xlsx XLSX spreadsheet
Wage_Determination_Heavy_CO20220002_2022Feb18_pgs6_0003.pdf PDF
B09_0040548566_Soliciation_Amendment_3_140P1221R0014_0003.pdf PDF
B11_0040548566_Site_Visit_Site_Visit_Form_0002.pdf PDF
ROMO_240839_306571_DWGs_final_0002.pdf PDF
Sol_140P1221R0014_Amd_0002.pdf PDF
Sol_140P1221R0014_Amd_0001.pdf PDF
B08_0040548566_Solicitation_140P1221R0014_SF1442_0001.pdf PDF
B08_0040548566_Solicitation_Specs_Revised_2022Jan25_151_pgs.pdf PDF
B03_0040548566_Wage_Determination_Heavy_CO20220002_2022Jan28_7_pgs.pdf PDF
B08_0040548566_Solicitation_Price_Schedule.xlsx XLSX spreadsheet
B08_0040548566_Solicitation_Certification_of_Vaccination_Form.pdf PDF
B08_0040548566_Solicitation_Past_Performance_Question.docx DOCX document
B08_0040548566_Solicitation_Vaccination_Certification_Notification.pdf PDF
Sol_140P1221R0014.pdf PDF
B08_0040548566_Solicitation_GenRefs.doc DOC document
B08_0040548566_Solicitation_Drawings_Revised_2021July26_24_pgs_.pdf PDF
B08_0040548566_Solicitation_LmtOnSubconRpt.xlsx XLSX spreadsheet
B08_0040548566_Solicitation_Bid_Bond_SF24-16d.pdf PDF
Show all 27

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

(x)

140P1221R0014 x x

1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE

RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR

OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

x

PIL

Lakewood CO 80228 12795 W Alameda Parkway NPS, IMR - Lakewood MABO

02/09/20220003

13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

FACILITY CODE CODE

10B. DATED (SEE ITEM 13)

10A. MODIFICATION OF CONTRACT/ORDER NO.

9B. DATED (SEE ITEM 11)

9A. AMENDMENT OF SOLICITATION NO.

CODE

8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)

7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY

PAGE OF PAGES

4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)

1. CONTRACT ID CODE

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

02/09/2022

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority) appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

E. IMPORTANT: Contractor is not is required to sign this document and return __________________ copies to the issuing office.

ORDER NO. IN ITEM 10A.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

The purpose of this amendment 3 is to provide Q&A, revised spec, revised price schedule, revised WD Heavy, and to add WD Highway for asphalt classification & rates only. All other classifications are to be taken from the revised WD Heavy.

On the contract price schedule, line items 1j, 1k, and 1l had a small quantity change (+/-

1) and the only thing that was changed in the specs was in the definition of contract line items, 1j under Definition of Contract Line Items.

Attachments:

Q&A (Dated: 2/24/2022, 1 pg., pdf)

Specification (Revised 2/23/2022 151 pgs, pdf)

Continued ...

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)

15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED

(Signature of person authorized to sign) (Signature of Contracting Officer)

Sherry Packard

STANDARD FORM 30 (REV. 11/2016)

Prescribed by GSA FAR (48 CFR) 53.243

Previous edition unusable

Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .

ITEM NO. SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

NAME OF OFFEROR OR CONTRACTOR

2 167

CONTINUATION SHEET

REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF

(A) (B) (C) (D) (E) (F)

140P1221R0014/0003

Price Schedule Revised (revised 2/23/2022, 1 pg.

Excel)

Wage Determination_Heavy_CO20220002 (Revised

2022Feb18 pgs. 6)

B03 0040548566_Wage Determination_Highway -

Ashalt Classifications & Rates Only _CO20220014

2022Jan07_6 pgs.

Period of Performance: 05/06/2022 to 02/20/2023

NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)

Sponsored by GSA

FAR (48 CFR) 53.110

File details come from the government source that posted it. Updated .