B11_0040548566_Site_Visit_Site_Visit_Form_0002.pdf

PDF 169 KB Posted

Attached to
ROMO HQE WATERLINE REHAB PHASE 7 & 8
Solicitation number
140P1221R0014
Issued by

About this file

This document contains records from a site inspection tour and pre-bid conference for a federal solicitation. The solicitation is for the ROMO Waterline Rehab Phases 7 & 8 project located at Rocky Mountain National Park. The meeting took place on February 17, 2022 at the Beaver Meadows Visitor Center and was facilitated by the Contracting Officer's Representative. Questions asked and answers provided covered requirements for equipment inspections, contractor lodging and waste disposal, as well as maintenance of vehicle access during construction and tree removal. Disturbance areas and restoration requirements were also discussed. Bidders in attendance acknowledged receipt of notice that only the Contracting Officer may issue changes to the solicitation.

View the file

Other files

File Type Posted
B09_0040548566_Soliciation_Amendment_4__Specs_Revised_2022Mar3_152_pgs_0004.pdf PDF
B09_0040548566_Soliciation_Amendment_4__DWGs_final_20220228_0004.pdf PDF
Sol_140P1221R0014_Amd_0004.pdf PDF
B09_0040548566_Soliciation_Amendment_4__Spec-Draw-Price_2022Mar4_0004.pdf PDF
B09_0040548566_Soliciation_Amendment_4__Price_Schedule_Rev_2022Mar3_0004.xlsx XLSX spreadsheet
Wage_Determination_Highway_-_Ashalt_Classifications___Rates__CO20220014_2022Jan07_6_pgs_0003.pdf PDF
Amendment_3_Q_A_0003.pdf PDF
Specs_Revised_2022Feb23_151_pgs_0003.pdf PDF
Solicitation_Price_Schedule_Rev_2022Feb23_0003.xlsx XLSX spreadsheet
Wage_Determination_Heavy_CO20220002_2022Feb18_pgs6_0003.pdf PDF
Sol_140P1221R0014_Amd_0003.pdf PDF
B09_0040548566_Soliciation_Amendment_3_140P1221R0014_0003.pdf PDF
ROMO_240839_306571_DWGs_final_0002.pdf PDF
Sol_140P1221R0014_Amd_0002.pdf PDF
Sol_140P1221R0014_Amd_0001.pdf PDF
B08_0040548566_Solicitation_140P1221R0014_SF1442_0001.pdf PDF
B08_0040548566_Solicitation_Specs_Revised_2022Jan25_151_pgs.pdf PDF
B03_0040548566_Wage_Determination_Heavy_CO20220002_2022Jan28_7_pgs.pdf PDF
B08_0040548566_Solicitation_Price_Schedule.xlsx XLSX spreadsheet
B08_0040548566_Solicitation_Certification_of_Vaccination_Form.pdf PDF
B08_0040548566_Solicitation_Past_Performance_Question.docx DOCX document
B08_0040548566_Solicitation_Vaccination_Certification_Notification.pdf PDF
Sol_140P1221R0014.pdf PDF
B08_0040548566_Solicitation_GenRefs.doc DOC document
B08_0040548566_Solicitation_Drawings_Revised_2021July26_24_pgs_.pdf PDF
B08_0040548566_Solicitation_LmtOnSubconRpt.xlsx XLSX spreadsheet
B08_0040548566_Solicitation_Bid_Bond_SF24-16d.pdf PDF
Show all 27

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

UNITED STATES

DEPARTMENT OF THE INTERIOR

SITE INSPECTION TOUR/PREBID CONFERENCE RECORD

_______ Initials Form modified by JC 8/2014 Page # ____ of _______

1. Solicitation/Reference No.: 140P1221R0014

4. Meeting Place: Beaver Meadows Visitor Center, Rocky Mountain National Park, Estes Park, CO 80517

2. Project Title: ROMO Waterline Rehab Phases 7 & 8

3. Date & Time: 10:00 am - 2/17/2022 5. Facilitated by Name and Title: William McHugh, Civil Engineer/COR

NOTICE

No changes to the solicitation are binding unless issued by the Contracting Officer as a formal written solicitation amendment.

1. Attended and Notice Acknowledged by: (Use continuation form as needed)

2. Questions asked and responses give:

1. Will equipment be required to be inspected daily?

a. No, equipment must be inspected before entering the park and as long as it remains in the park it does not have to be re-inspected. If it leaves the park, it will need to be inspected again before entering.

2. Will the park have any lodging for contractors?

a. No, no lodging within the park will be provided. Contractors are responsible for finding their own lodging if needed.

3. Does the Park want to keep any of the construction waste?

a. No, unless the drawings specifically call out to “salvage” items, all waste much be disposed of properly as defined in the specs.

4. Do the RV sites have a concrete pad?

a. No, the RV sites are mostly gravel with some wood framing the site. Any disturbance to the sites must be restored to pre-construction conditions.

5. To maintain vehicle access on chief’s head road, can work and disturbance go off-road?

a. All work and disturbance must remain in the defined Limits of Disturbance as shown on the contract drawings. On chief’s head road, this does include an area off the road. As stated in the contract documents, vehicle access must be maintained where noted. This is especially critical on chief’s head road as it is the only road that provides access to park and regional wildland firefighter buildings and access must be maintained for emergency purposes. This includes some oversized firefighting vehicles.

6. Can tree limbs be removed if they are in the way?

a. See specification section 01 11 00 – 1.8.D

3. Was a complete site inspection tour conducted? Yes No (If “No”, explain – Use Continuation form as needed

By (Name) Title Date