Attch_13_Bid_Schedule_Revised_0002.xlsx

XLSX spreadsheet 16 KB Posted

Attached to
LABARGE WATERSHED Federal contract opportunity
Solicitation number
140L6222R0009
Issued by
Department of the Interior Bureau of Land Management Wyoming Region

About this file

This document contains a bid schedule for a federal contract solicitation to perform watershed restoration work for two sites within the LaBarge Watershed. The bid schedule outlines estimated quantities and unit costs for various work items including general conditions, earthwork, culvert installation in various sizes, crushed base material, concrete block mats, erosion control measures, reclamation seeding, and construction oversight. It requests unit pricing and extended totals for both the Wildcat Canyon and Upper Bird Draw culvert replacement projects. Additional line items cover bonds, insurance, profit, overhead, and contingencies. Upon award, the contractor will perform restoration at the two locations which include installing new culverts, addressing erosion issues, and re-establishing native vegetation. The associated federal contract opportunity provides further details, identifying the solicitation number, name of the watershed project, that it is a solicitation type, and that the contracting agency is the Bureau of Land Management Wyoming Region.

View the file

Other files for this federal contract opportunity

Show all 15

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sheet1

Solicitation 140L6222R0009 LaBarge Watershed Restoration
Bid Schedule Revised
BLM-38 Wildcat Canyon Culvert
Item NumberDescriptionEstimated Quantity*UnitUnit CostTotal Cost*Quantities provided are purely estimates and equitable adjustments will only be considered
1General Conditions1Lump Sumin accordance with FAR clause 52.211-18 Variation in Estimated Quantity
2Mobilization/Demobilization*1Lump Sum
3Earthwork8070Cubic Yards*Both sites are located close to each other, so there is only expected to be one mobilization/demobilization
4Remove and Dispose Exisitng Culvert1Lump Sum
5Crushed Base Purchase/Install7Cubic Yards
612-inch Culvert Materials and Installation60Linear Feet
718-inch Culvert Materials and Installation40Linear Feet
866-inch Culvert Materials and Installation60Linear Feet
9CMP Flared End Section1Lump Sum
10Concrete Block Mat Materials and Installation3200Square Feet
11Energy Dissipation Unit Materials and Installation18Each
12Roughness Treatment3.34Acres
13Reclamation Seeding3.34Acres
14Construction Oversight (Staking, Oversight, As-Builts, etc.)1Lump Sum
15Monitoring and Maintenance1Lump Sum
Wildcat Canyon Subtotal:
BLM-39 Upper Bird Draw Culvert
Item NumberDescriptionEstimated Quantity*UnitUnit CostTotal Cost
1General Conditions1Lump Sum
2Clearing and Grubbing1Lump Sum
3Storm Water Control1Lump Sum
4Construction Staking1Lump Sum
5Materials Testing1Lump Sum
6Remove and Dispose Existing Pipe1Lump Sum
7CMP Arch Pipe 60" x 46"48Linear Feet
8CMP Flared End Section1Lump Sum
9Crushed Base Purchase/Install10Cubic Yards
10Seeding1,130Square Yards
11Concrete Block Mat Materials and Installation1,725Square Feet
12Energy Dissipation Unit Materials and Installation300Each
13Erosion Control Blanket310Square Yards
14Excavation and Grading for Erosion Repair396Cubic Yards
Upper Bird Draw Subtotal:
Contractor Fees
Item NumberDescriptionEstimated Quantity*UnitUnit CostTotal Cost
1Bonds1Lump Sum
2Insurance1Lump Sum
3Profit1Lump Sum
4Overhead1Lump Sum
5Contingency Costs1Lump Sum
Fees Subtotal:
Project Grand Total:

File details come from the government source that posted it. Updated .