This document is a price schedule for a federal solicitation to rehabilitate waterlines at Rocky Mountain National Park. The National Park Service is seeking offers to complete work on Phases 7 and 8 of the project, including installing over 5,000 linear feet each of 6-inch and 4-inch HDPE water lines, 23 gate valves, 4 air release/vacuum valve vaults, 9 fire hydrants, and 31 small and 6 large HDPE service laterals. Offerors must provide pricing for all base line items as well as optional items which include replacing existing air release/vacuum valve vaults and completing site improvements at an RV site. Pricing should be listed by contract line item number for both unit and lump sum items. The total proposed price must include amounts for both the base work and all option line items.
View the file
Other files
Show all 27
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Price Schedule
| Contract Price Schedule | |||||
| National Park Service (NPS) | |||||
| Solicitation Number: 140P1221R0014 | |||||
| ROMO - PMIS #240839 & 306571 | |||||
| Project Title: | Waterline Rehab Phase 7 & 8 | ||||
| Notice: Offerors are required to submit, at minimum, an offer that conforms to the solicitation documents with pricing for Base line items and all | |||||
| option line items. Failure to do so may render the proposal unacceptable. On lump-sum line items, provide the total price only. For all unit-priced | |||||
| line items, provide the unit price and the extended total price. If no specific line item exists for a portion of the work, include the costs in a related | |||||
| item. In case of error in calculation of extended prices, the unit price governs. In case of error in summation, the total of the corrected amounts | |||||
| govern. Round totals and extended prices to whole dollars. Refer to solicitation section “H” for additional information regarding contract options | |||||
| Contract Line Item Number (CLIN) | Contract Line Item (CLI) Title | Quantity | Unit of Measure | Unit Price | Total Price |
| 1 | Base Contract | ||||
| 1a | Mobilization and Demobilization | 1 | LS | ||
| 1b | Demolition | 1 | LS | ||
| 1c | Archeological Monitoring and Report | 1 | LS | ||
| 1d | 6-inch HDPE Water Line – Open Trench | 5280 | LF | ||
| 1e | 4-inch HDPE Water Line – Open Trench | 800 | LF | ||
| 1f | Gate Valve | 23 | EA | ||
| 1g | Air Release/Vacuum Valve Vault | 4 | EA | ||
| 1h | Fire Hydrant | 9 | EA | ||
| 1i | Connect New 6-inch to Existing Water Line | 4 | EA | ||
| 1j | 2-Inch HDPE Service Lateral with Shut Off Valve and 2-inch Pump Out Assembly | 31 | EA | ||
| 1k | 4-Inch HDPE Service Lateral with Shut Off Valve and 2-inch Pump Out Assembly | 6 | EA | ||
| 1l | Frostproof Water Hydrant | 22 | EA | ||
| 1m | Pavement Patching Asphalt | 7791 | SF | ||
| 1n | Gravel Roadway Patching | 47247 | SF | ||
| 1o | Cast in Place Concrete – Flatwork – Concrete Replacement | 41 | SF | ||
| 1p | Rock Excavation | 7826 | BCY | ||
| 1q | Stabilization and Seeding | 8850 | SY | ||
| 1r | Utility Crossings | 115 | EA | ||
| TOTAL BASE PRICE (Subline Item Number 1a-1r) --------------------------------------------------------------------------------- | $0.00 | ||||
| 2 | OPTION A, Remove and Replace Existing Air Release/Vacuum Valve Vault | 3 | EA | $0.00 | |
| 3 | OPTION B, Site Improvements – RV Site P | 1 | LS | - 0 | |
| TOTAL PRICE FOR ALL OPTIONS (Contract Line Item Number 2 through 3) ----------------------------------------------------------- | $0.00 | ||||
| TOTAL PROPOSED PRICE - BASE PLUS ALL OPTIONS (Contract Line Item Number 1 through 3) -------------------------- | $0.00 | ||||
| All measurement and payment information is included in Division 01 Specifications Section 01 27 00 Definition of Contract Line Items. |
File details come from the government source that posted it. Updated .